I applied via Naukri.com and was interviewed in Dec 2024.Β There were 2 interview rounds.
Land acquisition is deparant for karnataka and tsr, agriment, govt liaison, public relation, work salved,
Yes land acquisition test
The commissioning process of a PV solar plant involves testing, adjusting, and optimizing the system to ensure it is functioning properly.
Testing the electrical components and connections to ensure they are working correctly
Adjusting the system settings to maximize efficiency and output
Optimizing the performance of the solar panels to achieve the desired energy production
Checking for any potential issues or malfunction
Transformer types of testing include routine tests, type tests, and special tests to ensure proper functioning and safety.
Routine tests include insulation resistance, turns ratio, and polarity tests.
Type tests are conducted on a prototype to verify design parameters like temperature rise and short-circuit withstand.
Special tests may include impulse voltage, partial discharge, and noise level tests.
Testing ensures trans...
I applied via Recruitment Consulltant and was interviewed in Oct 2024.Β There were 2 interview rounds.
Land aquisation for aptitude test
Legal and liaison department work for GD
I have 5 years of experience working in the solar industry, including project management and team leadership.
Managed solar installation projects from start to finish
Led a team of technicians and engineers in implementing solar solutions
Developed and maintained relationships with suppliers and clients
Stayed updated on industry trends and regulations
Implemented cost-saving measures to improve project efficiency
Rays Power Infra interview questions for popular designations
I applied via LinkedIn and was interviewed before Jun 2023.Β There were 2 interview rounds.
The critical path is the longest sequence of tasks in a project that must be completed on time in order for the project to finish on schedule.
Identifying the critical path helps in determining the minimum time needed to complete a project.
It consists of tasks that have zero slack or float, meaning any delay in these tasks will delay the entire project.
Activities on the critical path are often marked with a double line ...
I will plan a 50 Mwp project by conducting feasibility studies, creating a detailed project timeline, securing necessary permits, sourcing materials and contractors, and implementing a quality control plan.
Conduct feasibility studies to assess site suitability and potential challenges
Create a detailed project timeline outlining key milestones and deadlines
Secure necessary permits and approvals from local authorities
Sou...
MSP (Microsoft Project) is a project management software developed by Microsoft, while Primavera is a project management software developed by Oracle.
MSP is developed by Microsoft, while Primavera is developed by Oracle.
MSP is more commonly used for smaller projects, while Primavera is preferred for larger and more complex projects.
MSP is known for its user-friendly interface and ease of use, while Primavera is known f...
Get interview-ready with Top Rays Power Infra Interview Questions
I applied via Approached by Company and was interviewed before Jul 2023.Β There was 1 interview round.
A step-up transformer is used to increase the voltage in an electrical circuit.
Step-up transformers have more turns in the secondary coil than in the primary coil.
They work based on the principle of electromagnetic induction.
The primary coil is connected to a power source with a lower voltage, while the secondary coil is connected to the load.
The increased voltage in the secondary coil is proportional to the ratio of t...
I applied via Referral and was interviewed before May 2020.Β There were 4 interview rounds.
Top trending discussions
based on 16 interviews
Interview experience
based on 159 reviews
Rating in categories
Electrical Engineer
28
salaries
| βΉ1.6 L/yr - βΉ5.8 L/yr |
Assistant Manager
23
salaries
| βΉ3.8 L/yr - βΉ9.8 L/yr |
Senior Engineer
16
salaries
| βΉ4 L/yr - βΉ7.7 L/yr |
Engineer
12
salaries
| βΉ3 L/yr - βΉ6 L/yr |
Project Engineer
11
salaries
| βΉ2 L/yr - βΉ6.3 L/yr |
Adani Green Energy
Azure Power
Tata Power Solar
Hero Future Energies