The progress percentage can be negative if the actual progress is less than the planned progress.
Negative variance indicates that the actual progress is behind the planned progress.
The updated schedule end date may not be changed if there are mitigating actions or recovery plans in place.
Factors such as resource constraints, delays in procurement, or unexpected issues can contribute to negative variance without changin
Yes, I loaded the schedule with resources.
I ensured that all tasks in the schedule had the necessary resources assigned to them.
I considered the availability and skills of the resources when assigning them to tasks.
I regularly reviewed and updated the schedule to ensure that resources were allocated efficiently.
For example, in a construction project, I loaded the schedule with labor, equipment, and materials needed for
Top trending discussions
I applied via Approached by Company and was interviewed in Sep 2022. There were 3 interview rounds.
Delete removes an activity from the project, while dissolve removes a relationship between activities.
Delete removes an activity from the project and all its relationships with other activities.
Dissolve removes a relationship between two activities, but the activities themselves remain in the project.
Deleting an activity can have a cascading effect on the rest of the project, while dissolving a relationship only affect...
I prepare programme by identifying objectives, breaking them down into tasks, assigning resources and setting timelines.
Identify objectives and goals
Break down objectives into smaller tasks
Assign resources and responsibilities to team members
Set timelines and deadlines for each task
Regularly review and update the programme to ensure progress is on track