To calculate a BBS for footing, you need to determine the size and spacing of reinforcement bars required for the footing construction.
Calculate the total area of the footing
Determine the design requirements for the footing (such as load capacity)
Select the appropriate size and spacing of reinforcement bars based on design requirements
Calculate the total length of reinforcement bars needed for the footing
Prepare a deta...
Nominal cover for pipeline refers to the minimum thickness of concrete cover over the reinforcement in a pipeline.
Nominal cover is typically specified in project specifications or design drawings.
The purpose of nominal cover is to protect the reinforcement from corrosion and provide durability to the pipeline.
The nominal cover for pipelines can vary depending on factors such as the type of pipeline, environmental condi...
Top trending discussions
I applied via Naukri.com and was interviewed in Nov 2023. There was 1 interview round.
posted on 22 Nov 2023
I applied via Campus Placement and was interviewed in Oct 2023. There were 2 interview rounds.
I applied via Naukri.com and was interviewed in Nov 2023. There was 1 interview round.
based on 2 interviews
Interview experience
based on 5 reviews
Rating in categories
Senior Engineer
42
salaries
| ₹3.5 L/yr - ₹7.8 L/yr |
Site Engineer
30
salaries
| ₹2.6 L/yr - ₹6 L/yr |
Civil Site Engineer
23
salaries
| ₹2.2 L/yr - ₹5 L/yr |
Junior Engineer
14
salaries
| ₹2 L/yr - ₹4.2 L/yr |
Civil Engineer
14
salaries
| ₹2 L/yr - ₹9.8 L/yr |
Tata Projects
Larsen & Toubro Limited
Hindustan Construction Company
Shapoorji Pallonji Group