I applied via Referral and was interviewed before Jan 2022. There were 3 interview rounds.
IS code for TMT bar & RMC plant specification is IS 1786:2008 and IS 4926:2003 respectively.
IS 1786:2008 specifies the requirements for high strength deformed steel bars and wires for concrete reinforcement.
IS 4926:2003 specifies the requirements for ready-mixed concrete (RMC) plant, including materials, mixing, transporting, and testing.
Both codes are important for ensuring quality and safety in construction projects.
BIS code is a standard set by Bureau of Indian Standards while IS code is a specific code within the BIS code.
BIS code covers a wide range of standards for various industries while IS code is specific to Indian Standards for a particular product or process.
IS code is a subset of BIS code and is used for quality control and assurance purposes.
For example, BIS code for cement covers various aspects like composition, pack...
NDT tests are non-destructive methods used to evaluate the properties of materials without causing damage.
NDT tests include methods like ultrasonic testing, radiography, magnetic particle testing, and liquid penetrant testing.
The criteria for NDT tests depend on the type of test being performed and the material being tested.
For example, in ultrasonic testing, the criteria may include the size and location of any defect...
Top trending discussions
I applied via Campus Placement and was interviewed in Dec 2024. There was 1 interview round.
The standard dimensions of a brick are 3 5/8 inches x 2 1/4 inches x 8 inches.
Standard brick size is 3 5/8 inches x 2 1/4 inches x 8 inches
Bricks can also come in different sizes based on region or purpose
Common brick sizes include modular, jumbo, and queen
The water-cement ratio is the ratio of the weight of water to the weight of cement used in a concrete mix.
It is a crucial factor in determining the strength and durability of concrete.
A lower water-cement ratio results in stronger and more durable concrete.
The typical range for water-cement ratio is between 0.4 to 0.6.
Excessive water in the mix can lead to lower strength and durability of concrete.
Heat of hydration is the heat released when water is added to cement during the chemical reaction of hydration.
Heat of hydration is the heat released when water is added to cement during the chemical reaction of hydration.
It is an exothermic reaction, meaning it releases heat.
The heat of hydration is important to consider in concrete construction to prevent cracking and ensure proper curing.
Higher heat of hydration can...
Curing is the process of maintaining adequate moisture and temperature in concrete to ensure proper hydration and strength development.
Curing helps prevent cracking and ensures the concrete reaches its full strength potential.
Common curing methods include water curing, membrane curing, and curing compounds.
Proper curing typically lasts for at least 7 days, but can vary depending on the type of concrete mix and environm
Footing is the bottommost part of a foundation that distributes the load of the structure to the soil.
Footing is typically made of concrete and is wider than the foundation walls to provide stability.
Foundations are the lower portion of a building structure that transfers the load to the soil.
There are different types of foundations such as shallow foundations (like spread footings) and deep foundations (like piles).
One way slab is supported on two opposite sides while two way slab is supported on all four sides.
One way slab is designed to carry loads along one direction only
Two way slab is designed to carry loads along both directions
One way slab is supported on two opposite sides
Two way slab is supported on all four sides
posted on 20 Sep 2024
I applied via Recruitment Consulltant and was interviewed in Aug 2024. There was 1 interview round.
The finance condition of our company is stable with a healthy cash flow and strong financial performance.
Our company has a positive cash flow, allowing us to meet financial obligations and invest in future projects.
We have a strong financial performance, with consistent profits and revenue growth.
We maintain a healthy balance sheet, with manageable debt levels and sufficient liquidity.
Our financial condition allows us ...
The process of tower foundation involves several steps that are carried out day by day.
Day 1: Site preparation and layout survey
Day 2: Excavation for foundation
Day 3: Reinforcement placement
Day 4: Formwork installation
Day 5: Concrete pouring
Day 6: Curing of concrete
Day 7: Removal of formwork
Day 8: Quality inspection and testing
Day 9: Backfilling around the foundation
Day 10: Final inspection and documentation
Cube mould size refers to the dimensions of the mould used to cast concrete cubes for testing.
Cube moulds are typically made of steel or cast iron.
The most common cube mould size used in construction is 150mm x 150mm x 150mm.
Other sizes like 100mm x 100mm x 100mm or 200mm x 200mm x 200mm may also be used depending on the requirements.
Cube moulds have removable base plates to facilitate easy removal of the hardened conc...
Quality points at the pouring time of concrete include proper mix proportions, correct placement, adequate compaction, and appropriate curing.
Proper mix proportions ensure the desired strength and durability of the concrete.
Correct placement involves placing the concrete in the designated location without segregation or excessive bleeding.
Adequate compaction ensures that there are no voids or air pockets in the concret...
Sloped cutting refers to the excavation of soil or rock at an inclined angle to create a slope or incline.
Sloped cutting is commonly used in construction projects to create roadways, railways, or canals on hilly terrains.
It involves removing the excess material from a higher elevation to a lower elevation, forming a sloping surface.
The angle of the slope is determined based on factors such as soil stability, desired gr...
based on 1 interview
Interview experience
Assistant Manager
323
salaries
| ₹7.5 L/yr - ₹16.7 L/yr |
Senior Engineer
294
salaries
| ₹5.5 L/yr - ₹13 L/yr |
Deputy Manager
192
salaries
| ₹8.5 L/yr - ₹22 L/yr |
Engineer
173
salaries
| ₹3.1 L/yr - ₹9 L/yr |
Manager
152
salaries
| ₹8 L/yr - ₹24 L/yr |
Thermax Limited
BHEL
Larsen & Toubro Limited
Tata Power