I applied via Naukri.com and was interviewed before May 2021. There were 2 interview rounds.
posted on 16 Jun 2022
I applied via Campus Placement and was interviewed before Jun 2021. There was 1 interview round.
I applied via Company Website and was interviewed in Feb 2020. There was 1 interview round.
I appeared for an interview before May 2020.
To fix the rate of 1 cum metre RCC for M10 and M20, factors like material cost, labor cost, equipment cost, and overheads need to be considered.
Determine the cost of materials required for 1 cum metre RCC for M10 and M20
Calculate the labor cost involved in the construction process
Consider the cost of equipment required for the construction process
Include overheads like transportation, insurance, and taxes
Compare the ra...
I applied via Company Website and was interviewed in Dec 2020. There were 3 interview rounds.
I applied via Approached by Company and was interviewed before Jan 2022. There were 3 interview rounds.
I applied via Approached by Company and was interviewed before Sep 2021. There were 3 interview rounds.
posted on 13 Jun 2021
I applied via Referral and was interviewed in Dec 2020. There were 3 interview rounds.
posted on 24 Mar 2020
I applied via Naukri.com and was interviewed in Feb 2020. There were 3 interview rounds.
I have 5 years of experience in the Oil & Gas sector, specifically in the Operations department.
I have worked in the Operations department of an oil and gas company for 5 years.
During my time in the sector, I have gained extensive knowledge of the operational processes and procedures involved in oil and gas production.
I have successfully managed various projects related to drilling, production optimization, and cost re...
Preparation of RA bill involves gathering all relevant information and creating a detailed invoice for goods or services provided.
Gather all necessary information such as product or service details, quantity, and pricing
Create a detailed invoice with clear descriptions and itemized costs
Include any applicable taxes or discounts
Ensure accuracy and completeness of the bill before submitting to the client
Follow up with th
posted on 25 Jun 2024
I applied via Company Website and was interviewed in May 2024. There were 2 interview rounds.
Reconciliation process of raw material involves comparing the physical inventory with the recorded inventory to identify discrepancies.
Verify the accuracy of raw material receipts and usage records
Compare physical inventory counts with the recorded inventory levels
Investigate and resolve any discrepancies found
Update inventory records accordingly
Implement controls to prevent future discrepancies
based on 4 reviews
Rating in categories
Assistant Manager
82
salaries
| ₹2.4 L/yr - ₹8.4 L/yr |
Deputy Manager
74
salaries
| ₹4.7 L/yr - ₹14 L/yr |
Manager
73
salaries
| ₹7.3 L/yr - ₹25 L/yr |
Senior Manager
42
salaries
| ₹11 L/yr - ₹29.2 L/yr |
Deputy General Manager
19
salaries
| ₹13 L/yr - ₹45.5 L/yr |
Larsen & Toubro Limited
L&T Construction
Tata Projects
Megha Engineering & Infrastructures