I applied via Walk-in and was interviewed in Feb 2023. There were 3 interview rounds.
Base line schedule is the original project plan, while updates are revisions made to the plan. PMC works involve monitoring and controlling project activities.
Base line schedule is the initial project plan that serves as a reference point for comparison.
Updates are changes made to the base line schedule to reflect actual progress and adjustments.
PMC (Project Management Consultant) works involve overseeing project activ...
Top trending discussions
I applied via Referral and was interviewed in Jul 2024. There was 1 interview round.
Plate weight can be calculated by multiplying the area of the plate by its density.
Calculate the area of the plate by multiplying its length and width.
Determine the density of the material of the plate.
Multiply the area by the density to get the weight of the plate.
Cycle time can be calculated by dividing the total production time by the total number of units produced.
Calculate the total production time, including setup time, processing time, and downtime.
Determine the total number of units produced during that time period.
Divide the total production time by the total number of units produced to get the cycle time.
Cycle Time = Total Production Time / Total Number of Units Produce