Filter interviews by
I applied via Company Website and was interviewed in Aug 2022. There were 2 interview rounds.
Plastering area calculation involves measuring the surface area to be covered with plaster.
Measure the length and height of the surface to be plastered
Multiply the length and height to get the surface area
Subtract the area of any openings such as doors and windows
Add 10% extra for wastage
The formula for plastering area calculation is: (Length x Height) - (Area of Openings) + 10% Wastage
Block work quantity estimation involves calculating the amount of blocks required for a construction project.
Determine the dimensions of the wall to be constructed
Calculate the area of the wall
Determine the size of the blocks to be used
Calculate the number of blocks required by dividing the area of the wall by the area of each block
Add 10% extra blocks for wastage and breakages
The number of blocks in one m3 depends on the size of the blocks.
The size of the blocks can vary depending on the material used.
For example, if the blocks are 20cm x 20cm x 20cm, then there would be 125 blocks in one m3.
However, if the blocks are 10cm x 10cm x 10cm, then there would be 1000 blocks in one m3.
BBS or Bar Bending Schedule is prepared by calculating the weight of steel required for a particular structure.
Understand the structural drawings and identify the different components
Calculate the total length of each component and the number of bars required
Calculate the weight of steel required for each component
Prepare a detailed list of all the components and their corresponding weight of steel
Use software like Aut...
Plastering deductions as per IS code refer to the deductions made in plastering thickness as per Indian Standards code.
IS code specifies deductions for plastering thickness based on the type of surface and the type of plaster used.
For example, for a smooth surface and cement plaster, the deduction is 6mm for internal walls and 8mm for external walls.
Similarly, for a rough surface and lime plaster, the deduction is 12mm...
I applied via Naukri.com and was interviewed in Apr 2024. There was 1 interview round.
Bbs,RCC qty, shuttering quantity evaluation written test by company
I applied via Approached by Company and was interviewed before May 2023. There were 2 interview rounds.
Technical round practical approach software knowledge
I applied via Naukri.com and was interviewed before Nov 2021. There were 4 interview rounds.
Cognitive plus technical Test of 1hr 40 min for Technical and 20min for cognitive
I applied via Referral and was interviewed before Aug 2022. There were 4 interview rounds.
IS Code Mode of Measurements refers to the Indian Standard code for measurement practices in construction projects.
IS Code Mode of Measurements is a set of guidelines provided by the Bureau of Indian Standards (BIS) for accurate measurement of quantities in construction projects.
These guidelines cover various aspects such as units of measurement, methods of measurement, and rules for taking measurements.
For example, IS...
Bar Bending Schedule is a document detailing the reinforcement placement in a beam.
Bar Bending Schedule includes details like bar diameter, spacing, length, and shape for each bar in the beam.
It helps in ensuring proper reinforcement placement as per structural design requirements.
Example: Bar Bending Schedule for a beam may specify 10mm diameter bars at 150mm spacing with a total length of 2.5m.
Bar Bending schedule for Column involves detailing the reinforcement requirements for columns in a construction project.
Bar Bending schedule includes details of reinforcement bars, their sizes, shapes, and placement in the column.
It is essential for ensuring the structural integrity and strength of the column.
The schedule is prepared based on structural drawings and design requirements.
Example: A typical bar bending sc...
I applied via Campus Placement and was interviewed before Aug 2020. There was 1 interview round.
posted on 20 Nov 2020
I applied via Campus Placement and was interviewed before Nov 2019. There were 5 interview rounds.
Escalation is the increase in cost or price of goods or services over time due to various factors.
Escalation is significant in construction projects where the cost of materials and labor can increase over time.
It is important to factor in escalation when creating project budgets and timelines.
The formula for escalation is: Escalated Cost = Base Cost x (1 + Escalation Rate)^Number of Years
For example, if the base cost o...
Penalty is a punishment for breach of contract while liquidity damages compensate for financial loss due to breach.
Penalty is a fixed amount agreed upon in the contract as a punishment for breach of contract.
Liquidity damages compensate for the actual financial loss suffered due to breach of contract.
Penalty is usually higher than the actual loss suffered while liquidity damages are calculated based on the actual loss.
...
Basic Price variation refers to the change in the cost of materials or labor used in a project.
Basic Price variation is a common clause in construction contracts.
It allows for adjustments to the contract price based on changes in the cost of materials or labor.
The variation can be positive or negative, depending on whether the cost has increased or decreased.
The variation is usually calculated using an agreed-upon form...
Yes, basic price variation is beneficial for a contract.
Basic price variation allows for adjustments to be made to the contract price based on changes in market conditions or material costs.
This helps to ensure that the contractor is not unfairly burdened with unexpected costs and can maintain profitability.
It also provides a level of transparency and accountability in the contract, as both parties are aware of the pot...
There are various types of contracts in construction projects. Each has its own advantages and drawbacks.
Types of contracts include lump sum, cost-plus, time and material, and unit price contracts.
Lump sum contracts provide a fixed price for the entire project, but can lead to disputes over changes.
Cost-plus contracts reimburse the contractor for all costs plus a fee, but can lead to inflated costs.
Time and material co...
posted on 11 Jun 2022
I applied via Campus Placement and was interviewed before Jun 2021. There were 3 interview rounds.
Mathematics, English, Reasoning
An antenna is a device that converts electrical signals into electromagnetic waves and vice versa. Satcom is short for satellite communication.
Antennas are used for transmitting and receiving signals in various applications such as radio, television, and wireless communication.
Satcom refers to the use of satellites for communication purposes, including television broadcasting, internet access, and military communicatio...
Clean India
Corruption
based on 2 reviews
Rating in categories
Project Manager
12
salaries
| ₹0 L/yr - ₹0 L/yr |
Sales Manager
11
salaries
| ₹0 L/yr - ₹0 L/yr |
Site Engineer
9
salaries
| ₹0 L/yr - ₹0 L/yr |
Project Engineer
8
salaries
| ₹0 L/yr - ₹0 L/yr |
Billing Engineer
7
salaries
| ₹0 L/yr - ₹0 L/yr |
Prestige Group
Sobha
Brigade Group
Godrej Properties