Upload Button Icon Add office photos
Engaged Employer

i

This company page is being actively managed by BSCPL Infrastructure Team. If you also belong to the team, you can get access from here

BSCPL Infrastructure Verified Tick

Compare button icon Compare button icon Compare

Filter interviews by

BSCPL Infrastructure Civil Structural Engineer Interview Questions, Process, and Tips

Updated 23 Oct 2020

BSCPL Infrastructure Civil Structural Engineer Interview Experiences

1 interview found

I applied via Naukri.com and was interviewed in Sep 2020. There were 3 interview rounds.

Interview Questionnaire 

6 Questions

  • Q1. What are the Auto level parts?
  • Ans. 

    Auto level parts are components of an auto level instrument used in surveying and construction.

    • Auto level parts include the telescope, leveling screws, bubble level, focusing knob, and tripod.

    • The telescope is used to sight and measure vertical and horizontal angles.

    • Leveling screws are used to adjust the instrument's level.

    • The bubble level helps in ensuring the instrument is properly leveled.

    • The focusing knob is used to...

  • Answered by AI
  • Q2. Metric chain lenth and links how much lenth of a link?
  • Ans. 

    A metric chain is 20 meters long and consists of 100 links, so each link is 0.2 meters long.

    • A metric chain is a measuring tool used in land surveying.

    • It is 20 meters long and consists of 100 links.

    • Each link is therefore 0.2 meters long.

    • Metric chains are used to measure distances on land with high accuracy.

  • Answered by AI
  • Q3. Slump test
  • Q4. What are the Concrete grades? And thier Ratio
  • Ans. 

    Concrete grades are classifications of concrete based on its strength and durability.

    • Concrete grades range from M5 to M100, with M representing mix and the number representing the compressive strength in megapascals (MPa)

    • The ratio of concrete mix varies depending on the grade, with higher grades requiring more cement, sand, and aggregate

    • For example, M20 concrete has a mix ratio of 1:1.5:3, meaning 1 part cement, 1.5 pa

  • Answered by AI
  • Q5. How we find out right angle?
  • Ans. 

    A right angle is a 90-degree angle formed by two perpendicular lines.

    • A right angle can be found using a protractor or a T-square.

    • A right angle can also be identified by the intersection of two perpendicular lines.

    • In construction, a plumb bob or level can be used to ensure that a corner is at a right angle.

  • Answered by AI
  • Q6. M30 =M means 30Means
  • Ans. 

    M30 =M means 30Means

    • M30 refers to a specific grade of concrete

    • The 'M' stands for mix design

    • The number following 'M' represents the compressive strength of the concrete in megapascals (MPa)

    • For example, M30 means the concrete has a compressive strength of 30 MPa

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Always be confideante

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
Hard
Process Duration
Less than 2 weeks
Result
No response

I applied via LinkedIn and was interviewed in Oct 2023. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. Sfd and bmd questions
  • Q2. Calculation of earthquake loads
  • Ans. 

    Earthquake loads are calculated using seismic design codes and formulas based on the seismic hazard of the region.

    • Determine the seismic hazard of the region using historical data and seismic maps

    • Select a seismic design code such as ASCE 7 or Eurocode 8

    • Calculate the seismic base shear using the formula V = CsW

    • Distribute the seismic base shear to the structure using the appropriate load combinations

    • Consider the effects o...

  • Answered by AI

I applied via Walk-in and was interviewed in Aug 2021. There were 5 interview rounds.

Interview Questionnaire 

4 Questions

  • Q1. Questions will be asked on your work experience. The works you have done in the site.
  • Q2. How to control steel wastage?
  • Ans. 

    Steel wastage can be controlled by proper planning, material handling, and inventory management.

    • Use accurate measurements and cutting techniques to minimize scrap

    • Ensure proper storage and handling of steel to prevent damage and corrosion

    • Implement inventory management systems to track usage and reduce over-ordering

    • Train workers on proper handling and cutting techniques to minimize errors

    • Reuse or recycle scrap steel when

  • Answered by AI
  • Q3. Quantity of cement & flyash in M40 grade concrete?
  • Ans. 

    The quantity of cement & fly ash in M40 grade concrete varies based on the mix design.

    • M40 grade concrete requires a minimum of 400 kg of cement per cubic meter of concrete.

    • Fly ash can be used as a partial replacement for cement in concrete.

    • The percentage of fly ash used in the mix design can range from 0-30%.

    • The exact quantity of cement and fly ash in M40 grade concrete depends on the specific mix design being used.

  • Answered by AI
  • Q4. Deduction of steel for a 45 & 90 degree bend?
  • Ans. 

    Deduction of steel for a 45 & 90 degree bend

    • For a 45 degree bend, deduct 1.5 times the diameter of the bar

    • For a 90 degree bend, deduct 2 times the diameter of the bar

    • This deduction is necessary to account for the length of the bend

    • The deduction varies based on the diameter of the bar being bent

    • The deduction is typically specified in the design drawings or codes

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be sure and honest with your working experience. Dont say anything extra that you haven't done in site before.
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - HR 

(1 Question)

  • Q1. What are the lessons learned from the HR policy?
Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Referral and was interviewed in Dec 2023. There was 1 interview round.

Round 1 - Technical 

(6 Questions)

  • Q1. About your self
  • Q2. What is the difference between Fixed and Pinned connection in base plate?
  • Ans. 

    Fixed connection does not allow rotation at the base plate, while pinned connection allows rotation.

    • Fixed connection is rigid and does not allow rotation at the base plate.

    • Pinned connection allows rotation at the base plate.

    • Fixed connection provides more stability and resistance to lateral forces.

    • Pinned connection is more flexible and allows for some movement.

    • Examples: Fixed connection is commonly used in high-rise bui...

  • Answered by AI
  • Q3. What is the rise and trade in stair?
  • Ans. 

    The rise is the vertical distance between two consecutive steps, while the tread is the horizontal distance.

    • The rise is typically around 7-8 inches, while the tread is usually around 10-11 inches.

    • The rise and tread dimensions are important for ensuring safe and comfortable stair design.

    • Building codes often dictate the minimum and maximum rise and tread dimensions for safety reasons.

  • Answered by AI
  • Q4. What is the pitch distance in bolt?
  • Ans. 

    Pitch distance in bolt refers to the distance between the centers of adjacent bolts in a bolted connection.

    • Pitch distance is typically measured from the center of one bolt to the center of the next bolt in a row.

    • It is important to maintain consistent pitch distances to ensure proper load distribution and structural integrity.

    • For example, in a bolted connection with a pitch distance of 2 inches, the centers of adjacent

  • Answered by AI
  • Q5. Make pipe rack section on both direction
  • Ans. 

    To create a pipe rack section on both directions.

    • Identify the location and dimensions for the pipe rack section

    • Consider the load requirements and support structures

    • Design the pipe rack section using appropriate materials and connections

    • Ensure proper spacing and alignment for pipes in both directions

  • Answered by AI
  • Q6. Make equipment foundation, Pump Foundation
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Conversation 

(1 Question)

  • Q1. Do you have experience with basements and below ground structures
  • Ans. 

    Yes, I have extensive experience with basements and below ground structures.

    • I have designed and analyzed numerous basements for residential and commercial buildings.

    • I am familiar with waterproofing techniques and soil mechanics related to below ground structures.

    • I have experience with retaining walls, foundations, and underground parking structures.

    • I have worked on projects involving deep excavations and shoring system...

  • Answered by AI
Interview experience
3
Average
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Not Selected

I applied via Company Website and was interviewed in Sep 2023. There was 1 interview round.

Round 1 - One-on-one 

(1 Question)

  • Q1. Bending moment & Shear force diagram, lateral pressure from soil & water, reinforcement provision, Tension & compression in retaining walls etc.

Interview Preparation Tips

Interview preparation tips for other job seekers - Study basics of mechanics if you have less than 5 years of experience.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via campus placement at National Institute of Technology (NIT), Warangal and was interviewed before May 2023. There were 3 interview rounds.

Round 1 - Aptitude Test 

Aptitude+ Technical MCQ test

Round 2 - Technical 

(5 Questions)

  • Q1. BMD and SFD diagram of continuous beam and portal frames.
  • Ans. 

    BMD and SFD diagrams show internal forces in a structure, like bending moment and shear force.

    • BMD diagram displays variation of bending moment along the length of a beam or frame.

    • SFD diagram shows variation of shear force along the length of a beam or frame.

    • In continuous beams, BMD and SFD diagrams help in analyzing internal forces at different supports and sections.

    • Portal frames have different loading conditions which...

  • Answered by AI
  • Q2. Basics of geotechnical engineering
  • Q3. Basics of Steel Structure
  • Q4. Plastic method of design
  • Ans. 

    Plastic method of design is a structural engineering approach that considers the redistribution of internal forces to achieve a more efficient design.

    • Plastic method allows for redistribution of internal forces beyond the elastic limit of the material.

    • It is based on the concept of plastic hinges forming in the structure to dissipate energy.

    • Design is based on achieving a collapse mechanism that is ductile and predictable...

  • Answered by AI
  • Q5. Basics of IS456 RCC
Round 3 - HR 

(2 Questions)

  • Q1. Tell me about About yourself
  • Q2. About Salary details

Interview Preparation Tips

Interview preparation tips for other job seekers - Just be technical sound

I applied via Referral

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. About your project and experience.

Interview Preparation Tips

Interview preparation tips for other job seekers - Confident about asignment. Work experience.

I applied via Naukri.com and was interviewed in Feb 2022. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. SFD BMD and technical questions on IS codes
Round 3 - HR 

(1 Question)

  • Q1. Previous experience and job profile discussion

Interview Preparation Tips

Interview preparation tips for other job seekers - Go through technical details of prefab and post harvest equipments

BSCPL Infrastructure Interview FAQs

What are the top questions asked in BSCPL Infrastructure Civil Structural Engineer interview?

Some of the top questions asked at the BSCPL Infrastructure Civil Structural Engineer interview -

  1. Metric chain lenth and links how much lenth of a li...read more
  2. What are the Concrete grades? And thier Ra...read more
  3. What are the Auto level par...read more

Tell us how to improve this page.

Interview Questions from Similar Companies

AECOM Interview Questions
4.2
 • 113 Interviews
Apco Infratech Interview Questions
3.7
 • 112 Interviews
GMR Group Interview Questions
4.1
 • 80 Interviews
Bechtel Interview Questions
4.0
 • 68 Interviews
View all
Junior Engineer Civil
79 salaries
unlock blur

₹1.8 L/yr - ₹4 L/yr

Junior Engineer
65 salaries
unlock blur

₹2 L/yr - ₹4.1 L/yr

Assistant Engineer
46 salaries
unlock blur

₹3 L/yr - ₹6 L/yr

Accountant
43 salaries
unlock blur

₹1.2 L/yr - ₹4.8 L/yr

Technical Assistant
41 salaries
unlock blur

₹1.4 L/yr - ₹2.5 L/yr

Explore more salaries
Compare BSCPL Infrastructure with

Larsen & Toubro Limited

4.0
Compare

GMR Group

4.1
Compare

Hindustan Construction Company

4.2
Compare

IRB Infrastructure

4.1
Compare
Did you find this page helpful?
Yes No
write
Share an Interview