Takt time is calculated by dividing the available production time by the customer demand.
Calculate the total available production time in a specified period (e.g. 1 day)
Determine the customer demand for the same period
Divide the total available production time by the customer demand to get the takt time
Takt Time = Total Production Time / Customer Demand
Line balancing is the process of assigning tasks to workstations in a way that evens out the workload and maximizes efficiency.
Identify the tasks required to complete a process
Determine the cycle time for each task
Assign tasks to workstations based on cycle time and workload
Ensure that workstations are balanced to avoid bottlenecks
Regularly review and adjust the line balancing to optimize efficiency
Capacity analysis involves evaluating the ability of a system or process to handle a certain amount of workload or demand.
Identify the key components of the system or process that contribute to its capacity
Collect data on the current workload or demand placed on the system
Use mathematical models or simulations to predict how the system will perform under different levels of workload
Consider factors such as resource ava...
I applied via Referral and was interviewed in Nov 2022. There were 2 interview rounds.
General Aptitude with reasoning
General Aptitude with reasoning
Ashok Leyland interview questions for popular designations
I applied via Naukri.com and was interviewed in Apr 2022. There were 2 interview rounds.
Get interview-ready with Top Ashok Leyland Interview Questions
I applied via Walk-in and was interviewed before Jun 2023. There was 1 interview round.
I applied via Campus Placement and was interviewed in Dec 2021. There were 2 interview rounds.
I applied via Company Website and was interviewed in Aug 2022. There were 2 interview rounds.
CNC, VMC, and HMC machines can handle various types of machining operations.
CNC machines use computer programming to control the movement of the cutting tool.
VMC machines are used for vertical milling operations.
HMC machines are used for horizontal milling operations.
These machines can handle a wide range of materials, including metals, plastics, and composites.
They are commonly used in industries such as aerospace, au
Technical features refer to the specific functionalities and capabilities of a product or service.
Technical features are often listed in product specifications or user manuals.
They can include things like processing speed, storage capacity, and connectivity options.
Technical features are important for consumers to consider when making purchasing decisions.
Examples of technical features in smartphones include camera res
I am currently earning X and expecting Y based on my skills and experience.
Mention your current salary and the salary you are expecting
Explain how you arrived at your expected salary based on your skills and experience
Be open to negotiation if the company offers a different salary package
Some of the top questions asked at the Ashok Leyland interview -
The duration of Ashok Leyland interview process can vary, but typically it takes about less than 2 weeks to complete.
based on 241 interviews
Interview experience
based on 4.5k reviews
Rating in categories
Assistant Manager
1.1k
salaries
| ₹0 L/yr - ₹0 L/yr |
Deputy Manager
997
salaries
| ₹0 L/yr - ₹0 L/yr |
Senior Officer
516
salaries
| ₹0 L/yr - ₹0 L/yr |
Quality Inspector
472
salaries
| ₹0 L/yr - ₹0 L/yr |
Manager
447
salaries
| ₹0 L/yr - ₹0 L/yr |
Tata Motors
Mahindra & Mahindra
Bharat Forge
Eicher Motors