Add office photos
Employer?
Claim Account for FREE

Apco Infratech

3.7
based on 1k Reviews
Filter interviews by

80+ MasterCard Interview Questions and Answers

Updated 11 Jan 2025

Q1. Crane capacity you use to lift U girder & what is the weight of U Girder?

Ans.

The crane capacity used to lift U girder depends on the weight of the girder.

  • The weight of the U girder needs to be determined first

  • The crane capacity should be greater than the weight of the U girder

  • Factors such as the length and width of the U girder should also be considered

  • Example: If the U girder weighs 50 tons, the crane capacity should be at least 60 tons

View 1 answer

Q2. Execution of Elevated Viaduct (ROB) 6.2KM 1200 numbers pile (Friction & end Bearing Pile) Foundation ROB Pile Cap and Pier, PSC T-Type Pier Cap, Post Tensioning Girder,Bow string (ROB) structure box interchange...

read more
Ans.

The execution of an elevated viaduct involves various tasks such as pile foundation, pier construction, post-tensioning girders, and bridge structures.

  • Tasks include pile foundation construction for the viaduct, pier construction for support, post-tensioning of girders for strength, and bridge structure assembly.

  • Activities also involve conducting load tests, NDT tests, deflection tests, and steel reconciliation for quality assurance.

  • Maintaining site activity includes preparing...read more

Add your answer

Q3. Rates of sub-contractors . Billing process. Reconciliation means and how it is done. Rate Analysis. Key points of your last project. Type of structure that you had seen in your last company. And their detailed...

read more
Ans.

The interview covered topics such as rates of sub-contractors, billing process, reconciliation, rate analysis, previous project experience, and types of structures encountered.

  • Explained the process of obtaining rates from sub-contractors and how they are incorporated into the billing process

  • Discussed the importance of reconciliation in ensuring accurate billing and payment

  • Described the process of rate analysis and how it is used to determine project costs

  • Shared key points and...read more

Add your answer

Q4. Q-What is toe & heel ? Ans - toe & heel retaining wall ka part h .eirth portion heel hota h aur noneirth portion toe hota h Q- box culvert ka drawing ban kar dikhaye? Aur kaise install Kiya jata h . Ans - drawi...

read more
Ans.

Toe and heel are parts of a retaining wall. Toe refers to the non-earth portion while heel refers to the earth portion.

  • Toe and heel are terms used in the context of retaining walls.

  • Toe refers to the non-earth portion of the wall.

  • Heel refers to the earth portion of the wall.

  • Toe provides stability and prevents sliding of the wall.

  • Heel provides support and resists the pressure exerted by the earth.

  • Toe and heel are important components in the design and construction of retaining ...read more

Add your answer
Discover MasterCard interview dos and don'ts from real experiences

Q5. Contractor rate who are doing erection in measurement?

Ans.

The contractor rate for erection in measurement varies depending on the project and location.

  • The rate can be hourly, daily, or project-based.

  • Factors that affect the rate include the complexity of the project, the location, and the experience of the contractor.

  • For example, in New York City, the average hourly rate for an erection engineer is $50-$100.

  • It is important to negotiate the rate and have a clear contract before starting the project.

Add your answer

Q6. What are the stages of Bridge Construction?

Ans.

Bridge construction involves several stages from planning to completion.

  • Planning and design

  • Site preparation and foundation work

  • Substructure construction

  • Superstructure construction

  • Finishing and maintenance

  • Examples of bridge types: suspension, cable-stayed, arch, beam, truss

Add your answer
Are these interview questions helpful?

Q7. How to know from PAN Card whether this number of company or firm or individual

Ans.

The PAN Card number can indicate whether it belongs to a company, firm, or individual.

  • The fourth character of the PAN Card number indicates the type of holder (P for individual, F for firm, C for company, etc.)

  • The fifth character of the PAN Card number indicates the first letter of the PAN holder's last name or surname.

  • For example, if the PAN Card number is ABCDE1234F, the 'F' in the fourth position indicates it belongs to a firm.

View 1 answer

Q8. What maintain higher cader employee and low cader employee

Ans.

Maintaining higher and lower cadre employees involves different strategies.

  • Higher cadre employees may require more challenging work and opportunities for growth and development.

  • Lower cadre employees may need more support and training to improve their skills and performance.

  • Regular performance evaluations and feedback can help both groups improve and stay motivated.

  • Creating a positive work culture and offering competitive compensation and benefits can also help retain employee...read more

View 1 answer
Share interview questions and help millions of jobseekers 🌟

Q9. What are the site and laboratory test on bricks and cement

Ans.

Site and laboratory tests on bricks and cement are essential for ensuring quality and durability of construction materials.

  • Site tests for bricks include visual inspection, water absorption test, compressive strength test, and efflorescence test.

  • Laboratory tests for bricks involve water absorption test, compressive strength test, efflorescence test, and soundness test.

  • Site tests for cement include checking the color, smell, and temperature of the cement, as well as conducting ...read more

Add your answer

Q10. What is the function of rectifier in a welding machine?

Ans.

Rectifier converts AC to DC current in a welding machine.

  • Rectifier is an electrical device that converts alternating current (AC) to direct current (DC).

  • In a welding machine, rectifier is used to convert the AC power supply to DC power supply.

  • DC power supply is required for welding as it provides a stable and consistent current.

  • There are different types of rectifiers used in welding machines such as diode rectifiers, thyristor rectifiers, and transistor rectifiers.

Add your answer

Q11. Tell about erection procedure?

Ans.

Erection procedure involves planning, preparation, and execution of the erection process for a structure or equipment.

  • The procedure starts with a detailed plan and schedule for the erection process.

  • The site is prepared by clearing the area and setting up the necessary equipment and tools.

  • The foundation is laid and the structure or equipment is assembled piece by piece.

  • Safety measures are taken throughout the process to ensure the well-being of workers and the integrity of the...read more

Add your answer

Q12. What is Fire and state it's classifications

Ans.

Fire is a chemical reaction that releases heat and light. It has four classifications.

  • Fire is a rapid oxidation process that produces heat and light.

  • The four classifications of fire are Class A, Class B, Class C, and Class D.

  • Class A fires involve ordinary combustibles like wood, paper, and cloth.

  • Class B fires involve flammable liquids and gases like gasoline and propane.

  • Class C fires involve electrical equipment like appliances and wiring.

  • Class D fires involve combustible met...read more

View 1 answer

Q13. Q- how many types of concrete ? Ans - M5 M7.5 M10 M15 M20 M25 M30 M35 M40 M45 M50

Ans.

There are various types of concrete used in construction, each with different strength and durability characteristics.

  • Concrete is classified based on its compressive strength, measured in megapascals (MPa).

  • Common types of concrete include M5, M7.5, M10, M15, M20, M25, M30, M35, M40, M45, and M50.

  • The number after 'M' represents the compressive strength of the concrete in MPa.

  • For example, M20 concrete has a compressive strength of 20 MPa.

  • Higher strength concrete is typically us...read more

Add your answer

Q14. Q-How much load can 1 Kuplak pipe take? Ans - 4 Ton ka load le sakta h

Ans.

A Kuplak pipe can withstand a load of 4 tons.

  • The load-bearing capacity of a Kuplak pipe is 4 tons.

  • This information is specific to Kuplak pipes and may vary for other types of pipes.

  • It is important to consider the weight distribution and other factors when determining the load capacity of a pipe.

  • Example: A Kuplak pipe can support the weight of a small car or heavy machinery.

Add your answer

Q15. At what decibel sound is classified as noise?

Ans.

Noise is classified as any sound above 85 decibels.

  • Noise levels above 85 decibels can cause hearing damage.

  • Examples of noise levels: normal conversation - 60 decibels, heavy traffic - 85 decibels, rock concert - 110 decibels.

  • It is important to wear hearing protection in noisy environments.

Add your answer

Q16. Do you know what is pivot table and add in Excel workshop vlookup use

Ans.

A pivot table is a data summarization tool in Excel, while VLOOKUP is used to search for a value in a table.

  • Pivot table is used to summarize and analyze data in Excel.

  • VLOOKUP is a function used to search for a value in a table and return a corresponding value.

  • Add-ins in Excel are additional features or tools that can be added to enhance functionality.

  • Workshop VLOOKUP is a training session focused on teaching how to use the VLOOKUP function effectively.

Add your answer

Q17. Difference between Extra Dose and cable stay bridge.

Ans.

Extra Dose bridge has additional support structures while cable stay bridge uses cables to support the bridge deck.

  • Extra Dose bridge has additional piers or columns for support.

  • Cable stay bridge uses cables attached to towers to support the bridge deck.

  • Extra Dose bridge is more common for shorter spans while cable stay bridge is used for longer spans.

  • Cable stay bridges have a more modern and sleek appearance compared to Extra Dose bridges.

Add your answer

Q18. What will happened when use soil compactor on GSB & wmm layer which deadload 12 ton or above?

Ans.

Using a soil compactor on GSB & WMM layers with a deadload of 12 tons or above can lead to excessive compaction and potential damage to the layers.

  • Excessive compaction can result in reduced permeability of the layers, affecting drainage.

  • The excessive force from the compactor can cause cracking or deformation in the layers.

  • It may also lead to uneven settlement and structural instability in the pavement.

  • Proper evaluation of the soil conditions and appropriate compaction equipme...read more

Add your answer

Q19. How to find grades of concrete which is already mixed

Ans.

Grades of concrete in a mixed batch can be estimated by performing a slump test and conducting compressive strength tests on samples.

  • Perform a slump test to determine the workability of the concrete mix.

  • Take samples from the mixed batch and cast test specimens for compressive strength testing.

  • Conduct compressive strength tests on the specimens to determine the grade of concrete.

  • Compare the test results with the standard requirements for different grades of concrete.

Add your answer

Q20. How do you assure piling Point ?

Ans.

Piling point can be assured by conducting thorough soil investigation, using appropriate piling equipment, and monitoring the piling process.

  • Conduct soil investigation to determine soil conditions and suitability for piling.

  • Select appropriate piling equipment based on soil conditions and project requirements.

  • Monitor the piling process to ensure proper installation and alignment of piles.

  • Perform load tests on completed piles to verify their capacity and integrity.

View 1 answer

Q21. How will you provide detailed schedule of 300 km laying

Ans.

I will break down the 300 km laying project into smaller sections, assign resources, estimate durations, and create a detailed schedule.

  • Break down the project into manageable sections such as 10 km segments

  • Assign resources including equipment, manpower, and materials to each section

  • Estimate durations for each activity based on historical data or industry standards

  • Create a detailed schedule using a scheduling software like Primavera P6 or Microsoft Project

  • Regularly update and ...read more

Add your answer

Q22. Deduction of steel for a 45 & 90 degree bend?

Ans.

Deduction of steel for a 45 & 90 degree bend

  • For a 45 degree bend, deduct 1.5 times the diameter of the bar

  • For a 90 degree bend, deduct 2 times the diameter of the bar

  • This deduction is necessary to account for the length of the bend

  • The deduction varies based on the diameter of the bar being bent

  • The deduction is typically specified in the design drawings or codes

Add your answer

Q23. What is the rpm and discharge of the pump

Ans.

The rpm and discharge of a pump are key parameters that determine its performance.

  • RPM (revolutions per minute) is the rotational speed of the pump's shaft.

  • Discharge refers to the volume of fluid that the pump can move in a given time.

  • The rpm and discharge of a pump are typically provided by the manufacturer in the pump's specifications.

  • For example, a centrifugal pump may have an rpm of 1750 and a discharge of 500 gallons per minute.

Add your answer

Q24. What is the distance between jaw in crusher?

Add your answer

Q25. What is the role of the data entry operator

Ans.

A data entry operator is responsible for inputting and updating data into computer systems accurately and efficiently.

  • Inputting and updating data into computer systems

  • Ensuring accuracy and efficiency in data entry

  • Verifying and correcting data errors

  • Maintaining confidentiality and security of data

  • Organizing and managing data files

  • Generating reports and summaries from data

  • Using data entry software and tools

  • Following data entry procedures and guidelines

View 2 more answers

Q26. How can take Necessary action regarding the safety policy ?

Add your answer

Q27. Pile built-up above cut off level as per IS code

Ans.

Pile built-up above cut off level as per IS code

  • IS code specifies the maximum allowable pile length above cut off level

  • Pile length above cut off level should not exceed 3 times the pile diameter

  • Built-up pile above cut off level can cause structural instability and failure

Add your answer

Q28. Quantity of cement & flyash in M40 grade concrete?

Ans.

The quantity of cement & fly ash in M40 grade concrete varies based on the mix design.

  • M40 grade concrete requires a minimum of 400 kg of cement per cubic meter of concrete.

  • Fly ash can be used as a partial replacement for cement in concrete.

  • The percentage of fly ash used in the mix design can range from 0-30%.

  • The exact quantity of cement and fly ash in M40 grade concrete depends on the specific mix design being used.

Add your answer

Q29. How many types Cement? Which is best grade?

Ans.

There are different types of cement such as Ordinary Portland Cement, Portland Pozzolana Cement, and Portland Slag Cement. The best grade depends on the specific application.

  • Types of cement include Ordinary Portland Cement, Portland Pozzolana Cement, and Portland Slag Cement

  • The best grade of cement depends on the specific application and requirements

  • For general construction purposes, Ordinary Portland Cement is commonly used

  • For projects requiring high durability and strength,...read more

Add your answer

Q30. What is the fuel consumption in H M Plant?

Add your answer

Q31. What is Grider Shuttering materials Sizes

Ans.

Grider Shuttering materials come in various sizes to support different construction needs.

  • Grider Shuttering materials sizes typically range from 1.5 meters to 3 meters in length.

  • Common widths for Grider Shuttering materials include 150mm, 200mm, and 250mm.

  • Thickness of Grider Shuttering materials can vary from 50mm to 100mm.

  • Examples of Grider Shuttering materials sizes: 2.5 meters in length, 200mm in width, and 75mm in thickness.

Add your answer

Q32. How to control steel wastage?

Ans.

Steel wastage can be controlled by proper planning, material handling, and inventory management.

  • Use accurate measurements and cutting techniques to minimize scrap

  • Ensure proper storage and handling of steel to prevent damage and corrosion

  • Implement inventory management systems to track usage and reduce over-ordering

  • Train workers on proper handling and cutting techniques to minimize errors

  • Reuse or recycle scrap steel whenever possible

Add your answer

Q33. What you check in purchase order

Ans.

In a purchase order, I check for accuracy, completeness, authorization, and adherence to company policies.

  • Check for accuracy of items, quantities, prices, and terms

  • Ensure completeness of information such as vendor details, delivery dates, and payment terms

  • Verify authorization by checking for approval signatures or electronic approvals

  • Ensure adherence to company policies and procedures regarding procurement

Add your answer

Q34. What is routers and their types?

Ans.

Routers are networking devices that forward data packets between computer networks. Types include wired, wireless, core, edge, and virtual routers.

  • Routers are used to connect multiple networks together

  • Wired routers use physical cables to connect devices

  • Wireless routers use Wi-Fi to connect devices

  • Core routers are used in the backbone of the network

  • Edge routers connect the network to external networks

  • Virtual routers are software-based routers used in virtualized environments

View 1 answer

Q35. What is switch and their types?

Ans.

A switch is a networking device that connects devices on a local area network (LAN) and forwards data packets between them.

  • Types of switches include managed switches, unmanaged switches, and layer 2/layer 3 switches.

  • Managed switches allow for configuration and monitoring of network traffic.

  • Unmanaged switches are plug-and-play devices with no configuration options.

  • Layer 2 switches operate at the data link layer and use MAC addresses to forward data.

  • Layer 3 switches operate at ...read more

View 1 answer

Q36. What is osi layers and their function?

Ans.

OSI (Open Systems Interconnection) model is a conceptual framework that standardizes the functions of a telecommunication or computing system into seven abstraction layers.

  • Physical Layer: Deals with physical connections and transmission of raw data.

  • Data Link Layer: Manages data frames and error detection/correction.

  • Network Layer: Handles routing and logical addressing.

  • Transport Layer: Ensures end-to-end communication and data flow control.

  • Session Layer: Manages sessions betwe...read more

View 1 answer

Q37. Why does use SMA layer in High speed express way?

Ans.

SMA layer is used in high speed expressways for its superior durability, rut resistance, and fatigue resistance.

  • SMA (Stone Matrix Asphalt) layer provides superior durability compared to traditional asphalt mixes.

  • SMA layer has excellent rut resistance, maintaining a smooth surface for high speed traffic.

  • The high binder content in SMA enhances fatigue resistance, reducing cracking and extending pavement life.

  • SMA mixtures are designed to withstand heavy traffic loads and harsh w...read more

Add your answer

Q38. What is SP02? explain in brief

Ans.

SP02 is a measure of oxygen saturation in the blood.

  • SP02 is a non-invasive way to measure the amount of oxygen in the blood.

  • It is measured as a percentage and is typically done using a pulse oximeter.

  • A normal SP02 reading is between 95-100%, while anything below 90% is considered low and may require medical attention.

  • SP02 levels can be affected by various factors such as altitude, lung diseases, and heart conditions.

Add your answer

Q39. How can possible implement the HSE Policy ?

Add your answer

Q40. Is code of Ms pipeline .?

Ans.

No, there is no specific code for Ms pipeline.

  • There is no specific code designated for Ms pipeline in the mechanical engineering field.

  • Ms pipeline may refer to a type of pipeline material or construction method, but it does not have a standardized code.

  • Engineers typically follow industry standards and specifications when designing and constructing pipelines.

Add your answer

Q41. What is GST rate of MS Steel

Ans.

GST rate on MS Steel is 18%

  • GST rate on MS Steel is 18%

  • MS Steel falls under the 18% GST slab

  • GST rate on MS Steel products is 18%

View 1 answer

Q42. Plastering work calculation for different size of wall

Ans.

Plastering work calculation involves determining the surface area of the wall and the thickness of the plaster.

  • Calculate the surface area of the wall by multiplying the height and length of each wall segment.

  • Determine the total surface area to be plastered by adding up the surface areas of all wall segments.

  • Multiply the total surface area by the desired thickness of the plaster to get the volume of plaster needed.

  • Consider wastage and additional coats when calculating the quan...read more

Add your answer

Q43. What was the model of jaw crusher?

Add your answer

Q44. What is network and networking?

Ans.

Network is a collection of computers and other devices connected together to share resources and information.

  • Network refers to the infrastructure that allows devices to communicate with each other.

  • Networking involves the process of connecting devices within a network to enable communication.

  • Examples of networks include LAN (Local Area Network), WAN (Wide Area Network), and the internet.

View 1 answer

Q45. Pile vertical tolerance as per IS code

Ans.

Vertical tolerance for piles as per IS code

  • As per IS 2911-1:2010, the vertical tolerance for piles is +/- 25mm

  • This tolerance is applicable for both driven and cast-in-situ piles

  • The tolerance is measured at the top of the pile and at intervals of 3m along the length

  • If the deviation exceeds the tolerance limit, the pile may need to be rejected or remedial measures taken

Add your answer

Q46. overall responsibility for highway work and contactor billing

Ans.

The overall responsibility for highway work includes overseeing project progress, ensuring quality standards are met, and managing contractor billing.

  • Oversee project progress to ensure timelines are met

  • Ensure quality standards are maintained throughout the construction process

  • Manage contractor billing and ensure accurate invoicing

  • Coordinate with various stakeholders including engineers, contractors, and government agencies

  • Address any issues or delays that may arise during the...read more

Add your answer

Q47. Who is ur immediate reporting person.

Add your answer

Q48. What is the timing of TTL?

Ans.

Time To Live (TTL) is a value in data packets that specifies the maximum amount of time the packet can remain in a network before being discarded.

  • TTL is a field in the IP header of a packet

  • It is measured in seconds

  • TTL is used to prevent packets from circulating indefinitely in a network

  • When a packet reaches a router, the TTL value is decremented by one

  • If the TTL reaches 0, the packet is discarded

Add your answer

Q49. Method of traversing calculation

Ans.

Traversing calculation involves measuring angles and distances between survey points to determine their relative positions.

  • Traversing involves a series of measurements taken between survey points

  • Angles are measured using a theodolite or total station

  • Distances are measured using a tape or electronic distance meter

  • Calculations are then performed to determine the coordinates of each point

  • Errors can be minimized by using redundant measurements and closing the traverse

View 1 answer

Q50. 30 cuibicmere per hour Batching plant experience

Ans.

I have experience working with a batching plant that can produce 30 cubic meters per hour.

  • I have operated and maintained a batching plant with a capacity of 30 cubic meters per hour.

  • I am familiar with the process of batching and mixing concrete.

  • I have experience troubleshooting and resolving issues with the batching plant.

  • I have ensured that the batching plant is always in good working condition and meets safety standards.

  • I have trained and supervised staff in operating the b...read more

Add your answer

Q51. What is favourable zone in RCC

Ans.

Favourable zone in RCC refers to the region of a reinforced concrete member where the concrete is in compression and the steel is in tension.

  • Favourable zone is the area where the concrete is able to resist compressive forces effectively.

  • It is typically located at the top of a beam or slab, where the bending moment is highest.

  • In this zone, the steel reinforcement helps to resist tensile forces, while the concrete resists compressive forces.

  • Proper design of the favourable zone ...read more

Add your answer

Q52. Process of Making Minor Bridge?

Ans.

The process of making a minor bridge involves planning, design, construction, and inspection.

  • 1. Planning phase involves determining the location, size, and type of bridge needed.

  • 2. Design phase includes creating detailed drawings and calculations for the bridge structure.

  • 3. Construction phase involves building the foundation, supports, and deck of the bridge.

  • 4. Inspection phase ensures the bridge meets safety and quality standards.

  • 5. Examples of minor bridges include footbrid...read more

View 1 answer

Q53. What is a micrometre.?

Ans.

A micrometre is a unit of length equal to one millionth of a meter, commonly used for measuring very small distances.

  • A micrometre is also known as a micron.

  • It is commonly used in fields such as engineering, physics, and biology for measuring small distances.

  • One micrometre is equal to 0.001 millimeters or 0.000001 meters.

  • Examples of objects measured in micrometres include bacteria, cells, and thin films.

  • Micrometres are often used in precision machining and manufacturing proces...read more

Add your answer

Q54. MS Excel uses all formula.

Ans.

No, MS Excel does not use all formulas.

  • MS Excel uses a wide range of formulas for various calculations and data manipulation.

  • Some commonly used formulas in MS Excel include SUM, AVERAGE, IF, VLOOKUP, and COUNT.

  • Formulas in MS Excel can be used to perform mathematical operations, logical comparisons, text manipulation, and more.

  • Users can also create custom formulas using functions and operators provided by MS Excel.

  • For example, the formula =SUM(A1:A5) calculates the sum of valu...read more

View 1 answer

Q55. Percentage of steel in pile

Ans.

The percentage of steel in a pile varies depending on the type and design of the pile.

  • The percentage of steel in a pile can range from 0% to over 90%.

  • The type of pile (e.g. steel, concrete, timber) and its design (e.g. diameter, length, wall thickness) determine the percentage of steel.

  • Steel piles typically have a higher percentage of steel than other types of piles.

  • The percentage of steel in a pile can also affect its cost and performance.

Add your answer

Q56. Pile concrete consumption +- tolerance

Ans.

Pile concrete consumption tolerance depends on various factors.

  • Pile diameter and length

  • Concrete mix design

  • Placement method

  • Quality control measures

  • Environmental conditions

  • Tolerance typically ranges from 5-10% of estimated consumption

  • Regular monitoring and adjustment of concrete consumption is necessary

Add your answer

Q57. Who is ur father etc…. Locality and all

Ans.

My father is a retired government official who served in the education department. We live in a peaceful neighborhood in the suburbs.

  • My father is a retired government official

  • He worked in the education department

  • We live in a peaceful neighborhood in the suburbs

Add your answer

Q58. What are the Basics of Store

Ans.

Basics of store include inventory management, customer service, sales, and merchandising.

  • Inventory management involves tracking stock levels, ordering new products, and organizing storage.

  • Customer service includes greeting customers, assisting with inquiries, and resolving issues.

  • Sales involve processing transactions, upselling products, and meeting revenue targets.

  • Merchandising focuses on product displays, promotions, and creating an attractive store layout.

  • Examples: Keeping...read more

Add your answer

Q59. how to eat, live, work, behave

Ans.

Maintain a healthy lifestyle and professional conduct.

  • Eat a balanced diet and stay hydrated

  • Exercise regularly and get enough sleep

  • Follow safety protocols and maintain cleanliness in the lab

  • Be punctual and respectful towards colleagues and patients

  • Maintain confidentiality and adhere to ethical standards

  • Continuously update knowledge and skills through training and education

Add your answer

Q60. Type of lapping in reinforcement

Ans.

Lapping in reinforcement involves overlapping two reinforcement bars to ensure continuity and strength in the structure.

  • Lapping is commonly used in construction to connect two reinforcement bars together.

  • The length of the lap varies depending on the design requirements and the type of reinforcement used.

  • Proper lapping ensures that the load is transferred effectively between the bars.

  • Examples of lapping include lap splices, mechanical splices, and welded splices.

Add your answer

Q61. Are you know typing?

Ans.

Yes, I am proficient in typing.

  • Yes, I am familiar with typing and can type accurately and efficiently.

  • I have experience using various typing software and tools.

  • I can type at a reasonable speed without errors.

  • For example, I have used Microsoft Word for typing reports and emails.

View 1 answer

Q62. Explain Pilling in detail.

Ans.

Pilling is the formation of small balls of fibers on the surface of a fabric.

  • Pilling occurs due to friction and abrasion on the fabric surface.

  • It is more common in synthetic fabrics than natural ones.

  • Pilling can be prevented by using fabric softeners, washing clothes inside out, and avoiding high heat in the dryer.

  • Pilling can be removed using a fabric shaver or a lint roller.

  • Pilling is not a sign of poor quality fabric, but rather a natural occurrence.

Add your answer

Q63. Method of traversing

Ans.

Traversing is the method used to measure and map land by moving from one point to another.

  • Traversing involves measuring angles and distances between points to create a network of interconnected lines.

  • Common methods of traversing include the compass rule, the transit rule, and the chain and compass method.

  • Traversing can be done using traditional surveying instruments like theodolites and total stations, or with modern GPS technology.

  • Example: In a compass rule traverse, the sur...read more

View 2 more answers

Q64. How do Reconciliation

Ans.

Reconciliation involves comparing financial records to ensure accuracy and consistency.

  • Reconciliation is the process of comparing two sets of records to ensure they match.

  • It is commonly done for bank statements, inventory records, and financial transactions.

  • Discrepancies found during reconciliation must be investigated and resolved.

  • Reconciliation helps identify errors, fraud, or missing transactions.

  • Regular reconciliation is important for maintaining accurate financial record...read more

Add your answer

Q65. What is moter and it capacity

Ans.

A motor is a device that converts electrical energy into mechanical energy to perform work.

  • Motors are commonly used in various applications such as electric vehicles, industrial machinery, and household appliances.

  • They come in different types such as AC motors, DC motors, and stepper motors.

  • Motor capacity refers to its power rating, typically measured in horsepower (HP) or kilowatts (kW).

  • Higher capacity motors can generate more mechanical power and are used for heavy-duty app...read more

Add your answer

Q66. Unit weight of steel

Ans.

Unit weight of steel is 7850 kg/m³

  • The unit weight of steel is the weight of a specific volume of steel

  • It is measured in kilograms per cubic meter (kg/m³)

  • The unit weight of steel is 7850 kg/m³

  • This value may vary slightly depending on the composition and manufacturing process of the steel

Add your answer

Q67. What is P&p

Ans.

P&p stands for Policies and Procedures.

  • Policies and Procedures are a set of guidelines and rules that an organization follows.

  • They help in maintaining consistency and standardization in the organization.

  • Policies and Procedures cover various aspects such as HR, finance, operations, etc.

  • They are designed to ensure compliance with legal and regulatory requirements.

  • Examples of P&p include employee code of conduct, IT security policy, procurement policy, etc.

Add your answer

Q68. Explain Costing, Manpower handling.

Ans.

Costing involves calculating the expenses associated with maintenance activities. Manpower handling involves managing and coordinating the workforce.

  • Costing in maintenance involves determining the costs of spare parts, equipment, labor, and other resources required for maintenance activities.

  • Manpower handling includes assigning tasks to technicians, scheduling shifts, providing training, and ensuring safety regulations are followed.

  • Effective costing helps in budgeting and opt...read more

Add your answer

Q69. What is lap length

Ans.

Lap length is the length of overlap between two reinforcing bars in a concrete structure to ensure proper transfer of loads.

  • Lap length is important for ensuring the continuity of reinforcement in concrete structures.

  • It is typically specified in building codes and design standards.

  • The lap length required depends on factors such as the diameter of the bars, concrete strength, and design loads.

  • For example, in a beam, the lap length is the distance over which one rebar extends be...read more

Add your answer

Q70. What is M4 in Planning

Ans.

M4 in Planning refers to a milestone that marks the completion of a significant phase or deliverable in a project schedule.

  • M4 is typically used in project management to signify a key point in the project timeline.

  • It is often associated with the completion of a major task or the achievement of an important project milestone.

  • M4 can help track progress, identify potential delays, and ensure that the project stays on schedule.

  • Examples of M4 milestones include completing the desig...read more

Add your answer

Q71. What is safety explain pls?

Ans.

Safety refers to the measures taken to prevent accidents, injuries, and other harmful incidents.

  • Safety involves identifying and assessing potential hazards and taking steps to eliminate or control them.

  • It also involves providing training and education to employees to ensure they understand how to work safely.

  • Regular inspections and audits are necessary to ensure safety standards are being met.

  • Examples of safety measures include wearing personal protective equipment, following...read more

Add your answer

Q72. Cable laying in tranch & cable tray

Ans.

Cable laying in tranch & cable tray involves the installation of electrical cables in underground trenches and on cable trays.

  • Cable laying in tranch involves digging trenches underground to lay cables for electrical connections.

  • Cable laying in cable tray involves placing cables on trays mounted on walls or ceilings for organized and safe routing.

  • Proper planning and design are essential for efficient cable laying to ensure safety and functionality.

  • Use of appropriate cable type...read more

Add your answer

Q73. IS code for BBS

Ans.

IS code for BBS is IS 1786:2008

  • IS 1786:2008 is the Indian Standard code for specifications of high strength deformed steel bars for concrete reinforcement

  • BBS stands for Bar Bending Schedule, which is a detailed list of reinforcement bars with their lengths and shapes required for construction

  • Following IS 1786:2008 ensures the quality and strength of the reinforcement bars used in construction projects

View 1 answer

Q74. Role of bearing in bridges

Ans.

Bearings in bridges help distribute loads and allow for movement due to temperature changes and settlement.

  • Bearings help distribute the loads from the superstructure to the substructure of the bridge.

  • They allow for movement of the bridge deck due to temperature changes, wind forces, and settlement of the foundation.

  • Bearings help reduce stress on the bridge components and prevent damage.

  • Common types of bearings used in bridges include elastomeric bearings, pot bearings, and sl...read more

Add your answer

Q75. Types of expansion joint

Ans.

Types of expansion joints include slip joints, bellows joints, and modular joints.

  • Slip joints allow for movement in one direction only

  • Bellows joints accommodate movement in multiple directions

  • Modular joints are made up of separate components that can be replaced individually

Add your answer

Q76. Types of contract.

Ans.

Types of contracts include express, implied, unilateral, bilateral, and voidable contracts.

  • Express contract: Clearly stated terms and conditions, either written or verbal.

  • Implied contract: Terms inferred from the actions or conduct of the parties involved.

  • Unilateral contract: One party makes a promise in exchange for the performance of an act by the other party.

  • Bilateral contract: Both parties exchange promises to perform certain actions.

  • Voidable contract: One party has the o...read more

Add your answer

Q77. Preventive maintenance of excavator.

Ans.

Preventive maintenance of excavator involves regular inspections, lubrication, and replacement of worn parts to ensure optimal performance and longevity.

  • Regularly inspecting the excavator for signs of wear and tear

  • Lubricating moving parts to prevent friction and reduce wear

  • Replacing worn out parts such as filters, belts, and hoses

  • Checking fluid levels and topping up as needed

  • Cleaning the excavator to prevent buildup of dirt and debris

  • Following manufacturer's maintenance sched...read more

Add your answer

Q78. Method of leveling

Ans.

Method of leveling is the process of determining the elevation of a point relative to a reference point.

  • The most common method of leveling is using a spirit level or a laser level.

  • Another method is trigonometric leveling, which uses trigonometry to calculate elevations.

  • Differential leveling involves measuring the difference in elevation between two points using a level and a rod.

  • Barometric leveling uses atmospheric pressure to determine elevation.

  • GPS leveling uses satellite t...read more

Add your answer

Q79. Cross section of road

Ans.

A cross section of a road is a vertical slice through the road showing the various layers and components.

  • A cross section typically includes the road surface, base course, subbase, and natural subgrade.

  • It helps engineers understand the composition of the road and plan for construction or maintenance.

  • Cross sections are used to determine the appropriate materials and thickness for each layer of the road.

  • Examples of cross section components include asphalt pavement, concrete pave...read more

Add your answer

Q80. Cable tray erection in metro

Ans.

Cable tray erection in metro involves installing cable trays to support and protect electrical cables in underground transportation systems.

  • Ensure proper planning and coordination with other trades to avoid conflicts during installation.

  • Select appropriate cable tray materials based on the environment and load requirements.

  • Follow safety regulations and guidelines to prevent accidents during installation.

  • Consider factors such as cable routing, accessibility for maintenance, and...read more

View 1 answer

Q81. What is ABC Analysis

Ans.

ABC Analysis is a method used in inventory management to categorize items based on their importance and prioritize them accordingly.

  • ABC Analysis categorizes items into three groups: A, B, and C.

  • Group A items are the most important and high-value items that require close monitoring and frequent replenishment.

  • Group B items are moderately important and have a moderate value.

  • Group C items are the least important and low-value items that require minimal attention.

  • The analysis help...read more

Add your answer

Q82. Soil compactor drum thickness.

Ans.

Soil compactor drum thickness is an important factor for compaction efficiency and durability.

  • The drum thickness of a soil compactor is typically between 0.5 to 1 inch.

  • Thicker drums are more durable and can withstand heavier loads.

  • The material of the drum also affects its thickness and durability, with steel drums being thicker than plastic ones.

  • Regular maintenance and inspection of the drum thickness is important to ensure optimal performance.

Add your answer

Q83. Incharge for highway section

Ans.

The Assistant General Manager for the highway section is responsible for overseeing the operations and maintenance of the highway, ensuring safety and efficiency.

  • Oversee maintenance and operations of the highway section

  • Ensure safety and efficiency of the highway

  • Coordinate with various departments and stakeholders

  • Implement policies and procedures to improve highway performance

Add your answer

Q84. CBR requirement of soil.

Ans.

CBR requirement of soil is a measure of its strength and ability to support heavy loads.

  • CBR stands for California Bearing Ratio.

  • It is a measure of the strength of a soil to support loads applied to it.

  • Higher CBR values indicate stronger soil.

  • CBR values are used in designing pavement structures.

  • Different types of soil have different CBR requirements.

Add your answer

Q85. Process of W. T. P

Ans.

The process of Water Treatment Plant (W.T.P) involves various stages to purify water for consumption.

  • 1. Coagulation: Adding chemicals to water to make particles clump together.

  • 2. Sedimentation: Allowing the clumped particles to settle at the bottom.

  • 3. Filtration: Passing water through filters to remove remaining particles.

  • 4. Disinfection: Adding chlorine or other chemicals to kill bacteria and viruses.

  • 5. Distribution: Sending the treated water to homes and businesses for cons...read more

Add your answer
Contribute & help others!
Write a review
Share interview
Contribute salary
Add office photos

Interview Process at MasterCard

based on 125 interviews
Interview experience
4.1
Good
View more
Interview Tips & Stories
Ace your next interview with expert advice and inspiring stories

Top Interview Questions from Similar Companies

3.9
 • 711 Interview Questions
3.7
 • 417 Interview Questions
4.0
 • 393 Interview Questions
3.9
 • 338 Interview Questions
4.1
 • 147 Interview Questions
3.8
 • 131 Interview Questions
View all
Top Apco Infratech Interview Questions And Answers
Share an Interview
Stay ahead in your career. Get AmbitionBox app
qr-code
Helping over 1 Crore job seekers every month in choosing their right fit company
70 Lakh+

Reviews

5 Lakh+

Interviews

4 Crore+

Salaries

1 Cr+

Users/Month

Contribute to help millions

Made with ❤️ in India. Trademarks belong to their respective owners. All rights reserved © 2024 Info Edge (India) Ltd.

Follow us
  • Youtube
  • Instagram
  • LinkedIn
  • Facebook
  • Twitter