A bar bending schedule is a document detailing the type, size, quantity, and placement of reinforcement bars in a concrete structure according to US code.
A bar bending schedule is prepared based on the structural drawings and specifications provided for a project.
It includes details such as bar mark, bar size, quantity, length, shape, and bending dimensions for each reinforcement bar.
The schedule helps in estimating th...
Top trending discussions
posted on 3 May 2019
I applied via Naukri.com and was interviewed before May 2018. There were 2 interview rounds.
I am currently earning $60,000 per year.
My current salary is $60,000 per year.
I am satisfied with my current salary.
I believe my salary reflects my experience and qualifications.
posted on 13 May 2018
I was interviewed before May 2017.
posted on 16 Mar 2022
I applied via LinkedIn and was interviewed in Feb 2022. There were 2 interview rounds.
Quantity survey involves estimating and managing costs of construction projects while billing is the process of invoicing clients for work done.
Quantity survey involves cost estimation, cost control, and cost management of construction projects.
Billing is the process of invoicing clients for work done on a project.
Quantity surveyors work closely with architects, engineers, and contractors to ensure that projects are co...
posted on 4 Apr 2021
Piles are used in construction to transfer loads from a structure to a stronger layer of soil or rock below the surface.
Types of piles include driven piles, bored piles, and screw piles.
Piles are provided to support structures on weak or compressible soil, to resist uplift forces, or to provide lateral support.
The diameter of a pile is determined based on the load it needs to support and the soil conditions.
LVUP (Large...
posted on 18 Dec 2020
I applied via Recruitment Consultant and was interviewed in Dec 2020. There were 4 interview rounds.
posted on 24 Oct 2020
I applied via Naukri.com and was interviewed in Sep 2020. There were 3 interview rounds.
The amount of cement used for making 1m³ of concrete varies depending on the desired strength and type of concrete.
The cement content typically ranges from 300 to 400 kg/m³ for general-purpose concrete.
For high-strength concrete, the cement content can be as high as 500 kg/m³ or more.
The water-cement ratio also affects the amount of cement required.
Admixtures and additives may be used to modify the properties of the co...
The amount of steel used for 1m³ concreting varies depending on the type of concrete and the structural requirements.
The steel used in concrete is typically in the form of reinforcing bars (rebar) or welded wire mesh.
The amount of steel required for 1m³ of concrete depends on the structural requirements and the type of concrete being used.
For example, a standard reinforced concrete slab may require 70-100 kg of steel p...
Process piping works involve the installation, inspection, and maintenance of pipes used in industrial processes.
Process piping works include the design, fabrication, and installation of pipes for conveying fluids or gases in industrial settings.
QA QC engineers ensure that the piping systems meet the required standards and specifications.
Inspection and testing of process piping is done to check for leaks, pressure, and...
Bolts tightening procedure involves following a specific torque value and sequence to ensure proper fastening of bolts.
Check the torque value specified in the design or manual
Use a torque wrench to tighten the bolts to the specified value
Tighten the bolts in a specific sequence to ensure even distribution of load
Recheck the torque value after tightening all bolts
Record the torque value and sequence for future reference
Hydrotest and pneumatic test are methods used to test the integrity of piping systems.
Hydrotest involves filling the piping system with water and pressurizing it to a specified level for a set duration.
Pneumatic test involves filling the piping system with compressed air or nitrogen and pressurizing it to a specified level for a set duration.
Both tests are used to ensure that the piping system can withstand the expecte...
posted on 9 Sep 2020
I applied via Company Website and was interviewed in Aug 2020. There were 3 interview rounds.
based on 1 interview
Interview experience
based on 12 reviews
Rating in categories
Rebar Estimator
24
salaries
| ₹1.8 L/yr - ₹3.6 L/yr |
Rebar Detailer
12
salaries
| ₹2.2 L/yr - ₹3.6 L/yr |
Estimator
6
salaries
| ₹2.6 L/yr - ₹4.2 L/yr |
Accountant
4
salaries
| ₹1.2 L/yr - ₹3.2 L/yr |
Executive Accountant
4
salaries
| ₹3.2 L/yr - ₹3.2 L/yr |
TCS
Infosys
Wipro
HCLTech