Filter interviews by
Clear (1)
I applied via Naukri.com and was interviewed in Aug 2024. There was 1 interview round.
Baseline schedule is the original project schedule used as a reference point for comparison.
Baseline schedule is the initial approved project schedule that serves as a benchmark for measuring project progress.
It includes the planned start and finish dates for project activities, milestones, and deliverables.
Any changes to the schedule must be compared against the baseline schedule to assess impact.
Baseline schedule hel...
Planning Engineer is responsible for creating project schedules, monitoring progress, identifying delays, and coordinating with stakeholders.
Creating project schedules using software like Primavera P6
Monitoring project progress and identifying potential delays
Coordinating with project team members, subcontractors, and clients
Analyzing project data to make informed decisions
Preparing progress reports and presenting to s
Weekly lookahead schedule involves reviewing upcoming tasks, identifying potential issues, and adjusting the schedule accordingly.
Review current progress and upcoming tasks for the week
Identify any potential issues or constraints that may impact the schedule
Adjust the schedule by re-sequencing tasks or allocating additional resources if needed
Communicate any changes to the project team to ensure alignment
I manage procurement schedule by creating a detailed plan, tracking progress, identifying risks, and communicating with stakeholders.
Create a detailed procurement schedule outlining key milestones and deadlines
Track progress regularly to ensure tasks are completed on time
Identify potential risks and develop contingency plans to mitigate them
Communicate effectively with suppliers, team members, and stakeholders to ensur...
Top trending discussions
posted on 12 Jun 2021
I applied via Walk-in and was interviewed before Jun 2020. There was 1 interview round.
The sampling frequency for private density test per square meter depends on the type of test being conducted.
The sampling frequency for a private density test per square meter varies depending on the type of test being conducted.
For example, a soil density test may require a sampling frequency of one sample per 100 square meters, while a concrete density test may require a sampling frequency of one sample per 10 square...
I was interviewed before Sep 2021.
Planning process involves defining objectives, identifying resources, creating a schedule, and monitoring progress.
Define project objectives and scope
Identify available resources and constraints
Create a detailed project schedule
Monitor progress and make adjustments as necessary
The planning process involves identifying objectives, determining resources, and creating a timeline for completion.
Identify project objectives and goals
Determine available resources and constraints
Create a detailed project plan with timelines and milestones
Monitor progress and make adjustments as necessary
Communicate with stakeholders and team members throughout the process
Dressing and personality
I applied via Campus Placement and was interviewed before Mar 2023. There was 1 interview round.
The structure work at the site involves the construction of a new building using steel beams and concrete columns.
Steel beams are being used for the framework of the building
Concrete columns are being installed to support the structure
The construction process includes pouring concrete, welding steel beams, and erecting walls
Managing site works involves overseeing construction activities, coordinating with contractors, ensuring safety regulations are followed, and meeting project deadlines.
Coordinate with contractors and subcontractors to ensure work is completed on time and within budget
Monitor progress of construction activities and address any issues that may arise
Ensure compliance with safety regulations and quality standards
Communicat...
I applied via Naukri.com and was interviewed before Jun 2022. There were 3 interview rounds.
I applied via Approached by Company and was interviewed in Aug 2023. There was 1 interview round.
I applied via Naukri.com and was interviewed before Jul 2023. There was 1 interview round.
I applied via Approached by Company and was interviewed in Jan 2023. There were 4 interview rounds.
Copy Monitor is a Revit tool that allows users to monitor and synchronize changes made to linked models.
Copy Monitor is used in Revit to ensure that changes made to linked models are reflected in the current model.
It allows users to monitor and synchronize changes made to linked models.
Copy Monitor can be used to track changes to elements such as walls, floors, and roofs.
It can also be used to monitor changes to parame...
Revit models can be linked using the 'Link Revit' tool in the 'Insert' tab.
Open the host model and go to the 'Insert' tab.
Click on 'Link Revit' and select the model to be linked.
Choose the appropriate settings for the link, such as positioning and visibility.
Repeat the process for any additional models to be linked.
Save the host model to ensure the links are maintained.
They gave an architectural model to create a structural model
I applied via Walk-in and was interviewed in Jan 2024. There was 1 interview round.
Types of paints and tiles commonly used in construction projects.
Types of paints: acrylic, latex, oil-based, enamel, spray paint
Types of tiles: ceramic, porcelain, glass, natural stone, mosaic
based on 1 interview
Interview experience
based on 4 reviews
Rating in categories
Billing Engineer
31
salaries
| ₹0 L/yr - ₹0 L/yr |
Civil Site Engineer
27
salaries
| ₹0 L/yr - ₹0 L/yr |
Executive Engineer
26
salaries
| ₹0 L/yr - ₹0 L/yr |
Junior Engineer
24
salaries
| ₹0 L/yr - ₹0 L/yr |
Site Engineer
22
salaries
| ₹0 L/yr - ₹0 L/yr |
Sobha
Prestige Group
Godrej Properties
DLF