I applied via Approached by Company and was interviewed before Oct 2021. There were 2 interview rounds.
The critical path is the longest sequence of activities in a project that must be completed on time to ensure the project's success.
It determines the shortest possible duration of a project.
It identifies the activities that cannot be delayed without delaying the entire project.
It helps in resource allocation and scheduling.
It is important to monitor and manage the critical path to ensure project completion on time.
Exam...
Construction schedule with multiple packages is prepared by breaking down the project into smaller packages and creating a schedule for each package.
Break down the project into smaller packages
Create a schedule for each package
Identify dependencies between packages
Integrate all schedules to create a master schedule
Update the schedule regularly to reflect progress and changes
I applied via Approached by Company and was interviewed in Jun 2024. There was 1 interview round.
Commercial building cost can vary depending on factors like location, size, materials, and amenities.
Factors influencing commercial building cost include location, size, materials, and amenities.
Cost can range from $100 to $500 per square foot depending on the above factors.
Additional costs may include permits, labor, design fees, and land acquisition.
Examples of commercial building costs: $1 million for a small office...
The cost of a residential building can vary depending on factors such as location, size, materials used, and labor costs.
Location plays a significant role in determining the cost of a residential building. Urban areas tend to have higher construction costs compared to rural areas.
The size of the building also impacts the cost. Larger buildings require more materials and labor, resulting in higher costs.
The quality of m...
I was working at XYZ Architecture Firm as a Senior Architect for the past 5 years.
Worked as a Senior Architect at XYZ Architecture Firm
Had been with the firm for 5 years
Involved in designing commercial and residential projects
My previous experience was diverse and enriching, allowing me to work on a variety of projects and hone my skills in architecture.
Worked on residential, commercial, and institutional projects
Led a team of architects and designers to successfully complete projects within deadlines
Collaborated with clients to understand their needs and deliver innovative design solutions
Utilized sustainable design principles in all proje...
Project coordination
Raj Kumar kanojiya, rohit sood
I applied via Naukri.com and was interviewed before Feb 2022. There were 2 interview rounds.
I will leverage my expertise in project planning to enhance efficiency, drive innovation, and foster collaboration within the organization.
Implement data-driven project management tools to streamline processes, reducing project timelines by up to 20%.
Foster a culture of collaboration by organizing cross-departmental workshops, leading to improved communication and project outcomes.
Utilize my experience in risk manageme...
I applied via Approached by Company and was interviewed before Dec 2021. There were 2 interview rounds.
Top trending discussions
I applied via Naukri.com and was interviewed in Oct 2020. There were 4 interview rounds.
posted on 23 Aug 2022
I applied via Referral and was interviewed before Aug 2021. There were 3 interview rounds.
Reasoning questions and General Awareness
based on 4 interview experiences
Difficulty level
Duration
based on 22 reviews
Rating in categories
Senior Manager Sales & Marketing
5
salaries
| ₹6 L/yr - ₹7.2 L/yr |
Senior Engineer
3
salaries
| ₹7 L/yr - ₹7.6 L/yr |
Sales Officer
3
salaries
| ₹3 L/yr - ₹4.2 L/yr |
Planning Engineer
3
salaries
| ₹5.8 L/yr - ₹5.8 L/yr |
General Manager Project
3
salaries
| ₹39 L/yr - ₹39 L/yr |
Cognizant
Teleperformance
iEnergizer
Reliance Retail