Upload Button Icon Add office photos

Filter interviews by

Uttar Pradesh Metro Rail Corporation Team Lead Interview Questions and Answers

Updated 26 Jun 2023

Uttar Pradesh Metro Rail Corporation Team Lead Interview Experiences

1 interview found

Team Lead Interview Questions & Answers

user image Anonymous

posted on 26 Jun 2023

Interview experience
1
Bad
Difficulty level
Easy
Process Duration
2-4 weeks
Result
-

I applied via Approached by Company and was interviewed before Jun 2022. There were 4 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - One-on-one 

(2 Questions)

  • Q1. Will you work for us
  • Ans. How quickly you can join us
  • Answered Anonymously
  • Q2. We will make you manager after 5year later
Round 3 - Technical 

(2 Questions)

  • Q1. No technical question ask
  • Q2. Even interviewer don't know any technical questions
Round 4 - HR 

(3 Questions)

  • Q1. We will increas you salary after 6 month later
  • Q2. But HR left the company
  • Q3. Next HR Said no we will not increase you salary till 10 year

Interview questions from similar companies

I applied via Company Website and was interviewed in Jan 2021. There were 3 interview rounds.

Interview Questionnaire 

5 Questions

  • Q1. Which documents needs to be maintained at PMC office?
  • Ans. 

    Various documents need to be maintained at the PMC office.

    • Project proposals and contracts

    • Budget and financial reports

    • Meeting minutes and agendas

    • Employee records and HR documents

    • Project progress reports

    • Legal and regulatory documents

    • Correspondence and communication records

    • Inventory and asset management records

  • Answered by AI
  • Q2. How project controlling is exercised?
  • Ans. 

    Project controlling is exercised through monitoring, measuring, and adjusting project activities to ensure they align with project goals.

    • Project controlling involves setting up a project plan with clear goals and objectives.

    • Regular monitoring and measurement of project activities against the plan is necessary.

    • Adjustments are made to the project plan as needed to ensure alignment with project goals.

    • Project controlling a...

  • Answered by AI
  • Q3. What are the limits of deviation of BOQ quantities as per CPWD norms?
  • Ans. 

    The limits of deviation of BOQ quantities as per CPWD norms depend on the type of work and range from -5% to +10%.

    • The limits of deviation are specified in the CPWD Manual.

    • For civil works, the limit of deviation is -5% to +10%.

    • For electrical and mechanical works, the limit of deviation is -10% to +15%.

    • For interior works, the limit of deviation is -10% to +20%.

    • The limits of deviation may vary depending on the type of wor...

  • Answered by AI
  • Q4. What are the limitations of mivan shuttering?
  • Ans. 

    Mivan shuttering has limitations in terms of design flexibility and cost-effectiveness.

    • Mivan shuttering is not suitable for complex designs or irregular shapes.

    • It requires skilled labor and specialized equipment, which can increase the overall cost.

    • It may not be suitable for small-scale projects due to the high initial investment.

    • It may not be suitable for projects with limited space or difficult access.

    • It may not be s...

  • Answered by AI
  • Q5. CPWD norms for working space area for calculating earthworm quantity in excavation of basement
  • Ans. 

    CPWD norms for working space area for calculating earthworm quantity in excavation of basement

    • CPWD recommends a working space area of 1.5 times the depth of excavation for calculating earthworm quantity

    • For example, if the depth of excavation is 2 meters, the working space area should be 3 meters

    • This calculation is important for determining the amount of organic matter in the soil and the need for soil improvement

    • CPWD g...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be positive, assertive and goal oriented. Adhere to your good habits.

I applied via Company Website and was interviewed in Jan 2021. There were 3 interview rounds.

Interview Questionnaire 

5 Questions

  • Q1. Which documents needs to be maintained at PMC office?
  • Ans. 

    Various documents need to be maintained at the PMC office.

    • Project proposals and contracts

    • Budget and financial reports

    • Meeting minutes and agendas

    • Employee records and HR documents

    • Project progress reports

    • Legal and regulatory documents

    • Correspondence and communication records

    • Inventory and asset management records

  • Answered by AI
  • Q2. How project controlling is exercised?
  • Ans. 

    Project controlling is exercised through monitoring, measuring, and adjusting project activities to ensure they align with project goals.

    • Project controlling involves setting up a project plan with clear goals and objectives.

    • Regular monitoring and measurement of project activities against the plan is necessary.

    • Adjustments are made to the project plan as needed to ensure alignment with project goals.

    • Project controlling a...

  • Answered by AI
  • Q3. What are the limits of deviation of BOQ quantities as per CPWD norms?
  • Ans. 

    The limits of deviation of BOQ quantities as per CPWD norms depend on the type of work and range from -5% to +10%.

    • The limits of deviation are specified in the CPWD Manual.

    • For civil works, the limit of deviation is -5% to +10%.

    • For electrical and mechanical works, the limit of deviation is -10% to +15%.

    • For interior works, the limit of deviation is -10% to +20%.

    • The limits of deviation may vary depending on the type of wor...

  • Answered by AI
  • Q4. What are the limitations of mivan shuttering?
  • Ans. 

    Mivan shuttering has limitations in terms of design flexibility and cost-effectiveness.

    • Mivan shuttering is not suitable for complex designs or irregular shapes.

    • It requires skilled labor and specialized equipment, which can increase the overall cost.

    • It may not be suitable for small-scale projects due to the high initial investment.

    • It may not be suitable for projects with limited space or difficult access.

    • It may not be s...

  • Answered by AI
  • Q5. CPWD norms for working space area for calculating earthworm quantity in excavation of basement
  • Ans. 

    CPWD norms for working space area for calculating earthworm quantity in excavation of basement

    • CPWD recommends a working space area of 1.5 times the depth of excavation for calculating earthworm quantity

    • For example, if the depth of excavation is 2 meters, the working space area should be 3 meters

    • This calculation is important for determining the amount of organic matter in the soil and the need for soil improvement

    • CPWD g...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be positive, assertive and goal oriented. Adhere to your good habits.

Uttar Pradesh Metro Rail Corporation Interview FAQs

How many rounds are there in Uttar Pradesh Metro Rail Corporation Team Lead interview?
Uttar Pradesh Metro Rail Corporation interview process usually has 4 rounds. The most common rounds in the Uttar Pradesh Metro Rail Corporation interview process are Resume Shortlist, One-on-one Round and Technical.
What are the top questions asked in Uttar Pradesh Metro Rail Corporation Team Lead interview?

Some of the top questions asked at the Uttar Pradesh Metro Rail Corporation Team Lead interview -

  1. Next HR Said no we will not increase you salary till 10 y...read more
  2. Even interviewer don't know any technical questi...read more
  3. We will increas you salary after 6 month la...read more

Tell us how to improve this page.

Uttar Pradesh Metro Rail Corporation Team Lead Interview Process

based on 1 interview

Interview experience

1
  
Bad
View more
Uttar Pradesh Metro Rail Corporation Team Lead Salary
based on 6 salaries
₹2 L/yr - ₹3 L/yr
72% less than the average Team Lead Salary in India
View more details

Uttar Pradesh Metro Rail Corporation Team Lead Reviews and Ratings

based on 3 reviews

1.8/5

Rating in categories

1.3

Skill development

1.1

Work-life balance

1.1

Salary

1.3

Job security

1.1

Company culture

1.1

Promotions

1.1

Work satisfaction

Explore 3 Reviews and Ratings
Joint General Manager
9 salaries
unlock blur

₹26 L/yr - ₹28 L/yr

Account Assistant
9 salaries
unlock blur

₹2 L/yr - ₹7.2 L/yr

TOM Operator
9 salaries
unlock blur

₹1.7 L/yr - ₹2.7 L/yr

Assistant Manager
6 salaries
unlock blur

₹6 L/yr - ₹15 L/yr

Team Lead
6 salaries
unlock blur

₹2 L/yr - ₹3 L/yr

Explore more salaries
Compare Uttar Pradesh Metro Rail Corporation with

Delhi Metro Rail Corporation

4.1
Compare

Mumbai Metro Rail Corporation

4.0
Compare

Bangalore Metro Rail Corporation

3.8
Compare

Kolkata Metro Rail Corporation

4.5
Compare
Did you find this page helpful?
Yes No
write
Share an Interview