Earthwork refers to the process of moving, excavating, and compacting soil and rock to prepare the ground for construction.
Earthwork involves activities such as excavation, grading, compaction, and backfilling.
It is essential for creating a stable foundation for roads, buildings, and other structures.
Earthwork also includes the removal of unwanted materials and the addition of necessary materials to achieve the desired...
GSB stands for Granular Sub Base and WMM stands for Wet Mix Macadam. GSB WMM is a type of road construction method using layers of granular materials.
GSB is the layer of granular material placed on the subgrade of a road to provide a stable foundation.
WMM is a mixture of aggregates, filler, and water laid on the GSB layer to form a strong base for the road.
GSB WMM construction involves compacting each layer properly to...
Top trending discussions
I applied via Referral and was interviewed before Jan 2020. There were 3 interview rounds.
The standard MDD (Maximum Dry Density) of subgrade soil varies depending on the specific project requirements and soil characteristics.
The standard MDD of subgrade soil is determined through laboratory tests.
It is influenced by factors such as soil type, compaction method, moisture content, and compaction effort.
Different soil types have different standard MDD values.
For example, the standard MDD of a sandy soil may be...
TCS stands for Tata Consultancy Services.
TCS is an Indian multinational IT services and consulting company.
It is one of the largest IT service providers in the world.
TCS offers a wide range of services including software development, infrastructure management, and consulting.
The company has a strong presence in the highway engineering sector, providing technology solutions for transportation and infrastructure projects...
The quantity of soil in embankment or subgrade can be determined using the method of average end area.
The method of average end area involves taking cross-sectional measurements at regular intervals along the embankment or subgrade.
The cross-sectional measurements are used to calculate the area of each section.
The average area is then multiplied by the length of the embankment or subgrade to determine the volume of soi...
The test to determine FDD of soil is called the Falling Head Permeability Test.
Falling Head Permeability Test is used to determine the coefficient of permeability of soil.
It involves measuring the time taken for water to flow through a soil sample under a constant head.
The test is conducted using a permeameter, which consists of a cylindrical tube with a soil sample and a falling head of water.
The coefficient of permea...
IRC recommends 8-10 passes of vibro roller for full compaction.
IRC (Indian Road Congress) recommends 8-10 passes of vibro roller for full compaction.
The number of passes may vary depending on factors such as soil type, moisture content, and thickness of the layer.
In some cases, additional passes may be required to achieve the desired level of compaction.
It is important to conduct regular tests to ensure that the desire...
The question is asking about the number of passes of different types of vibro rollers for highway construction.
6 passes of vibro roller 1P
6 passes of vibro roller 1MV
6 passes of vibro roller 1V
6 passes of vibro roller 2P
posted on 22 Nov 2024
Dowel bars are used in PQC to transfer load and prevent faulting in joints.
Dowel bars help in transferring loads between adjacent slabs, reducing stresses at joints
They prevent faulting by maintaining alignment and load transfer across joints
Improves overall performance and durability of the pavement
Commonly made of steel or fiberglass materials
posted on 18 Oct 2023
I applied via Company Website and was interviewed before Oct 2022. There were 3 interview rounds.
posted on 11 May 2018
I applied via Naukri.com and was interviewed before May 2017. There was 1 interview round.
The density of soil in the embankment layer varies depending on the type of soil and compaction methods used.
The density of soil in the embankment layer is typically measured in terms of dry density or wet density.
Dry density refers to the mass of solid soil particles per unit volume of soil, while wet density includes the mass of water as well.
The density of soil in the embankment layer is influenced by factors such a...
posted on 17 Jul 2017
I was interviewed before Jul 2016.
based on 1 interview
Interview experience
Civil Site Engineer
19
salaries
| ₹2.3 L/yr - ₹4.2 L/yr |
Project Manager
12
salaries
| ₹10 L/yr - ₹18.2 L/yr |
Store Executive
10
salaries
| ₹2.7 L/yr - ₹4 L/yr |
Site Engineer
10
salaries
| ₹2.3 L/yr - ₹4.2 L/yr |
Civil Engineer
8
salaries
| ₹2.4 L/yr - ₹4.5 L/yr |
Larsen & Toubro Limited
Tata Projects
GMR Group
Reliance Infrastructure