Upload Button Icon Add office photos
Engaged Employer

i

This company page is being actively managed by Scc Infrastructure Team. If you also belong to the team, you can get access from here

Scc Infrastructure Verified Tick

Compare button icon Compare button icon Compare

Filter interviews by

Clear (1)

Scc Infrastructure HSE Manager Interview Questions and Answers

Updated 17 Sep 2022

Scc Infrastructure HSE Manager Interview Experiences

1 interview found

HSE Manager Interview Questions & Answers

user image Anonymous

posted on 17 Sep 2022

I applied via Naukri.com and was interviewed in Aug 2022. There were 2 interview rounds.

Round 1 - HR 

(1 Question)

  • Q1. Asked about previous knowledge and SCC requirements
Round 2 - One-on-one 

(1 Question)

  • Q1. Past experience sharing

Interview Preparation Tips

Interview preparation tips for other job seekers - Base on your past experience sharing and question what you mentioned in your CV

Interview questions from similar companies

I was interviewed before Oct 2016.

Interview Questionnaire 

2 Questions

  • Q1.  turbine erection alignment and comissioning procedure
  • Ans. 

    Turbine erection alignment and commissioning procedure involves the process of aligning and commissioning a turbine for optimal performance.

    • Turbine erection alignment involves ensuring the turbine is properly aligned with the foundation and other components.

    • Commissioning procedure includes testing and verifying the functionality of the turbine.

    • Alignment is typically done using laser alignment tools to ensure precise po...

  • Answered by AI
  • Q2. Turbine erection sequence
  • Ans. 

    The turbine erection sequence refers to the specific order in which the components of a turbine are assembled and installed.

    • The foundation is prepared and the anchor bolts are installed.

    • The base frame is positioned and aligned with the anchor bolts.

    • The turbine tower sections are lifted and assembled on top of the base frame.

    • The nacelle, which houses the turbine's generator and other components, is installed on top of t...

  • Answered by AI

Interview Preparation Tips

Round: HR Interview
Experience: they are satisfy with my answers
Tips: explain exactly what you know

Round: Technical Interview
Experience: i explain what i know exactly

Skills: Thermal Power Plant Engineering

Interview Questionnaire 

2 Questions

  • Q1. The question was regarding the present role I'm assigned and how the implementation of scheduling tools can help planning of E.P.C. in their present business unit.
  • Q2. Technical question on my present project scheduling role & any other digital concept i'm associated with it currently.

Interview Preparation Tips

Round: Resume Shortlist
Experience: These days, not many companies shortlists the candidates by themselves instead they hire third parties in order to minimize the resources and cost burden. These talent acquisition members initially filters the resumes based upon the Years of Experience & the key skills which they receive from their parent companies by matching with the 70-80 % kind of similar roles of the candidates.

In my case, both my experience & roles are perfectly in sync with their requirements. So, they contacted me via naukri.com and asked me to share the updated resume & within a week I got the confirmation of my resume shortlisting & date for the 1st round of interview.

Round: Test
Experience: Primavera Scheduling Test

I was interviewed before Mar 2020.

Interview Questionnaire 

2 Questions

  • Q1. Technical
  • Q2. Family background

Interview Preparation Tips

Interview preparation tips for other job seekers - Same

I applied via Naukri.com and was interviewed in Jul 2019. There were 3 interview rounds.

Interview Questionnaire 

4 Questions

  • Q1. Asked about To mentioned areas of weakness of L&T, or needs improvement?
  • Q2. How to make check or maintain elevation of Underground Piping.
  • Ans. 

    Maintain elevation of underground piping by using level instruments and proper installation techniques.

    • Use a level instrument to check the elevation of the piping during installation.

    • Ensure that the piping is installed with a consistent slope to prevent low spots where water can accumulate.

    • Regularly inspect the piping to ensure that it has not shifted or settled, which can affect the elevation.

    • Consider using supports o...

  • Answered by AI
  • Q3. My Job specific role & responsibility, in previous organisation.
  • Ans. 

    In my previous role as Assistant Manager, I was responsible for overseeing daily operations, managing staff, and ensuring customer satisfaction.

    • Managed a team of employees and delegated tasks effectively

    • Handled customer complaints and resolved issues in a timely manner

    • Created and implemented strategies to improve efficiency and productivity

    • Collaborated with other departments to achieve company goals

    • Conducted performanc

  • Answered by AI
  • Q4. Welding Electrodes for different materials.
  • Ans. 

    Welding electrodes are chosen based on the material being welded. Different materials require different types of electrodes.

    • Electrodes for mild steel have a coating that produces a stable arc and minimal spatter.

    • Stainless steel electrodes have a coating that resists corrosion and produces a smooth, clean weld.

    • Cast iron electrodes have a high nickel content to prevent cracking.

    • Aluminum electrodes have a special coating ...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Just Be confidant, Be Humble, Be aware about your roles & Responsibility during job Period.

I applied via Naukri.com and was interviewed before Oct 2019. There were 3 interview rounds.

Interview Questionnaire 

2 Questions

  • Q1. Concrete rate breakup, Asking rate
  • Q2. Unique thumbrules breakup and unit conversion

Interview Preparation Tips

Interview preparation tips for other job seekers - I explained the concrete breakup with the margin of sub contractor, also explain the subcontractor unit rate breakup and Asking rate is anything like in cricket how many balla are remaining and how much u need to score more. Like.

Joining in L&T is my (No) for evey civil engineers dream..
Thumbrules break up
Rebar - (D2/162) ----(Area x Lengh x 7850).
Like

I applied via Walk-in and was interviewed before Nov 2019. There were 3 interview rounds.

Interview Questionnaire 

5 Questions

  • Q1. Regarding Technical questions interviewer asked me, like how to construct flexible pavement road ?
  • Q2. GSB CBR?
  • Q3. For One Lakh cum of soil dumping and compaction how many days require to finish ? and what is requirement of machinery unit?
  • Ans. 

    The duration and machinery requirement for dumping and compacting one lakh cum of soil.

    • The duration depends on the capacity of the machinery and the number of machines used.

    • The type of soil and the site conditions also affect the duration.

    • On average, it takes around 30-45 days to complete the task.

    • The machinery required includes excavators, bulldozers, dump trucks, and compactors.

  • Answered by AI
  • Q4.  Why we need to do C&G?
  • Q5. What is different between Minor bridge and Major bridge?
  • Ans. 

    Minor bridges are usually shorter and have a lower weight capacity than major bridges.

    • Major bridges are typically longer and have a higher weight capacity than minor bridges.

    • Minor bridges are often used for pedestrian or bike traffic, while major bridges are used for vehicles and heavy machinery.

    • Major bridges may require more maintenance and have a higher construction cost than minor bridges.

    • Examples of major bridges i...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be confident, Be bold and talk free. Don't fear about what you don't know, explain what are you well known and believe your knowledge and keep going and learning.

I applied via Campus Placement and was interviewed before Feb 2021. There were 2 interview rounds.

Round 1 - Aptitude Test 

3 tests are conducted

Round 2 - Technical 

(4 Questions)

  • Q1. In which are u have sound knowledge ? Field or system
  • Q2. Difference between DCS and plc
  • Ans. 

    DCS is used for continuous processes while PLC is used for discrete processes.

    • DCS stands for Distributed Control System and is used for continuous processes like oil refining, power generation, etc.

    • PLC stands for Programmable Logic Controller and is used for discrete processes like assembly lines, packaging machines, etc.

    • DCS is designed to handle large amounts of data from multiple sources and control multiple processe...

  • Answered by AI
  • Q3. How control valve works
  • Ans. 

    Control valves regulate fluid flow by adjusting the size of the valve opening.

    • Control valves are used in various industries such as oil and gas, chemical, and power generation.

    • They work by adjusting the size of the valve opening to regulate the flow of fluid.

    • The valve opening is controlled by a signal from a controller, which can be manual or automated.

    • Control valves can be classified into different types such as globe...

  • Answered by AI
  • Q4. How pressure switch works
  • Ans. 

    A pressure switch is a device that monitors pressure levels and triggers an action when a certain pressure is reached.

    • Pressure switch consists of a sensing element, switch mechanism, and a pressure port.

    • When the pressure reaches a certain level, the sensing element triggers the switch mechanism to open or close an electrical circuit.

    • Pressure switches are used in various applications such as HVAC systems, water pumps, a

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - For apptitude my approach was not to attempt all questions but ensure that whatever i am able to answer those are correct...hence i took my sweet time to answer each question.

Skills evaluated in this interview

I applied via Approached by Company and was interviewed before Mar 2021. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. It asks your old experience based questions

Interview Preparation Tips

Interview preparation tips for other job seekers - Interview Basicaly depends on your Luck. What he asked, if you answere, then you are selected, and not answering then you are rejected.

I applied via Recruitment Consultant and was interviewed before Nov 2020. There were 4 interview rounds.

Interview Questionnaire 

2 Questions

  • Q1. Three people seat and asked Just simple technical questions frequently from civil engineering in hindi & English and watched the confidence level also. Some difficult questions is also there but they have ...
  • Q2. Forget now because long years ago it has been done.

Interview Preparation Tips

Interview preparation tips for other job seekers - Be confident & should have technical knowledge.
Contribute & help others!
anonymous
You can choose to be anonymous

Scc Infrastructure Interview FAQs

How many rounds are there in Scc Infrastructure HSE Manager interview?
Scc Infrastructure interview process usually has 2 rounds. The most common rounds in the Scc Infrastructure interview process are HR and One-on-one Round.

Recently Viewed

INTERVIEWS

AECOM

No Interviews

INTERVIEWS

Currie & Brown

10 top interview questions

SALARIES

HRH Construction

SALARIES

VIKRAN Engineering & Exim

JOBS

Zend Consulting Services

No Jobs

INTERVIEWS

Edureka

No Interviews

JOBS

Michael Page International

No Jobs

SALARIES

Currie & Brown

INTERVIEWS

Conserve Solution

No Interviews

COMPANY BENEFITS

Motilal Oswal Financial Services

No Benefits

Tell us how to improve this page.

Scc Infrastructure HSE Manager Reviews and Ratings

based on 1 review

1.0/5

Rating in categories

1.0

Skill development

1.0

Work-life balance

1.0

Salary

1.0

Job security

1.0

Company culture

1.0

Promotions

1.0

Work satisfaction

Explore 1 Review and Rating
Civil Site Engineer
19 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Project Manager
12 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Site Engineer
10 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Store Executive
9 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Civil Engineer
8 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Explore more salaries
Compare Scc Infrastructure with

Larsen & Toubro Limited

4.0
Compare

Tata Projects

4.2
Compare

GMR Group

4.0
Compare

Reliance Infrastructure

4.1
Compare
Did you find this page helpful?
Yes No
write
Share an Interview