  • Q1. Two equipment in site but equipment in between goes to pipe centre fw welding after complete how to the hydrotest?
  • Ans. 

    The hydrotest can be conducted after completing the welding of the pipe center fw.

    • Ensure that the equipment on both ends of the pipe are ready for the hydrotest.

    • Isolate the section of the pipe where the welding was done using blinds or spectacle blinds.

    • Connect the hydrotest pump to one end of the pipe and fill it with water.

    • Increase the pressure gradually to the required test pressure and hold it for the specified dura...

  • Answered by AI

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
-

I applied via Naukri.com and was interviewed in Nov 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(13 Questions)

  • Q1. How much carbon percentage in Carbon Steel
  • Ans. 

    The carbon percentage in carbon steel varies from 0.05% to 2.0% depending on the grade.

    • Carbon steel is an alloy of iron and carbon.

    • The amount of carbon in carbon steel determines its strength and hardness.

    • Low carbon steel contains less than 0.3% carbon, while high carbon steel contains more than 0.6% carbon.

    • Some common grades of carbon steel and their carbon percentage are: A36 (0.26%), 1018 (0.18%), and 1045 (0.45%).

  • Answered by AI
  • Q2. What is difference between concentric and eccentric reducer
  • Ans. 

    Concentric reducers have a common centerline while eccentric reducers have an offset centerline.

    • Concentric reducers are used in vertical piping systems to prevent accumulation of air pockets.

    • Eccentric reducers are used in horizontal piping systems to prevent accumulation of solids or liquids.

    • Concentric reducers are symmetrical while eccentric reducers are not.

    • Concentric reducers are easier to manufacture and install th

  • Answered by AI
  • Q3. Which reinforcement fittings used in piping
  • Ans. 

    Reinforcement fittings are used to strengthen and support piping systems.

    • Common reinforcement fittings include tees, elbows, reducers, and couplings.

    • Telescoping fittings are used to adjust the length of piping systems.

    • Flange fittings are used to connect pipes to other equipment or structures.

    • Saddles are used to support piping systems on walls or ceilings.

    • Reinforcement fittings can be made of various materials, includin...

  • Answered by AI
  • Q4. Why elbo let used in piping
  • Ans. 

    Elbow lets change the direction of flow in piping system.

    • Elbows are used to change the direction of flow in a piping system.

    • They come in different angles such as 45°, 90° and 180°.

    • They are available in different materials such as PVC, copper, steel, etc.

    • Elbows can be welded or threaded onto the piping system.

    • They are commonly used in plumbing, HVAC, and industrial piping systems.

  • Answered by AI
  • Q5. If we have to replace bypass valve on top of vessel and plant is running, then how to replace that valve ??
  • Ans. 

    The bypass valve can be replaced by isolating the vessel, depressurizing it, and then replacing the valve.

    • Isolate the vessel by closing the inlet and outlet valves

    • Depressurize the vessel by venting the gas or liquid

    • Remove the old valve and install the new one

    • Repressurize the vessel and open the inlet and outlet valves

  • Answered by AI
  • Q6. What is Permit to work
  • Ans. 

    Permit to work is a formal written system used to control high-risk activities.

    • It is a document that outlines the work to be done and the hazards associated with it.

    • It is used to ensure that all necessary safety precautions are taken before work begins.

    • It is issued by a competent authority and must be signed by all parties involved in the work.

    • Examples include hot work permits, confined space permits, and excavation pe

  • Answered by AI
  • Q7. Tell me about yourself and your experience
  • Q8. What is isolation and how many types of isolation
  • Ans. 

    Isolation is the process of separating a system or equipment from its energy source to ensure safety during maintenance or repair.

    • Isolation involves disconnecting a system or equipment from its power source, locking it out, and tagging it to prevent accidental re-energization.

    • There are two types of isolation: electrical isolation and mechanical isolation.

    • Electrical isolation involves disconnecting the electrical supply...

  • Answered by AI
  • Q9. What is positive isolation
  • Ans. 

    Positive isolation is the process of completely isolating a section of a system to prevent any flow or transfer of material.

    • Positive isolation is achieved by using valves, blinds, or other physical barriers to completely block the flow of material.

    • It is important for safety and maintenance purposes, as it allows workers to safely perform tasks without the risk of exposure to hazardous materials.

    • Examples of positive iso...

  • Answered by AI
  • Q10. How to do positive isolation
  • Ans. 

    Positive isolation is the process of completely isolating a section of piping or equipment from the rest of the system to perform maintenance or repairs.

    • Identify the section of piping or equipment that needs to be isolated

    • Close all valves and block all lines leading to and from the section

    • Use blind flanges or spectacle blinds to physically block the section

    • Ensure that the isolation is secure and pressure tested before ...

  • Answered by AI
  • Q11. When we do nitrogen purging and why it's required
  • Ans. 

    Nitrogen purging is done to remove impurities and oxygen from pipelines before commissioning or maintenance work.

    • Nitrogen purging is done to create an inert atmosphere inside the pipeline to prevent explosions or fires.

    • It is required before commissioning or maintenance work to remove impurities and oxygen from the pipeline.

    • Nitrogen purging is also done to prevent corrosion and contamination of the pipeline.

    • It is common...

  • Answered by AI
  • Q12. What is difference between pipe and tube
  • Ans. 

    Pipes are used to transport fluids and gases, while tubes are used for structural purposes.

    • Pipes have a standardized outer diameter and wall thickness, while tubes have a standardized inner diameter and wall thickness.

    • Pipes are typically round, while tubes can be round, square, or rectangular.

    • Pipes are often used in plumbing and HVAC systems, while tubes are used in construction and engineering applications.

    • Pipes are u...

  • Answered by AI
  • Q13. Which pipe material or standard used in past experience
  • Ans. 

    I have experience working with various pipe materials and standards including carbon steel, stainless steel, and PVC.

    • I have worked with carbon steel pipes in a power plant project.

    • I have also worked with stainless steel pipes in a pharmaceutical plant project.

    • In a water treatment plant project, I have worked with PVC pipes.

    • I am familiar with ASME B31.3, API 5L, and ASTM standards for pipe materials and welding procedur

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Read your resume carefully, be confident, eye contact and imagine that you knew better than them , if you don't know say I don't know , don't answer in stories , always prepare for interview as per company requirements.

I applied via Recruitment Consulltant and was interviewed before Sep 2021. There was 1 interview round.

Round 1 - HR 

(1 Question)

  • Q1. What do you face a big problem during turnaround
  • Ans. Can you explained basic difference between ASME and ASTM
  • Answered Anonymously

Interview Preparation Tips

Interview preparation tips for other job seekers - I face normally and heard carefully question,
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Feb 2024. There were 2 interview rounds.

Round 1 - Aptitude Test 

Question answer related piping job ,material related, manpower handling etc...

Round 2 - Technical 

(5 Questions)

  • Q1. Piping related question, Piping material astm code
  • Q2. Types of piping drawing
  • Ans. 

    Types of piping drawings include Piping and Instrumentation Diagrams (P&IDs), Isometric drawings, and Orthographic drawings.

    • Piping and Instrumentation Diagrams (P&IDs) show the piping system along with instruments and control devices.

    • Isometric drawings show the 3D representation of the piping system.

    • Orthographic drawings show the top, front, and side views of the piping system.

  • Answered by AI
  • Q3. Difference b/w construction and fabrication drawing?
  • Ans. 

    Construction drawings show how a structure will be built, while fabrication drawings provide detailed instructions for manufacturing individual components.

    • Construction drawings focus on overall structure layout and dimensions

    • Fabrication drawings provide detailed instructions for manufacturing individual components

    • Construction drawings are used by contractors on site, fabrication drawings are used by manufacturers in wo...

  • Answered by AI
  • Q4. Piping material code ?
  • Ans. 

    Piping material code refers to the standards and specifications used for selecting materials for piping systems.

    • Piping material codes are used to ensure the proper selection of materials based on factors like pressure, temperature, and fluid being transported.

    • Common piping material codes include ASME B31.3 for process piping, ASTM for materials specifications, and API for oil and gas piping.

    • These codes provide guidelin...

  • Answered by AI
  • Q5. Difference b/w pipe and tubes
  • Ans. 

    Pipes are used to transport fluids or gases, while tubes are used for structural applications or heat transfer.

    • Pipes are measured by their inside diameter, while tubes are measured by their outside diameter.

    • Pipes are typically round in shape, while tubes can be round, square, or rectangular.

    • Pipes are commonly used in plumbing, HVAC systems, and oil and gas industries, while tubes are used in construction, automotive, a

  • Answered by AI

Interview Preparation Tips

Topics to prepare for Reliance Industries Piping Engineer interview:
  • Piping
  • Statatic Equipment
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(5 Questions)

  • Q1. Work experience, country name, types of work, manpower handling etc
  • Q2. Punjlloyd ltd ,brouge 2 project,abudhabi
  • Q3. Allkulaib int kuwait ,subiya power plant
  • Q4. Dyam punjlloyd ,saudi arabia ,satrop projects
  • Q5. Towell eng, oman orpic (srip extension projects)
Round 3 - Aptitude Test 

Manpower nhandling only

Interview Preparation Tips

Interview preparation tips for other job seekers - try a EPC company blike perrofac

I applied via Recruitment Consulltant and was interviewed in Aug 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Properly align and format text in your resume. A recruiter will have to spend more time reading poorly aligned text, leading to high chances of rejection.
View all tips
Round 2 - Interview 

(2 Questions)

  • Q1. General questions related to past work experience and previous job changes.
  • Q2. It was an interview to check personality traits rather that technical knowledge

Interview Preparation Tips

Interview preparation tips for other job seekers - Remain honest, positive and calm during the interview. Don’t say negative things about past employers/ jobs.
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
-

I applied via Naukri.com and was interviewed in Nov 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Double-check your resume for any spelling mistakes. The recruiter may consider spelling mistakes as careless behavior or poor communication skills.
View all tips
Round 2 - Technical 

(13 Questions)

  • Q1. How much carbon percentage in Carbon Steel
  • Ans. 

    The carbon percentage in carbon steel varies from 0.05% to 2.0% depending on the grade.

    • Carbon steel is an alloy of iron and carbon.

    • The amount of carbon in carbon steel determines its strength and hardness.

    • Low carbon steel contains less than 0.3% carbon, while high carbon steel contains more than 0.6% carbon.

    • Some common grades of carbon steel and their carbon percentage are: A36 (0.26%), 1018 (0.18%), and 1045 (0.45%).

  • Answered by AI
  • Q2. What is difference between concentric and eccentric reducer
  • Ans. 

    Concentric reducers have a common centerline while eccentric reducers have an offset centerline.

    • Concentric reducers are used in vertical piping systems to prevent accumulation of air pockets.

    • Eccentric reducers are used in horizontal piping systems to prevent accumulation of solids or liquids.

    • Concentric reducers are symmetrical while eccentric reducers are not.

    • Concentric reducers are easier to manufacture and install th

  • Answered by AI
  • Q3. Which reinforcement fittings used in piping
  • Ans. 

    Reinforcement fittings are used to strengthen and support piping systems.

    • Common reinforcement fittings include tees, elbows, reducers, and couplings.

    • Telescoping fittings are used to adjust the length of piping systems.

    • Flange fittings are used to connect pipes to other equipment or structures.

    • Saddles are used to support piping systems on walls or ceilings.

    • Reinforcement fittings can be made of various materials, includin...

  • Answered by AI
  • Q4. Why elbo let used in piping
  • Ans. 

    Elbow lets change the direction of flow in piping system.

    • Elbows are used to change the direction of flow in a piping system.

    • They come in different angles such as 45°, 90° and 180°.

    • They are available in different materials such as PVC, copper, steel, etc.

    • Elbows can be welded or threaded onto the piping system.

    • They are commonly used in plumbing, HVAC, and industrial piping systems.

  • Answered by AI
  • Q5. If we have to replace bypass valve on top of vessel and plant is running, then how to replace that valve ??
  • Ans. 

    The bypass valve can be replaced by isolating the vessel, depressurizing it, and then replacing the valve.

    • Isolate the vessel by closing the inlet and outlet valves

    • Depressurize the vessel by venting the gas or liquid

    • Remove the old valve and install the new one

    • Repressurize the vessel and open the inlet and outlet valves

  • Answered by AI
  • Q6. What is Permit to work
  • Ans. 

    Permit to work is a formal written system used to control high-risk activities.

    • It is a document that outlines the work to be done and the hazards associated with it.

    • It is used to ensure that all necessary safety precautions are taken before work begins.

    • It is issued by a competent authority and must be signed by all parties involved in the work.

    • Examples include hot work permits, confined space permits, and excavation pe

  • Answered by AI
  • Q7. Tell me about yourself and your experience
  • Q8. What is isolation and how many types of isolation
  • Ans. 

    Isolation is the process of separating a system or equipment from its energy source to ensure safety during maintenance or repair.

    • Isolation involves disconnecting a system or equipment from its power source, locking it out, and tagging it to prevent accidental re-energization.

    • There are two types of isolation: electrical isolation and mechanical isolation.

    • Electrical isolation involves disconnecting the electrical supply...

  • Answered by AI
  • Q9. What is positive isolation
  • Ans. 

    Positive isolation is the process of completely isolating a section of a system to prevent any flow or transfer of material.

    • Positive isolation is achieved by using valves, blinds, or other physical barriers to completely block the flow of material.

    • It is important for safety and maintenance purposes, as it allows workers to safely perform tasks without the risk of exposure to hazardous materials.

    • Examples of positive iso...

  • Answered by AI
  • Q10. How to do positive isolation
  • Ans. 

    Positive isolation is the process of completely isolating a section of piping or equipment from the rest of the system to perform maintenance or repairs.

    • Identify the section of piping or equipment that needs to be isolated

    • Close all valves and block all lines leading to and from the section

    • Use blind flanges or spectacle blinds to physically block the section

    • Ensure that the isolation is secure and pressure tested before ...

  • Answered by AI
  • Q11. When we do nitrogen purging and why it's required
  • Ans. 

    Nitrogen purging is done to remove impurities and oxygen from pipelines before commissioning or maintenance work.

    • Nitrogen purging is done to create an inert atmosphere inside the pipeline to prevent explosions or fires.

    • It is required before commissioning or maintenance work to remove impurities and oxygen from the pipeline.

    • Nitrogen purging is also done to prevent corrosion and contamination of the pipeline.

    • It is common...

  • Answered by AI
  • Q12. What is difference between pipe and tube
  • Ans. 

    Pipes are used to transport fluids and gases, while tubes are used for structural purposes.

    • Pipes have a standardized outer diameter and wall thickness, while tubes have a standardized inner diameter and wall thickness.

    • Pipes are typically round, while tubes can be round, square, or rectangular.

    • Pipes are often used in plumbing and HVAC systems, while tubes are used in construction and engineering applications.

    • Pipes are u...

  • Answered by AI
  • Q13. Which pipe material or standard used in past experience
  • Ans. 

    I have experience working with various pipe materials and standards including carbon steel, stainless steel, and PVC.

    • I have worked with carbon steel pipes in a power plant project.

    • I have also worked with stainless steel pipes in a pharmaceutical plant project.

    • In a water treatment plant project, I have worked with PVC pipes.

    • I am familiar with ASME B31.3, API 5L, and ASTM standards for pipe materials and welding procedur

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Read your resume carefully, be confident, eye contact and imagine that you knew better than them , if you don't know say I don't know , don't answer in stories , always prepare for interview as per company requirements.

I applied via Recruitment Consulltant and was interviewed before Sep 2021. There was 1 interview round.

Round 1 - HR 

(1 Question)

  • Q1. What do you face a big problem during turnaround
  • Ans. Can you explained basic difference between ASME and ASTM
  • Answered Anonymously

Interview Preparation Tips

Interview preparation tips for other job seekers - I face normally and heard carefully question,
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(1 Question)

  • Q1. Transformers, motor, maintenance and operation
Round 2 - HR 

(1 Question)

  • Q1. Basic salary family background
Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Do not use an unprofessional email address such as cool_boy@email.com. It shows a lack of professionalism by the candidate.
View all tips
Round 2 - Technical 

(4 Questions)

  • Q1. Saudi aramco engineering standards.
  • Ans. 

    Saudi Aramco Engineering Standards are guidelines and specifications used in engineering projects for Saudi Aramco.

    • Saudi Aramco Engineering Standards cover various aspects of engineering design, materials, construction, and operation.

    • These standards ensure consistency, quality, and safety in all engineering projects undertaken by Saudi Aramco.

    • Examples of areas covered by the standards include piping design, electrical ...

  • Answered by AI
  • Q2. Design related discussions
  • Q3. Safe practices in design
  • Ans. 

    Safe practices in design involve considering potential hazards, following regulations, and prioritizing safety.

    • Identify potential hazards in the design process

    • Follow industry regulations and standards for safety

    • Prioritize safety over cost or convenience

    • Regularly review and update safety protocols

    • Include safety features in the design, such as emergency shut-off valves

    • Consider environmental impact and sustainability in d

  • Answered by AI
  • Q4. Quality of deliverables
  • Ans. 

    Quality of deliverables is crucial for successful project completion.

    • Ensuring accuracy and completeness of drawings and documents

    • Adhering to project specifications and standards

    • Regularly reviewing and revising deliverables to meet client requirements

    • Seeking feedback from stakeholders to improve quality

    • Using software tools effectively to enhance deliverables

    • Maintaining clear communication with team members for consisten

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Familiarization with the clients standard and procedures

Skills evaluated in this interview

Tell us how to improve this page.

Interview Questions from Similar Companies

TCS Interview Questions
3.7
 • 10.1k Interviews
Siemens Interview Questions
4.1
 • 416 Interviews
Bosch Interview Questions
4.2
 • 325 Interviews
Thermax Limited Interview Questions
4.2
 • 231 Interviews
Cummins Interview Questions
4.3
 • 227 Interviews
Shell Interview Questions
4.0
 • 189 Interviews
View all
Ramsis Engineering Piping Supervisor Salary
based on 4 salaries
₹0.9 L/yr - ₹4.8 L/yr
67% less than the average Piping Supervisor Salary in India
View more details

Ramsis Engineering Piping Supervisor Reviews and Ratings

based on 1 review

4.0/5

Rating in categories

5.0

Skill development

2.0

Work-Life balance

5.0

Salary & Benefits

3.0

Job Security

4.0

Company culture

3.0

Promotions/Appraisal

2.0

Work Satisfaction

Explore 1 Review and Rating
Senior Engineer
5 salaries
unlock blur

₹8.4 L/yr - ₹20 L/yr

Construction Management
5 salaries
unlock blur

₹15.5 L/yr - ₹40 L/yr

Mechanical Supervisor
5 salaries
unlock blur

₹6.5 L/yr - ₹8.5 L/yr

Mechanical Engineer
4 salaries
unlock blur

₹12 L/yr - ₹18 L/yr

Safety Engineer
4 salaries
unlock blur

₹7.2 L/yr - ₹12 L/yr

Explore more salaries
Compare Ramsis Engineering with

Larsen & Toubro Limited

4.0
Compare

TCS

3.7
Compare

BHEL

4.2
Compare

Thermax Limited

4.2
Compare

Calculate your in-hand salary

Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Did you find this page helpful?
Yes No
write
Share an Interview