Risk assessment involves identifying hazards, evaluating risks, implementing control measures, and reviewing effectiveness.
Identify hazards present in the workplace
Evaluate the risks associated with each hazard
Implement control measures to reduce or eliminate risks
Review the effectiveness of the control measures
Document the risk assessment process and findings
Polymerization equation involves the reaction of monomers to form a polymer chain.
Polymerization is a process where monomers react to form a polymer chain.
The general equation for polymerization is: (Monomer) n -> Polymer
Examples include the polymerization of ethylene to form polyethylene and the polymerization of styrene to form polystyrene.
I applied via Recruitment Consulltant
I would like to work in your company, i have a professional certificate in oil and gas drilling rig operation
Preventive and corrective maintenance of various electrical equipment including breakers, motors, transformers, and relays.
Perform regular maintenance on high and low voltage breakers, motors, and transformers.
Test and calibrate various protection relays for motors, transformers, and generators.
Conduct transformer oil BDV test, thermal scanning, and earth fault and prediction tests.
Terminate high voltage motors, instal...
Preventive and corrective maintenance of various electrical equipment including breakers, motors, transformers, and relays.
Perform regular maintenance tasks on high and low voltage breakers, motors, and transformers.
Test and calibrate protection relays for motors, transformers, and generators.
Conduct transformer oil BDV tests, thermal scanning, and earth fault and prediction tests.
Terminate high voltage motors, install...
Preventive and corrective maintenance of various electrical equipment including breakers, motors, transformers, switches, relays, and testing/calibration of protections.
Preventive maintenance of H.V & LV breakers, motors, transformers, switches, etc.
Corrective maintenance of HV/MV/LV switchgears, breakers, cubicles, etc.
Testing and calibration of various protection relays for motors, transformers, generators.
Transforme...
I applied via Naukri.com and was interviewed in Nov 2023. There were 2 interview rounds.
Quants, DI, reasoning
I applied via Recruitment Consulltant and was interviewed in Mar 2023. There were 2 interview rounds.
posted on 8 Jul 2022
To gland cable and connect instrument cables, follow proper cable routing and termination techniques.
Select the appropriate cable gland size and type for the cable being installed
Ensure the cable is properly routed and secured to prevent damage or strain on the connections
Strip the cable insulation to the appropriate length and prepare the conductors for termination
Connect the conductors to the appropriate terminals on...
Yes, location drawing is a detailed plan or map that shows the exact location of electrical and instrumentation equipment.
Location drawing is used to identify the exact location of electrical and instrumentation equipment in a facility.
It helps in maintenance and troubleshooting of equipment.
Location drawing includes details such as equipment tag numbers, cable routing, and junction box locations.
It is important for sa...
Cable tray fabrication in existing gas plant involves careful planning and execution.
Determine the required cable tray size and material
Identify the location and route of the cable tray
Ensure proper support and grounding of the cable tray
Fabricate the cable tray according to industry standards and specifications
Install the cable tray and secure it in place
Test the cable tray for functionality and safety
The process of pulling electrical cables involves planning, preparation, and execution.
Plan the route and determine the cable length needed
Prepare the cable by attaching pulling grips and lubrication
Use a cable puller to pull the cable through conduit or trays
Terminate the cable at both ends and test for continuity
Document the installation for future reference
Safety at work refers to the measures taken to prevent accidents, injuries, and illnesses in the workplace.
Safety protocols and procedures should be established and followed by all employees.
Regular safety inspections and audits should be conducted to identify and address potential hazards.
Personal protective equipment (PPE) should be provided and used when necessary.
Training and education on safety practices should be...
Permit to work is a formal written system used to control high-risk activities.
It is a safety procedure used in industries such as oil and gas, construction, and manufacturing.
It involves obtaining permission from a supervisor or manager before starting a high-risk activity.
The permit outlines the specific steps and precautions that must be taken to ensure the safety of workers and the environment.
Examples of high-risk...
Procurement Specialist
7
salaries
| ₹4 L/yr - ₹9.5 L/yr |
Designer
4
salaries
| ₹3.8 L/yr - ₹5.3 L/yr |
Senior Designer
4
salaries
| ₹4.5 L/yr - ₹5 L/yr |
Senior Project Engineer
4
salaries
| ₹41 L/yr - ₹50 L/yr |
Procurement Executive
4
salaries
| ₹3.5 L/yr - ₹4.2 L/yr |
TechnipFMC
L&T Energy Hydrocarbon
Baker Hughes
Schlumberger