I applied via Naukri.com and was interviewed before Jul 2021. There was 1 interview round.
To prepare a baseline schedule, identify all project activities, sequence them, estimate durations, and assign resources.
Identify all project activities
Sequence the activities in logical order
Estimate the duration of each activity
Assign resources to each activity
Develop a network diagram
Calculate the critical path
Set the baseline start and finish dates
Update the schedule regularly
Top trending discussions
I applied via Approached by Company and was interviewed in Sep 2022. There were 3 interview rounds.
Delete removes an activity from the project, while dissolve removes a relationship between activities.
Delete removes an activity from the project and all its relationships with other activities.
Dissolve removes a relationship between two activities, but the activities themselves remain in the project.
Deleting an activity can have a cascading effect on the rest of the project, while dissolving a relationship only affect...
I prepare programme by identifying objectives, breaking them down into tasks, assigning resources and setting timelines.
Identify objectives and goals
Break down objectives into smaller tasks
Assign resources and responsibilities to team members
Set timelines and deadlines for each task
Regularly review and update the programme to ensure progress is on track