L&T Water & Effluent Treatment
10+ NTPC Interview Questions and Answers
Q1. 132/33/11Kv Transmission line phase to phase clearance
Q2. How many types of tower used in 45° Angel point.
Q3. What is the survey done in the new transmission line.
Q4. What should be the clearance of 33kv line crossing.
Q5. What type of motor used in your pump house.
Q6. What types of CT & PT used for sub- station
Q7. 90kn & 120kn long rod insulator used in 132kv transmission line.
Q8. What types of conductor used in your site.
Q9. Which insulator used in 132 transmission line.
Q10. Principal of bearings, refrigeration
Bearings are used to reduce friction between two moving parts while refrigeration is the process of cooling a space or substance.
Bearings work on the principle of reducing friction between two moving parts by providing a smooth surface for them to roll or slide against each other.
Refrigeration works on the principle of removing heat from a space or substance, which causes it to cool down.
Bearings are commonly used in machines such as engines, turbines, and pumps to reduce fri...read more
Q11. Designing parameters of heat exchanger,
Designing parameters of heat exchanger involves determining heat transfer rate, surface area, fluid flow rate, and material selection.
Determine the heat transfer rate required for the application
Select appropriate fluids and their flow rates
Calculate the surface area required for heat transfer
Choose suitable materials for construction based on operating conditions
Consider factors such as pressure drop, fouling, and corrosion
Optimize the design for efficiency and cost-effectiv...read more
Q12. How can pump seal replacement
Pump seal replacement can be done by following proper procedures and using the right tools.
Ensure the pump is turned off and disconnected from power source before starting the replacement.
Remove the old seal carefully, taking note of its orientation and position.
Clean the seal chamber thoroughly before installing the new seal.
Apply lubricant or sealant as recommended by the manufacturer.
Reassemble the pump and test for leaks before putting it back into operation.