I applied via Referral and was interviewed before Jun 2021. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. How to manage Reconciliation ?
  • Ans. 

    Reconciliation can be managed by following a systematic approach to match and compare financial records.

    • Identify the source of discrepancies

    • Compare records from different sources

    • Investigate and resolve discrepancies

    • Document all findings and resolutions

    • Perform regular checks to ensure accuracy

  • Answered by AI
  • Q2. Proper billing as per IS code
  • Ans. 

    Proper billing as per IS code ensures adherence to standardized billing practices.

    • Billing should be done in accordance with the relevant IS code for accurate and fair invoicing.

    • The IS code provides guidelines on various aspects of billing, such as measurement, rates, and calculations.

    • Proper documentation and record-keeping are essential to support the billing process as per the IS code.

    • Regular audits and checks should ...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Know about IS 1200, mainly shuttering, plasters
How to create proper data sheet

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Referral and was interviewed before May 2023. There was 1 interview round.

Round 1 - Technical 

(5 Questions)

  • Q1. How do you make RMC reconciliation?
  • Ans. 

    RMC reconciliation involves comparing the quantity of materials ordered with the quantity used in construction to ensure accuracy.

    • Collect all the data related to RMC (Ready Mix Concrete) orders and deliveries.

    • Compare the quantity of RMC ordered with the quantity actually used in construction.

    • Identify any discrepancies and investigate the reasons behind them.

    • Adjust the records accordingly to ensure accurate billing and

  • Answered by AI
  • Q2. How to calculate bbs ?
  • Ans. 

    BBS (Bar Bending Schedule) is calculated by determining the quantity of steel reinforcement required for a particular concrete structure.

    • Calculate the total length of bars required for each diameter and type of reinforcement.

    • Determine the number of bars required for each diameter and type of reinforcement.

    • Calculate the total weight of bars required for each diameter and type of reinforcement.

    • Prepare a detailed schedule...

  • Answered by AI
  • Q3. How to check paint measurements?
  • Ans. 

    Paint measurements can be checked using a paint thickness gauge to ensure compliance with specifications.

    • Use a paint thickness gauge to measure the thickness of the paint layer.

    • Compare the measured thickness with the specified thickness in the project specifications.

    • Ensure that the paint thickness is uniform across the surface.

    • Repeat the measurements at multiple points to ensure accuracy.

    • Adjust the paint application if...

  • Answered by AI
  • Q4. How do you find extra items for WO amendment?
  • Ans. 

    Extra items for WO amendment can be found by reviewing project specifications, consulting with stakeholders, conducting site visits, and analyzing previous change orders.

    • Review project specifications for any missed items or changes

    • Consult with stakeholders such as architects, engineers, and contractors for input

    • Conduct site visits to identify any additional work required

    • Analyze previous change orders to see if any item

  • Answered by AI
  • Q5. How do you ConsiderJMR is right or wrong?
  • Ans. 

    Consider JMR based on project specifications, quantities, rates, and market conditions.

    • Review project specifications to ensure accurate billing

    • Verify quantities of materials and work done

    • Check rates for labor, materials, and equipment

    • Consider market conditions for pricing accuracy

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - For billing engineer interview you should practice of bbs and procedures of billing and backup required for billing process!
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Apr 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. About salary and benefits
Round 3 - One-on-one 

(4 Questions)

  • Q1. About my key activity and responsibility
  • Q2. Process of variation
  • Ans. 

    Process of variation involves documenting and analyzing changes in project scope, cost, or schedule.

    • Variations are changes to the original scope, cost, or schedule of a project

    • Variations must be documented and approved by the relevant parties

    • The impact of variations on project budget and timeline must be analyzed

    • Examples of variations include design changes, unforeseen site conditions, and client requests

  • Answered by AI
  • Q3. Details about TDS
  • Q4. Details about NS items

Interview Preparation Tips

Topics to prepare for The Louis Berger Group Billing Engineer interview:
  • Contact
  • Running bill
  • Escalations
  • Variation
  • Ns items

I applied via Recruitment Consulltant and was interviewed before Apr 2021. There was 1 interview round.

Round 1 - One-on-one 

(2 Questions)

  • Q1. Rate analysis for plaster
  • Ans. 

    Rate analysis for plaster involves calculating the cost of materials, labor, and equipment required for plastering a specific area.

    • Determine the area to be plastered

    • Calculate the quantity of materials required (cement, sand, water)

    • Determine the cost of materials per unit

    • Calculate the cost of labor per unit area

    • Include the cost of equipment and tools used

    • Add all costs to get the total cost of plastering

    • Example: For plas...

  • Answered by AI
  • Q2. BBS for steel and BOQ for building items
  • Ans. 

    BBS is Bar Bending Schedule used for steel reinforcement and BOQ is Bill of Quantities used for building items.

    • BBS provides details of reinforcement steel required for construction.

    • BOQ lists all the materials and quantities required for construction.

    • BBS is used for steel reinforcement in structures like columns, beams, slabs, etc.

    • BOQ is used for building items like bricks, cement, sand, etc.

    • Both BBS and BOQ are importa...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Study IS 1200 all parts, material reconciliation

Jain Engineers Interview FAQs

How many rounds are there in Jain Engineers Senior Billing Engineer interview?
Jain Engineers interview process usually has 1 rounds. The most common rounds in the Jain Engineers interview process are Technical.
How to prepare for Jain Engineers Senior Billing Engineer interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Jain Engineers. The most common topics and skills that interviewers at Jain Engineers expect are Billing Engineering and Estimation Engineering.
What are the top questions asked in Jain Engineers Senior Billing Engineer interview?

Some of the top questions asked at the Jain Engineers Senior Billing Engineer interview -

  1. How to manage Reconciliatio...read more
  2. Proper billing as per IS c...read more

Tell us how to improve this page.

People are getting interviews through

based on 1 Jain Engineers interview
Referral
100%
Low Confidence
?
Low Confidence means the data is based on a small number of responses received from the candidates.

Interview Questions from Similar Companies

TCS Interview Questions
3.7
 • 10.3k Interviews
Siemens Interview Questions
4.1
 • 425 Interviews
Bosch Interview Questions
4.2
 • 328 Interviews
Thermax Limited Interview Questions
4.2
 • 235 Interviews
Cummins Interview Questions
4.3
 • 230 Interviews
Voltas Interview Questions
4.0
 • 123 Interviews
BHEL Interview Questions
4.2
 • 103 Interviews
View all
Jain Engineers Senior Billing Engineer Salary
based on 5 salaries
₹4.3 L/yr - ₹6.9 L/yr
28% less than the average Senior Billing Engineer Salary in India
View more details
Site Engineer
21 salaries
unlock blur

₹2 L/yr - ₹3.5 L/yr

Safety Officer
19 salaries
unlock blur

₹2.2 L/yr - ₹4.5 L/yr

Civil Site Engineer
18 salaries
unlock blur

₹1.5 L/yr - ₹4.5 L/yr

Senior Engineer
13 salaries
unlock blur

₹4 L/yr - ₹6.5 L/yr

Senior Site Engineer
11 salaries
unlock blur

₹3.3 L/yr - ₹6 L/yr

Explore more salaries
Compare Jain Engineers with

TCS

3.7
Compare

Larsen & Toubro Limited

4.0
Compare

BHEL

4.2
Compare

Thermax Limited

4.2
Compare

Calculate your in-hand salary

Confused about how your in-hand salary is calculated? Enter your annual salary (CTC) and get your in-hand salary
Did you find this page helpful?
Yes No
write
Share an Interview