I applied via Recruitment Consulltant and was interviewed in Aug 2023. There were 3 interview rounds.
Maintaining a material register involves keeping track of all materials used in a project.
Create a register to record details of all materials used
Include information such as material type, quantity, and source
Update the register regularly to reflect any changes or additions
Use standardized formats to ensure consistency and ease of use
Examples of formats include spreadsheets, databases, or online tools
Top trending discussions
I applied via Approached by Company and was interviewed before Apr 2021. There was 1 interview round.
I applied via Approached by Company and was interviewed before Oct 2022. There were 2 interview rounds.
Extra Dose bridge has additional support structures while cable stay bridge uses cables to support the bridge deck.
Extra Dose bridge has additional piers or columns for support.
Cable stay bridge uses cables attached to towers to support the bridge deck.
Extra Dose bridge is more common for shorter spans while cable stay bridge is used for longer spans.
Cable stay bridges have a more modern and sleek appearance compared t
Types of contracts include express, implied, unilateral, bilateral, and voidable contracts.
Express contract: Clearly stated terms and conditions, either written or verbal.
Implied contract: Terms inferred from the actions or conduct of the parties involved.
Unilateral contract: One party makes a promise in exchange for the performance of an act by the other party.
Bilateral contract: Both parties exchange promises to perf...
I applied via Approached by Company and was interviewed in Jul 2024. There was 1 interview round.
HRG stands for Human Resource Group while LRG stands for Large Retail Group.
HRG focuses on managing human resources within an organization
LRG focuses on managing a large retail business
HRG deals with employee relations, recruitment, training, and development
LRG deals with sales, inventory management, customer service, and marketing
Transformer sizing involves calculating the appropriate size of a transformer based on load requirements.
Determine the total load requirements in kVA
Consider the load factor and diversity factor
Calculate the transformer size based on the total load requirements
Ensure the transformer is rated for the appropriate voltage and frequency
Consult with a professional engineer if needed
Designing a floating head assembly involves considering various factors such as material selection, sealing mechanisms, and thermal expansion.
Select appropriate materials for the floating head assembly based on the application requirements.
Design effective sealing mechanisms to prevent leakage and ensure proper functioning.
Consider thermal expansion and contraction to accommodate temperature variations.
Ensure proper al...
H2S service for pressure vessel refers to the use of hydrogen sulfide in a pressure vessel.
H2S service involves the handling and containment of hydrogen sulfide gas in a pressure vessel.
Pressure vessels used in H2S service must be designed and constructed to withstand the corrosive effects of hydrogen sulfide.
Special materials and coatings may be required to prevent hydrogen sulfide from corroding the pressure vessel.
R...
Gaskets are mechanical seals used to prevent leakage between two surfaces. There are various types of gaskets available.
Sheet gaskets
Spiral wound gaskets
Ring gaskets
Metallic gaskets
Rubber gaskets
Cork gaskets
Non-asbestos gaskets
I applied via Referral and was interviewed in May 2022. There were 2 interview rounds.
FEED is Front End Engineering Design, the initial phase of engineering design. Hazop & Hazid are safety studies. 3D model is finalised after multiple reviews.
FEED is the initial phase of engineering design where the project scope is defined and preliminary designs are developed.
Hazop & Hazid are safety studies conducted during the design phase to identify and mitigate potential hazards.
SIL (Safety Integrity Level) is a...
I appeared for an interview in Sep 2024.
I left previous companies to pursue growth opportunities, align with my career goals, and seek better work-life balance.
I left Company A after 3 years to seek a role that offered more leadership opportunities, as I wanted to develop my management skills.
At Company B, I transitioned to a new position that aligned better with my long-term career goals in project management.
I departed from Company C to find a work environ...
I applied via Campus Placement and was interviewed before Jan 2020. There were 5 interview rounds.
based on 1 interview
Interview experience
Civil Site Engineer
14
salaries
| ₹2.5 L/yr - ₹4.5 L/yr |
Site Engineer
7
salaries
| ₹2 L/yr - ₹4.5 L/yr |
Civil Engineer
7
salaries
| ₹2.2 L/yr - ₹5.2 L/yr |
Senior Engineer
5
salaries
| ₹3.4 L/yr - ₹6.6 L/yr |
Project Manager
5
salaries
| ₹6 L/yr - ₹8.4 L/yr |
Megha Engineering & Infrastructures
Shapoorji Pallonji Group
Alstom Transportation
Tata Technologies