I applied via Approached by Company and was interviewed before Aug 2023. There were 2 interview rounds.
Lead time
Lead time is the amount of time a successor activity can start before its predecessor activity finishes
It helps in optimizing project schedules and resource allocation
During the Risk Identification stage, risks are prioritized based on probability and impact.
Risk Identification stage is where potential risks are identified and documented
Probability and impact assessment helps in prioritizing risks
Common tools used for prioritizing risks include risk matrix and risk assessment matrix
Agile Process is a project management approach that emphasizes flexibility, collaboration, and incremental progress.
Iterative approach to project management
Focus on delivering value to the customer
Adaptability to changing requirements
Frequent communication and collaboration among team members
Use of sprints or iterations to break down work into manageable chunks
Examples: Scrum, Kanban, Extreme Programming
I am most familiar with Agile, Waterfall, and Scrum methodologies.
Agile methodology focuses on iterative development and collaboration between cross-functional teams.
Waterfall methodology follows a linear sequential approach to project management.
Scrum methodology is a subset of Agile that emphasizes on short, iterative work cycles called sprints.
Top trending discussions
posted on 16 May 2024
Aptitude Test on basic Java questions
posted on 16 May 2024
Aptitude Test on basic Java questions
posted on 4 Jan 2025
Some of the top questions asked at the Deuglo Infosystem Project Manager interview -
based on 1 interview
Interview experience
Quality Engineer
4
salaries
| ₹2 L/yr - ₹2.2 L/yr |
PHP Developer
4
salaries
| ₹3 L/yr - ₹3 L/yr |
QA Engineer
4
salaries
| ₹1.4 L/yr - ₹2.7 L/yr |
UI Developer
4
salaries
| ₹2.5 L/yr - ₹4.2 L/yr |
UI/UX Designer
3
salaries
| ₹1.8 L/yr - ₹2.2 L/yr |
TCS
Infosys
Wipro
HCLTech