I applied via Referral and was interviewed in Nov 2023. There was 1 interview round.
SPI (Schedule Performance Index) & CPI (Cost Performance Index) are key performance indicators used in project management to measure project schedule and cost performance.
SPI measures the efficiency of work accomplished compared to the planned schedule. SPI = EV / PV
CPI measures the efficiency of work accomplished compared to the actual cost. CPI = EV / AC
SPI & CPI values above 1 indicate good performance, below 1 indi...
Top trending discussions
I applied via Walk-in and was interviewed before Jan 2022. There were 2 interview rounds.
based on 1 interview
Interview experience
based on 1 review
Rating in categories
Mechanical Engineer
56
salaries
| ₹2.3 L/yr - ₹6 L/yr |
Project Engineer
33
salaries
| ₹2.4 L/yr - ₹9.2 L/yr |
QA QC Engineer
31
salaries
| ₹2 L/yr - ₹8.2 L/yr |
Safety Officer
30
salaries
| ₹3.5 L/yr - ₹7.6 L/yr |
Maintenance Engineer
21
salaries
| ₹3 L/yr - ₹6.2 L/yr |
L&T Construction
Tata Projects
Shapoorji Pallonji Group
Hindustan Construction Company