Filter interviews by

AFRY Engineering India Pvt Ltd Interview Questions and Answers

Be the first one to contribute and help others!

Interview questions from similar companies

Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-
Round 1 - One-on-one 

(2 Questions)

  • Q1. What is firewall
  • Ans. 

    A firewall is a network security system that monitors and controls incoming and outgoing network traffic based on predetermined security rules.

    • Acts as a barrier between a trusted internal network and untrusted external network

    • Filters network traffic based on rules set by the administrator

    • Can be hardware-based or software-based

    • Examples include Cisco ASA, Palo Alto Networks, and Windows Firewall

  • Answered by AI
  • Q2. Cyber security related questions

Skills evaluated in this interview

Interview experience
4
Good
Difficulty level
-
Process Duration
-
Result
-

I applied via Recruitment Consulltant

Round 1 - Technical 

(1 Question)

  • Q1. Will ask Technical Questions Related to Projects.
Round 2 - HR 

(1 Question)

  • Q1. Will ask about past companies experience and role, responsibility etc.
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - One-on-one 

(1 Question)

  • Q1. What kind of customer complaint you handled in last company
  • Ans. 

    I handled a variety of customer complaints in my last company, ranging from billing issues to product quality concerns.

    • Resolved billing discrepancies by investigating and correcting errors

    • Addressed product quality complaints by offering refunds or replacements

    • Assisted customers with technical issues by providing troubleshooting steps

    • Managed delivery delays by communicating updates and offering compensation

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Good company
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Indeed and was interviewed in Apr 2024. There were 3 interview rounds.

Round 1 - HR 

(1 Question)

  • Q1. Brief description about the requirements and job description.
Round 2 - Technical 

(1 Question)

  • Q1. Virtual Technical interview
Round 3 - Technical 

(1 Question)

  • Q1. Face to face technicsl interview
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Coding Test 

Python program python

Tunnel Design Engineer Interview Questions & Answers

Arup user image Anonymous

posted on 4 Aug 2024

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
More than 8 weeks
Result
Selected Selected

I applied via Company Website and was interviewed in Feb 2024. There were 2 interview rounds.

Round 1 - HR 

(2 Questions)

  • Q1. Why ARUP why not other
  • Ans. 

    ARUP is a global firm known for innovative and sustainable tunnel design solutions.

    • ARUP has a strong reputation for delivering high-quality and innovative tunnel projects.

    • The company has a diverse team of experts with extensive experience in tunnel design.

    • ARUP prioritizes sustainability and environmental considerations in their designs.

    • The firm has a global presence, allowing for collaboration on projects worldwide.

  • Answered by AI
  • Q2. Basic HR questions
Round 2 - Technical 

(2 Questions)

  • Q1. Question about tunnel and my past experience
  • Q2. About the aligmen of the tunnel, geotechnical and structural desnment

Interview Preparation Tips

Interview preparation tips for other job seekers - Be genuine and share your only real experience with their international team is highly experienced.
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Recruitment Consulltant and was interviewed in Aug 2023. There was 1 interview round.

Round 1 - Technical 

(3 Questions)

  • Q1. Foundation installation process is oil and gas industry
  • Ans. Explain it as required as per industry requirement like Valid Permit, Valid lifting plan, Approved method statement, barrication,Sign boards, banks man, competent and certified equipment and operator, rigger, color coded and inspected lifting accessories, check wind speed limits, foggy or dusty weather conditions
  • Answered Anonymously
  • Q2. Excavation process for oil and gas industry
  • Ans. 

    Excavation process in the oil and gas industry involves several steps to ensure safe and efficient operations.

    • The first step in the excavation process is to conduct a thorough site survey to identify potential hazards and determine the best approach for excavation.

    • Before excavation begins, proper permits and approvals must be obtained from relevant authorities.

    • Excavation equipment such as excavators, bulldozers, and ba...

  • Answered by AI
  • Q3. Valid Permit, approved method statement, Excavation certificate, check GPR (Ground penetrating radar)report, CAT (Cable avoidance Tool) Scan, Drawing, route marker, Trial pit, hard barricade the area, cert...

Interview Preparation Tips

Interview preparation tips for other job seekers - Be prepared as per your resume and for the post you apply for
If possible then Do some research about company and project that you apply for
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Mar 2024. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. Method of delay analysis
  • Ans. 

    Delay analysis methods are used to determine the causes and impacts of project delays.

    • There are various methods of delay analysis such as Critical Path Method (CPM), Time Impact Analysis (TIA), Impacted As-Planned, and As-Built.

    • Each method has its own advantages and limitations, and the choice of method depends on the specific circumstances of the project.

    • CPM is a commonly used method that analyzes the project schedule...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Focus on delay and scheduling
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - HR 

(2 Questions)

  • Q1. What credential you possess for the position
  • Q2. What can you contribute to the organization?

Interview Preparation Tips

Interview preparation tips for other job seekers - State the qualification you have and experiences.
Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Technical 

(2 Questions)

  • Q1. Base plate size, thickness ,tube size, thickness o.d.,id. Weight/meter Ans 150 m.m, thickness 6m.m., tube size max. 6 merer, thickness 4.0 m.m., o.d 48.3 m.m. ,i.d. 40.3 m.m. , weight/ meter 4.4 k.g
  • Q2. Type of scaffold Ans. (1) mobile tower (2) indipendent tower (3) suspended tower (4) candilever (5) racker tower (6) basket (7) febricate and frame scaffold
  • Ans. 

    There are various types of scaffolds such as mobile tower, independent tower, suspended tower, cantilever, racker tower, basket, and fabricated and frame scaffold.

    • Mobile tower scaffold is a type of scaffold that can be easily moved from one place to another.

    • Independent tower scaffold is a free-standing scaffold that does not require support from the building or structure.

    • Suspended tower scaffold is a type of scaffold t...

  • Answered by AI
Round 2 - Technical 

(1 Question)

  • Q1. Gin wheel capacity Ans. 25 k.g.
  • Ans. 

    The gin wheel capacity is 25 kg.

    • The gin wheel is a pulley system used to lift and lower materials on a scaffold.

    • The capacity of the gin wheel refers to the maximum weight it can safely lift.

    • It is important to ensure that the weight of the load being lifted does not exceed the capacity of the gin wheel.

    • Exceeding the capacity can result in accidents and injuries.

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Very good archirodon very nice company
And good management
Everything is very good

AFRY Engineering India Pvt Ltd Interview FAQs

How to prepare for AFRY Engineering India Pvt Ltd interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at AFRY Engineering India Pvt Ltd . The most common topics and skills that interviewers at AFRY Engineering India Pvt Ltd expect are CATIA, Solid Works, Teamcenter, UG and UG NX.

Tell us how to improve this page.

AFRY Engineering India Pvt Ltd Interview Process

based on 1 interview

Interview experience

4
  
Good
View more

Interview Questions from Similar Companies

TCE Interview Questions
3.8
 • 244 Interviews
AECOM Interview Questions
4.2
 • 111 Interviews
Worley Interview Questions
4.2
 • 108 Interviews
TechnipFMC Interview Questions
4.0
 • 68 Interviews
Bechtel Interview Questions
4.0
 • 66 Interviews
Mott MacDonald Interview Questions
4.2
 • 42 Interviews
Black & Veatch Interview Questions
4.3
 • 12 Interviews
View all

AFRY Engineering India Pvt Ltd Reviews and Ratings

based on 23 reviews

4.1/5

Rating in categories

3.8

Skill development

4.5

Work-life balance

4.2

Salary

4.2

Job security

4.4

Company culture

3.9

Promotions

3.8

Work satisfaction

Explore 23 Reviews and Ratings
Senior Technical Lead
3 salaries
unlock blur

₹19.1 L/yr - ₹24 L/yr

Explore more salaries
Compare AFRY Engineering India Pvt Ltd with

TCE

3.8
Compare

L&T Technology Services

3.3
Compare

Jacobs Engineering Group

4.1
Compare

Fluor Corporation

4.3
Compare
Did you find this page helpful?
Yes No
write
Share an Interview