Free float is the amount of time an activity can be delayed without delaying the early start of its successor. Total float is the amount of time an activity can be delayed without delaying the project end date.
Free float is the amount of time an activity can be delayed without delaying the early start of its successor.
Total float is the amount of time an activity can be delayed without delaying the project end date.
Fre...
EVMS stands for Earned Value Management System, a project management technique to measure project performance.
EVMS integrates scope, schedule, and cost parameters to track project progress.
It uses metrics like Planned Value (PV), Earned Value (EV), and Actual Cost (AC) to assess project performance.
EVMS helps in identifying project variances and taking corrective actions to bring the project back on track.
It is widely ...
Project progress can be tracked by comparing actual progress against planned progress.
Compare actual progress against planned progress
Use project management software to track progress
Monitor key performance indicators (KPIs)
Regularly update project schedule and budget
Conduct progress meetings with stakeholders
Top trending discussions
based on 2 reviews
Rating in categories
Planning Engineer
14
salaries
| ₹8.6 L/yr - ₹24 L/yr |
Project Manager
10
salaries
| ₹12.5 L/yr - ₹50.9 L/yr |
Site Engineer
7
salaries
| ₹6 L/yr - ₹10 L/yr |
Quantity Surveyor
7
salaries
| ₹5.2 L/yr - ₹10.3 L/yr |
Senior Quantity Surveyor
7
salaries
| ₹15 L/yr - ₹29 L/yr |
TCS
Infosys
Wipro
HCLTech