The process of tower foundation involves several steps that are carried out day by day.
Day 1: Site preparation and layout survey
Day 2: Excavation for foundation
Day 3: Reinforcement placement
Day 4: Formwork installation
Day 5: Concrete pouring
Day 6: Curing of concrete
Day 7: Removal of formwork
Day 8: Quality inspection and testing
Day 9: Backfilling around the foundation
Day 10: Final inspection and documentation
Cube mould size refers to the dimensions of the mould used to cast concrete cubes for testing.
Cube moulds are typically made of steel or cast iron.
The most common cube mould size used in construction is 150mm x 150mm x 150mm.
Other sizes like 100mm x 100mm x 100mm or 200mm x 200mm x 200mm may also be used depending on the requirements.
Cube moulds have removable base plates to facilitate easy removal of the hardened conc...
Quality points at the pouring time of concrete include proper mix proportions, correct placement, adequate compaction, and appropriate curing.
Proper mix proportions ensure the desired strength and durability of the concrete.
Correct placement involves placing the concrete in the designated location without segregation or excessive bleeding.
Adequate compaction ensures that there are no voids or air pockets in the concret...
Sloped cutting refers to the excavation of soil or rock at an inclined angle to create a slope or incline.
Sloped cutting is commonly used in construction projects to create roadways, railways, or canals on hilly terrains.
It involves removing the excess material from a higher elevation to a lower elevation, forming a sloping surface.
The angle of the slope is determined based on factors such as soil stability, desired gr...
Top trending discussions
posted on 20 Nov 2021
I applied via Naukri.com and was interviewed in May 2021. There was 1 interview round.
I applied via Referral and was interviewed before Apr 2021. There was 1 interview round.
I applied via Naukri.com and was interviewed in Jul 2021. There were 4 interview rounds.
I applied via Recruitment Consulltant and was interviewed before May 2022. There were 3 interview rounds.
posted on 11 Oct 2020
I applied via Recruitment Consulltant and was interviewed in Oct 2020. There were 5 interview rounds.
posted on 19 Feb 2024
I applied via Referral and was interviewed in Aug 2023. There were 2 interview rounds.
posted on 28 Mar 2024
I applied via Company Website and was interviewed before Mar 2023. There was 1 interview round.
The process of erection of duct involves planning, fabrication, transportation, installation, and testing.
Planning involves determining the layout, size, and material of the ducts.
Fabrication includes cutting, bending, and assembling the ducts according to the design.
Transportation is the movement of fabricated ducts to the installation site.
Installation involves positioning and connecting the ducts to the HVAC system.
...
The code followed for the fabrication of steel structure materials is typically based on industry standards and regulations.
The fabrication of steel structures is typically governed by codes such as the American Institute of Steel Construction (AISC) Code of Standard Practice.
Other codes that may be followed include the American Welding Society (AWS) D1.1 Structural Welding Code - Steel.
Fabrication processes must also ...
The erection sequence of a steel structure involves planning and executing the assembly of components in a specific order to ensure safety and stability.
Start by assembling the foundation and anchor bolts.
Next, erect the columns and connect them to the foundation.
Then, install the beams and trusses to form the framework.
After that, add the bracing and diagonal members for stability.
Finally, complete the structure by ad...
posted on 16 Oct 2024
The erection sequence of ESP involves several steps to ensure proper installation and functioning.
1. Prepare the foundation for the ESP unit.
2. Install the support structure for the ESP.
3. Assemble the ESP components such as the casing, electrodes, and rapping system.
4. Connect the necessary electrical and mechanical components.
5. Test the ESP system for proper functioning before commissioning.
6. Commission the ESP sys...
Various ESP materials suppliers include Schlumberger, Baker Hughes, Halliburton, Weatherford, and National Oilwell Varco.
Schlumberger
Baker Hughes
Halliburton
Weatherford
National Oilwell Varco
posted on 2 Dec 2024
I applied via Naukri.com and was interviewed in Jun 2024. There was 1 interview round.
based on 6 reviews
Rating in categories
Project Engineer
613
salaries
| ₹4.8 L/yr - ₹18.3 L/yr |
R&D Engineer
330
salaries
| ₹6 L/yr - ₹22.2 L/yr |
Financial Analyst
259
salaries
| ₹2 L/yr - ₹8.6 L/yr |
Design Engineer
240
salaries
| ₹1.2 L/yr - ₹10 L/yr |
Finance Specialist
200
salaries
| ₹2.8 L/yr - ₹7.5 L/yr |
Thermax Limited
Isgec Heavy Engineering
Kirloskar Oil Engines
Kirloskar Brothers