  • Q1. What is strength of M25 grade.
  • Q2. Complete Process of tower foundation day by day.
  • Ans. 

    The process of tower foundation involves several steps that are carried out day by day.

    • Day 1: Site preparation and layout survey

    • Day 2: Excavation for foundation

    • Day 3: Reinforcement placement

    • Day 4: Formwork installation

    • Day 5: Concrete pouring

    • Day 6: Curing of concrete

    • Day 7: Removal of formwork

    • Day 8: Quality inspection and testing

    • Day 9: Backfilling around the foundation

    • Day 10: Final inspection and documentation

  • Answered by AI
  • Q3. What is cube mould size.?
  • Ans. 

    Cube mould size refers to the dimensions of the mould used to cast concrete cubes for testing.

    • Cube moulds are typically made of steel or cast iron.

    • The most common cube mould size used in construction is 150mm x 150mm x 150mm.

    • Other sizes like 100mm x 100mm x 100mm or 200mm x 200mm x 200mm may also be used depending on the requirements.

    • Cube moulds have removable base plates to facilitate easy removal of the hardened conc...

  • Answered by AI
  • Q4. What are quality point at the pouring time of concrete.?
  • Ans. 

    Quality points at the pouring time of concrete include proper mix proportions, correct placement, adequate compaction, and appropriate curing.

    • Proper mix proportions ensure the desired strength and durability of the concrete.

    • Correct placement involves placing the concrete in the designated location without segregation or excessive bleeding.

    • Adequate compaction ensures that there are no voids or air pockets in the concret...

  • Answered by AI
  • Q5. Proper vibrate and proper mixing of concrete and good shuttering with oil and not mix extra water in concrete.
  • Q6. What is sloped cutting..?
  • Ans. 

    Sloped cutting refers to the excavation of soil or rock at an inclined angle to create a slope or incline.

    • Sloped cutting is commonly used in construction projects to create roadways, railways, or canals on hilly terrains.

    • It involves removing the excess material from a higher elevation to a lower elevation, forming a sloping surface.

    • The angle of the slope is determined based on factors such as soil stability, desired gr...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - This interview was a technical one but was majorly a stress test. It lasted for about 1 hour 10 minutes. The interviewer wanted to test both my knowledge and communication skills. Most of the questions asked to me were related to my B.Tech curriculum i.e. computer science related topics. He stressed a lot on the basics related to my project topic. Luckily I was able to answer most of the questions correctly. I tried to answer each question with examples and also used props on the table (like pens, paperweights, pen stands etc.) to explain my theories. It was my first offcampus interview, and I think I did pretty well for a fresher. You need to stay calm and should apply presence of mind. Please go through the job description thoroughly word-by-word and recheck your resume to ensure that you are a best-fit for the position.

Interview questions from similar companies

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Campus Placement and was interviewed in Dec 2024. There was 1 interview round.

Round 1 - Technical 

(6 Questions)

  • Q1. What are the dimensions of a standard brick?
  • Ans. 

    The standard dimensions of a brick are 3 5/8 inches x 2 1/4 inches x 8 inches.

    • Standard brick size is 3 5/8 inches x 2 1/4 inches x 8 inches

    • Bricks can also come in different sizes based on region or purpose

    • Common brick sizes include modular, jumbo, and queen

  • Answered by AI
  • Q2. What is the water-cement ratio?
  • Ans. 

    The water-cement ratio is the ratio of the weight of water to the weight of cement used in a concrete mix.

    • It is a crucial factor in determining the strength and durability of concrete.

    • A lower water-cement ratio results in stronger and more durable concrete.

    • The typical range for water-cement ratio is between 0.4 to 0.6.

    • Excessive water in the mix can lead to lower strength and durability of concrete.

  • Answered by AI
  • Q3. What is the heat of hydration?
  • Ans. 

    Heat of hydration is the heat released when water is added to cement during the chemical reaction of hydration.

    • Heat of hydration is the heat released when water is added to cement during the chemical reaction of hydration.

    • It is an exothermic reaction, meaning it releases heat.

    • The heat of hydration is important to consider in concrete construction to prevent cracking and ensure proper curing.

    • Higher heat of hydration can...

  • Answered by AI
  • Q4. What is curing?
  • Ans. 

    Curing is the process of maintaining adequate moisture and temperature in concrete to ensure proper hydration and strength development.

    • Curing helps prevent cracking and ensures the concrete reaches its full strength potential.

    • Common curing methods include water curing, membrane curing, and curing compounds.

    • Proper curing typically lasts for at least 7 days, but can vary depending on the type of concrete mix and environm

  • Answered by AI
  • Q5. What is footing and foundation?
  • Ans. 

    Footing is the bottommost part of a foundation that distributes the load of the structure to the soil.

    • Footing is typically made of concrete and is wider than the foundation walls to provide stability.

    • Foundations are the lower portion of a building structure that transfers the load to the soil.

    • There are different types of foundations such as shallow foundations (like spread footings) and deep foundations (like piles).

  • Answered by AI
  • Q6. What is one way slab and two way slab?
  • Ans. 

    One way slab is supported on two opposite sides while two way slab is supported on all four sides.

    • One way slab is designed to carry loads along one direction only

    • Two way slab is designed to carry loads along both directions

    • One way slab is supported on two opposite sides

    • Two way slab is supported on all four sides

  • Answered by AI

Interview Preparation Tips

Topics to prepare for Kirloskar Brothers Civil Site Engineer interview:
  • Hr Fresher
Interview preparation tips for other job seekers - Civil engineering is a significant contribution that is essential for our lives.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Campus Placement and was interviewed in Dec 2024. There was 1 interview round.

Round 1 - Technical 

(6 Questions)

  • Q1. What are the dimensions of a standard brick?
  • Ans. 

    The standard dimensions of a brick are 3 5/8 inches x 2 1/4 inches x 8 inches.

    • Standard brick size is 3 5/8 inches x 2 1/4 inches x 8 inches

    • Bricks can also come in different sizes based on region or purpose

    • Common brick sizes include modular, jumbo, and queen

  • Answered by AI
  • Q2. What is the water-cement ratio?
  • Ans. 

    The water-cement ratio is the ratio of the weight of water to the weight of cement used in a concrete mix.

    • It is a crucial factor in determining the strength and durability of concrete.

    • A lower water-cement ratio results in stronger and more durable concrete.

    • The typical range for water-cement ratio is between 0.4 to 0.6.

    • Excessive water in the mix can lead to lower strength and durability of concrete.

  • Answered by AI
  • Q3. What is the heat of hydration?
  • Ans. 

    Heat of hydration is the heat released when water is added to cement during the chemical reaction of hydration.

    • Heat of hydration is the heat released when water is added to cement during the chemical reaction of hydration.

    • It is an exothermic reaction, meaning it releases heat.

    • The heat of hydration is important to consider in concrete construction to prevent cracking and ensure proper curing.

    • Higher heat of hydration can...

  • Answered by AI
  • Q4. What is curing?
  • Ans. 

    Curing is the process of maintaining adequate moisture and temperature in concrete to ensure proper hydration and strength development.

    • Curing helps prevent cracking and ensures the concrete reaches its full strength potential.

    • Common curing methods include water curing, membrane curing, and curing compounds.

    • Proper curing typically lasts for at least 7 days, but can vary depending on the type of concrete mix and environm

  • Answered by AI
  • Q5. What is footing and foundation?
  • Ans. 

    Footing is the bottommost part of a foundation that distributes the load of the structure to the soil.

    • Footing is typically made of concrete and is wider than the foundation walls to provide stability.

    • Foundations are the lower portion of a building structure that transfers the load to the soil.

    • There are different types of foundations such as shallow foundations (like spread footings) and deep foundations (like piles).

  • Answered by AI
  • Q6. What is one way slab and two way slab?
  • Ans. 

    One way slab is supported on two opposite sides while two way slab is supported on all four sides.

    • One way slab is designed to carry loads along one direction only

    • Two way slab is designed to carry loads along both directions

    • One way slab is supported on two opposite sides

    • Two way slab is supported on all four sides

  • Answered by AI

Interview Preparation Tips

Topics to prepare for Kirloskar Brothers Civil Site Engineer interview:
  • Hr Fresher
Interview preparation tips for other job seekers - Civil engineering is a significant contribution that is essential for our lives.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Recruitment Consulltant and was interviewed in Aug 2024. There was 1 interview round.

Round 1 - HR 

(1 Question)

  • Q1. What's finance condition ur company
  • Ans. 

    The finance condition of our company is stable with a healthy cash flow and strong financial performance.

    • Our company has a positive cash flow, allowing us to meet financial obligations and invest in future projects.

    • We have a strong financial performance, with consistent profits and revenue growth.

    • We maintain a healthy balance sheet, with manageable debt levels and sufficient liquidity.

    • Our financial condition allows us ...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Project management in building construction & executive project
Interview experience
3
Average
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. About civil structure
Round 3 - Technical 

(1 Question)

  • Q1. About civil structure

ABB Interview FAQs

What are the top questions asked in ABB Civil Site Engineer interview?

Some of the top questions asked at the ABB Civil Site Engineer interview -

  1. What are quality point at the pouring time of concret...read more
  2. Complete Process of tower foundation day by d...read more
  3. What is cube mould siz...read more

Tell us how to improve this page.

Join ABB Helping industries outrun with our leading technologies

Interview Questions from Similar Companies

Siemens Interview Questions
4.1
 • 416 Interviews
Johnson Controls Interview Questions
3.5
 • 261 Interviews
Tata Power Interview Questions
3.9
 • 161 Interviews
BHEL Interview Questions
4.1
 • 113 Interviews
GE Interview Questions
4.2
 • 102 Interviews
View all
ABB Civil Site Engineer Salary
based on 10 salaries
₹3.5 L/yr - ₹9 L/yr
63% more than the average Civil Site Engineer Salary in India
View more details

ABB Civil Site Engineer Reviews and Ratings

based on 6 reviews

2.7/5

Rating in categories

2.7

Skill development

1.5

Work-life balance

3.2

Salary

1.8

Job security

2.1

Company culture

3.0

Promotions

2.6

Work satisfaction

Explore 6 Reviews and Ratings
Project Engineer
594 salaries
unlock blur

₹4.8 L/yr - ₹18.3 L/yr

R&D Engineer
322 salaries
unlock blur

₹6.5 L/yr - ₹22.2 L/yr

Financial Analyst
256 salaries
unlock blur

₹2 L/yr - ₹10 L/yr

Design Engineer
241 salaries
unlock blur

₹2 L/yr - ₹10.5 L/yr

Finance Specialist
196 salaries
unlock blur

₹2.8 L/yr - ₹7.5 L/yr

Explore more salaries
Compare ABB with

Siemens

4.1
Compare

Schneider Electric

4.1
Compare

Emerson Electric Co.

4.1
Compare

Honeywell International India

3.9
Compare
Did you find this page helpful?
Yes No
write
Share an Interview