I applied via Referral and was interviewed in May 2022. There were 3 interview rounds.
Concrete specifications and mixing procedures
Concrete specifications include strength, slump, air content, and maximum aggregate size
Mixing procedures involve proper proportioning of materials, thorough mixing, and appropriate curing
Concrete should be mixed for at least 2 minutes and not more than 5 minutes
Water-cement ratio should be maintained as per the specifications
Admixtures can be added to improve the properties
Top trending discussions
I applied via Naukri.com and was interviewed in Jul 2022. There were 3 interview rounds.
I applied via Company Website and was interviewed in Aug 2024. There were 3 interview rounds.
Plaster wall thickness 6mm slab bottom
12mm plaster smooth surface
Cube test after 7 day nd 14 day
Slump cone test true
I applied via Referral and was interviewed in Apr 2024. There was 1 interview round.
Slab shuttering is checked by ensuring proper alignment, levelness, and stability of formwork before concrete pouring.
Check alignment of formwork with respect to the structural drawings
Ensure formwork is level using a spirit level
Inspect the stability of formwork to prevent any collapse during concrete pouring
Check for any gaps or misalignments in the formwork that may affect the quality of the slab
Verify that all nece...
Concrete quantity can be calculated by multiplying the volume of the area to be filled by the density of the concrete.
Calculate the volume of the area to be filled (length x width x height)
Determine the density of the concrete (usually around 2400 kg/m^3)
Multiply the volume by the density to get the total concrete quantity needed
Consider adding a percentage for wastage or spillage
Lapping is provided in columns to ensure proper bonding between the column reinforcement and the beam reinforcement.
Lapping is typically provided at the junction of vertical and horizontal reinforcement bars in columns.
It helps in transferring the load from the column to the beam effectively.
The length of lapping required is specified in the structural drawings or as per design requirements.
Proper lapping ensures struc...
I applied via Walk-in and was interviewed in Feb 2023. There were 3 interview rounds.
Technical and practical experience with quality aspects
I applied via Walk-in and was interviewed before Nov 2023. There was 1 interview round.
I applied via Referral and was interviewed before Nov 2022. There was 1 interview round.
I applied via Approached by Company and was interviewed before Sep 2021. There were 2 interview rounds.
Steel testing includes mechanical, chemical, and physical tests to ensure quality and safety.
Mechanical tests include tensile, compression, and impact tests to measure strength and toughness.
Chemical tests analyze the composition of the steel to ensure it meets required standards.
Physical tests include hardness, corrosion resistance, and fatigue tests to assess durability and performance.
Non-destructive testing methods...
Site Engineer
26
salaries
| ₹2.1 L/yr - ₹4.8 L/yr |
Assistant Project Manager
20
salaries
| ₹4.2 L/yr - ₹8.5 L/yr |
Senior Engineer
19
salaries
| ₹3.6 L/yr - ₹8.1 L/yr |
Civil Site Engineer
16
salaries
| ₹2 L/yr - ₹3.6 L/yr |
Assistant Manager
12
salaries
| ₹4.4 L/yr - ₹7.5 L/yr |
Tata Group
Reliance Industries
Aditya Birla Group
Mahindra & Mahindra