Filter interviews by
I applied via Indeed and was interviewed in Dec 2024. There were 3 interview rounds.
PPM of dosing can be calculated by dividing the weight of the solute by the weight of the solution and multiplying by 1,000,000.
Calculate the weight of the solute (in grams)
Calculate the weight of the solution (in grams)
Divide the weight of the solute by the weight of the solution
Multiply the result by 1,000,000 to get the ppm
Aerobic and anaerobic digesters are systems used to break down organic matter. FM ratio is the ratio of food waste to microorganisms in the digester.
Aerobic digester uses oxygen to break down organic matter, while anaerobic digester operates without oxygen.
Aerobic digesters are faster but require more energy, while anaerobic digesters are slower but more energy efficient.
FM ratio (Food to Microorganism ratio) is the ra...
Yes, I have extensive experience in pump and motors as well as electrical components.
I have worked with various types of pumps and motors, including centrifugal pumps and induction motors.
I am familiar with troubleshooting and repairing electrical components such as circuit breakers and control panels.
I have experience in conducting preventive maintenance on pumps and motors to ensure optimal performance.
I have knowled...
I have 5 years of experience in the construction industry with a salary range of $50,000 to $70,000.
5 years of experience in construction industry
Salary range between $50,000 to $70,000
Familiar with industry standards for compensation
Negotiated salary increases based on performance
Received bonuses for meeting project deadlines
I applied via Recruitment Consulltant and was interviewed in Oct 2023. There was 1 interview round.
ETP stands for Effluent Treatment Plant, which is used to treat wastewater before it is discharged into the environment.
ETP removes contaminants from wastewater through physical, chemical, and biological processes.
It helps in reducing the pollution load in water bodies by treating industrial effluents.
Common processes in ETP include screening, sedimentation, biological treatment, and disinfection.
ETP plays a crucial ro...
Designing an ETP involves determining the required treatment processes, sizing the equipment, and ensuring compliance with regulations.
Identify the type and volume of wastewater to be treated
Select appropriate treatment processes such as physical, chemical, and biological
Size the equipment based on the flow rate and characteristics of the wastewater
Consider factors like space availability, budget, and regulatory requir...
Parameters to check in ETP include pH level, temperature, turbidity, dissolved oxygen, and chemical dosing.
pH level
Temperature
Turbidity
Dissolved oxygen
Chemical dosing
COD is Chemical Oxygen Demand, BOD is Biochemical Oxygen Demand, FM ratio is Food to Microorganism ratio.
COD is a measure of the amount of oxygen required to chemically oxidize organic matter in water.
BOD is a measure of the amount of oxygen required by microorganisms to break down organic matter in water.
FM ratio is the ratio of food (organic matter) to microorganisms in a biological treatment system.
Example: A high C...
Achieving final water parameters involves proper testing, treatment, and monitoring.
Perform regular water testing to monitor parameters such as pH, chlorine levels, and turbidity
Adjust treatment methods based on test results to maintain optimal water quality
Implement proper filtration systems to remove impurities and contaminants
Regularly monitor and maintain equipment to ensure efficient operation
Train staff on proper
I applied via Approached by Company and was interviewed in Feb 2023. There were 2 interview rounds.
I applied via Monster and was interviewed before Jan 2023. There was 1 interview round.
Rochem Separation Systems interview questions for popular designations
I applied via Approached by Company and was interviewed before Nov 2021. There were 2 interview rounds.
I applied via Referral
I applied via Referral and was interviewed before Apr 2022. There were 2 interview rounds.
I applied via Naukri.com and was interviewed before Jan 2022. There were 2 interview rounds.
I applied via Naukri.com and was interviewed before Aug 2021. There were 3 interview rounds.
Working scenario asked. about material costing. have explained and cleared doubts
I applied via Naukri.com and was interviewed before Sep 2021. There were 2 interview rounds.
Top trending discussions
The duration of Rochem Separation Systems interview process can vary, but typically it takes about less than 2 weeks to complete.
based on 11 interviews
Interview experience
based on 226 reviews
Rating in categories
Service Engineer
118
salaries
| ₹1.8 L/yr - ₹5.6 L/yr |
Technician
37
salaries
| ₹2 L/yr - ₹3.3 L/yr |
Design Engineer
21
salaries
| ₹1.8 L/yr - ₹5.2 L/yr |
Senior Service Engineer
21
salaries
| ₹3 L/yr - ₹9.6 L/yr |
RO Plant Operator
20
salaries
| ₹1 L/yr - ₹3 L/yr |
Alfa Laval
GEA Group
Pall Corporation
ANDRITZ SEPARATION