Cables in a cable drum can be identified by checking the cable tags, color coding, cable length, and cable type.
Check the cable tags for identification information
Look for color coding on the cables
Measure the cable length to match with specifications
Identify the cable type based on markings or specifications
I applied via Recruitment Consulltant and was interviewed before Oct 2023. There was 1 interview round.
JHA stands for Job Hazard Analysis, a process used to identify and control potential hazards in the workplace.
Identify the job or task to be analyzed
Break down the job into steps
Identify potential hazards for each step
Determine preventive measures to control the hazards
Document the JHA and communicate it to relevant personnel
HSE responsibilities include ensuring health, safety, and environmental regulations are followed in the workplace.
Developing and implementing health and safety policies
Conducting risk assessments and identifying hazards
Training employees on safety procedures
Investigating accidents and near misses
Ensuring compliance with regulations and standards
Promoting a culture of safety and environmental awareness
I applied via Company Website and was interviewed before Dec 2022. There were 2 interview rounds.
Medgulf Construction Company interview questions for popular designations
I applied via Referral and was interviewed before Jan 2022. There were 2 interview rounds.
Top trending discussions
posted on 13 May 2018
I was interviewed before May 2017.
A line chart for a 10 km action plan with safety precautions, procurement, manpower, and equipment.
Identify safety precautions needed for the project
Procure necessary equipment and manpower
Create a timeline for the project
Allocate resources efficiently
Ensure compliance with regulations and standards
Monitor progress and adjust plan as needed
To calculate pup-piece length for a 12 inch pipeline with two sections already lowered and overlap 5m and s-bend rolling, two 90 degree LR bends.
Calculate the total length of the pipeline
Subtract the length of the two sections already lowered and overlap 5m
Add the length of the two 90 degree LR bends
Divide the result by 2 to get the length of each pup-piece
Collapse and damage percentage for HDD crossings are calculated based on various factors such as soil type, borehole diameter, and drilling fluid properties.
Collapse percentage is calculated using the Mohr-Coulomb failure criterion
Damage percentage is calculated based on the tensile strength of the pipe and the bending stress induced during the pullback process
Factors such as soil type, borehole diameter, and drilling ...
Methodology for rock excavation involves drilling, blasting, and removal of debris. Quantity is measured by volume or weight.
Drilling holes in rock using specialized equipment
Placing explosives in the holes and detonating them
Removing the debris using heavy machinery
Measuring the quantity of rock excavated by volume or weight
Using software to calculate the amount of explosives needed for a specific excavation project
posted on 4 Apr 2021
Piles are used in construction to transfer loads from a structure to a stronger layer of soil or rock below the surface.
Types of piles include driven piles, bored piles, and screw piles.
Piles are provided to support structures on weak or compressible soil, to resist uplift forces, or to provide lateral support.
The diameter of a pile is determined based on the load it needs to support and the soil conditions.
LVUP (Large...
posted on 9 Oct 2020
I applied via Company Website and was interviewed in Sep 2020. There were 3 interview rounds.
I have experience working with a batching plant that can produce 30 cubic meters per hour.
I have operated and maintained a batching plant with a capacity of 30 cubic meters per hour.
I am familiar with the process of batching and mixing concrete.
I have experience troubleshooting and resolving issues with the batching plant.
I have ensured that the batching plant is always in good working condition and meets safety standa...
I applied via Naukri.com and was interviewed in Jun 2020. There were 4 interview rounds.
based on 8 interviews
Interview experience
based on 91 reviews
Rating in categories
Mechanical Engineer
7
salaries
| ₹6.6 L/yr - ₹22 L/yr |
HSE Officer
7
salaries
| ₹6.3 L/yr - ₹10 L/yr |
Construction Management
5
salaries
| ₹51 L/yr - ₹80 L/yr |
Instrument Engineer
5
salaries
| ₹8.4 L/yr - ₹30 L/yr |
Safety Officer
5
salaries
| ₹3 L/yr - ₹8 L/yr |
Larsen & Toubro Limited
Tata Projects
Shapoorji Pallonji Group
Hindustan Construction Company