RCC Mivon shuttering experience involves using reinforced concrete construction techniques for formwork and scaffolding.
Experience in setting up formwork and scaffolding for reinforced concrete structures
Knowledge of RCC Mivon shuttering techniques and materials
Ability to interpret construction drawings and plans for RCC Mivon shuttering
Experience in coordinating with construction teams and contractors for RCC Mivon sh
I applied via Approached by Company and was interviewed before Aug 2022. There were 4 interview rounds.
Top trending discussions
I applied via Naukri.com and was interviewed in Jan 2021. There was 1 interview round.
CRM is a process that helps businesses manage their interactions with customers throughout the customer lifecycle.
CRM stands for Customer Relationship Management.
It involves acquiring, analyzing, and utilizing customer data to improve customer satisfaction and loyalty.
The process includes various stages such as lead generation, customer acquisition, customer service, and customer retention.
CRM systems often include fea...
I applied via Naukri.com and was interviewed in May 2021. There was 1 interview round.
I applied via Referral and was interviewed in Feb 2021. There were 3 interview rounds.
I applied via Recruitment Consulltant and was interviewed before Feb 2022. There were 2 interview rounds.
I will start by conducting a site survey and obtaining necessary permits and approvals.
Conduct a site survey to assess the land and determine the best location for the construction
Obtain necessary permits and approvals from local authorities
Develop a detailed plan for the construction process, including timelines and budget
Hire a team of contractors and subcontractors to carry out the construction work
Ensure compliance...
The number of days for slab cycle in Mivan technology varies depending on the project and the size of the slab.
The duration of slab cycle in Mivan technology is project-specific.
The size of the slab also affects the number of days for slab cycle.
Factors such as weather conditions and availability of resources can also impact the duration of slab cycle.
On average, slab cycle in Mivan technology can take anywhere from 3 ...
I applied via Job Portal and was interviewed in Sep 2022. There were 2 interview rounds.
based on 3 interviews
Interview experience
based on 38 reviews
Rating in categories
Assistant Manager
163
salaries
| ₹6.2 L/yr - ₹15.2 L/yr |
Project Engineer
57
salaries
| ₹4.5 L/yr - ₹9 L/yr |
Manager
47
salaries
| ₹8.7 L/yr - ₹21 L/yr |
Project Manager
34
salaries
| ₹9.8 L/yr - ₹19.5 L/yr |
Senior Manager
29
salaries
| ₹14 L/yr - ₹32.5 L/yr |
Omaxe
Emaar India Limited
Brigade Group
Puravankara