Shuttering quantity calculation involves determining the amount of formwork needed for a construction project.
Calculate the surface area of the structure that needs formwork
Determine the type of formwork material to be used
Consider the complexity of the structure and any special requirements
Account for wastage and extra material for safety
Use standard formulas or software for accurate calculations
posted on 22 Nov 2023
I applied via Campus Placement and was interviewed in Oct 2023. There were 2 interview rounds.
posted on 17 Mar 2024
I applied via Walk-in and was interviewed in Sep 2023. There was 1 interview round.
Earth cutting as per CPWD norms involves following specific guidelines for excavation work.
CPWD norms specify the depth and width of excavation for different types of soil
The guidelines also include safety measures to be followed during earth cutting
Proper disposal of excavated material is also a key aspect of CPWD norms
Deductions in measurements include shrinkage, wastage, breakage, and spillage.
Shrinkage: Reduction in size or weight of materials during handling or storage.
Wastage: Loss of materials during the construction process.
Breakage: Damage to materials during transportation or handling.
Spillage: Accidental loss of materials due to spills or leaks.
posted on 30 Jun 2024
I applied via Approached by Company and was interviewed in Dec 2023. There was 1 interview round.
posted on 25 May 2024
I applied via Referral and was interviewed before May 2023. There was 1 interview round.
posted on 29 May 2023
I applied via Walk-in and was interviewed in Nov 2022. There were 3 interview rounds.
I applied via Walk-in and was interviewed before Apr 2023. There were 2 interview rounds.
posted on 12 Feb 2024
I applied via Newspaper Ad and was interviewed before Feb 2023. There was 1 interview round.
The labor charges for main items like concrete, shuttering, and reinforcement steel vary depending on factors such as location, project size, and labor rates.
The labor charges for concrete are typically calculated based on the volume of concrete required and the prevailing labor rates.
The labor charges for shuttering (formwork) are usually determined based on the area of formwork required and the complexity of the desi...
Rolling margin is a financial metric that measures the profitability of a company's operations over a specific period of time.
Rolling margin is calculated by dividing the operating profit by the net sales and expressing it as a percentage.
It helps in evaluating the efficiency and profitability of a company's core business activities.
A higher rolling margin indicates better profitability and operational efficiency.
For e...
The allowable wastage percentage of a major item varies depending on the industry and project specifications.
The allowable wastage percentage is typically specified in the project contract or specifications.
It is important to minimize wastage to control costs and ensure efficient resource utilization.
The allowable wastage percentage may differ for different major items, such as concrete, steel, or electrical materials.
...
I applied via Walk-in and was interviewed before Jun 2021. There was 1 interview round.
based on 10 reviews
Rating in categories
Assistant Manager
646
salaries
| ₹5.2 L/yr - ₹20 L/yr |
Senior Engineer
437
salaries
| ₹4.3 L/yr - ₹13 L/yr |
Civil Engineer
226
salaries
| ₹1 L/yr - ₹9.5 L/yr |
Project Engineer
217
salaries
| ₹3 L/yr - ₹11 L/yr |
Safety Officer
208
salaries
| ₹2 L/yr - ₹9 L/yr |
Larsen & Toubro Limited
Tata Projects
Sterlite Power
Kalpataru Projects International