I manage the team by setting clear goals, providing support and resources, fostering open communication, and recognizing achievements.
Set clear goals and expectations for team members
Provide necessary support and resources for team to succeed
Foster open communication and collaboration within the team
Recognize and reward team achievements to boost morale
Critical path is the longest sequence of tasks in a project that must be completed on time in order for the project to finish on schedule.
Critical path helps in identifying the minimum amount of time needed to complete a project.
It consists of tasks that have zero slack or float, meaning any delay in these tasks will delay the entire project.
Activities on the critical path are often depicted in a project management Gan...
To prepare a baseline schedule, you need to establish project scope, identify key milestones, determine task dependencies, estimate durations, assign resources, and finalize the schedule.
Establish the project scope and objectives
Identify key milestones and deliverables
Determine task dependencies and sequence of activities
Estimate durations for each task
Assign resources to tasks
Finalize the schedule with start and end d
I applied via Approached by Company and was interviewed in Sep 2022. There were 3 interview rounds.
Delete removes an activity from the project, while dissolve removes a relationship between activities.
Delete removes an activity from the project and all its relationships with other activities.
Dissolve removes a relationship between two activities, but the activities themselves remain in the project.
Deleting an activity can have a cascading effect on the rest of the project, while dissolving a relationship only affect...
I prepare programme by identifying objectives, breaking them down into tasks, assigning resources and setting timelines.
Identify objectives and goals
Break down objectives into smaller tasks
Assign resources and responsibilities to team members
Set timelines and deadlines for each task
Regularly review and update the programme to ensure progress is on track
I applied via Walk-in and was interviewed in May 2020. There were 4 interview rounds.
I can add value to their current process by leveraging my past experience in material planning.
I have successfully optimized inventory levels in my previous role, resulting in cost savings.
I have implemented a demand forecasting system that improved accuracy and reduced stockouts.
I have developed strong relationships with suppliers, negotiating better pricing and terms.
I have implemented lean manufacturing principles, ...