Upload Button Icon Add office photos

Dilip Buildcon

Compare button icon Compare button icon Compare

Filter interviews by

Dilip Buildcon Electrical Engineer Interview Questions and Answers

Updated 19 Oct 2023

Dilip Buildcon Electrical Engineer Interview Experiences

2 interviews found

Interview experience
5
Excellent
Difficulty level
-
Process Duration
-
Result
-
Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(3 Questions)

  • Q1. What is Full form DOL starter
  • Ans. 

    DOL starter stands for Direct-On-Line starter, used to start motors by directly connecting them to the power supply.

    • DOL starter is the simplest and most common type of motor starter.

    • It directly connects the motor to the power supply without any intermediate starting method.

    • It provides full voltage to the motor during starting, which can cause high inrush current.

    • DOL starters are suitable for small to medium-sized motor...

  • Answered by AI
  • Q2. What is APFC PANEL
  • Ans. 

    APFC PANEL stands for Automatic Power Factor Correction Panel, used to maintain power factor in electrical systems.

    • APFC PANEL automatically monitors and corrects the power factor of electrical systems.

    • It helps in reducing electricity bills by maintaining a high power factor.

    • APFC PANELs are commonly used in industries and commercial buildings.

    • They consist of capacitors that are switched on and off based on the load requ...

  • Answered by AI
  • Q3. Star dalta conection

I applied via Walk-in and was interviewed in Jul 2019. There was 1 interview round.

Interview Questionnaire 

3 Questions

  • Q1. Are u give me a chance fighting for this task.....
  • Q2. If i "m qualifing this task in your comny so how many days in u r providing me joining letter.....
  • Q3. What is your comny expensive for engineer.
  • Ans. 

    Company expenses for engineers include salaries, benefits, training, equipment, and travel costs.

    • Salaries are a major expense for engineers, varying based on experience and specialization.

    • Benefits such as healthcare, retirement plans, and bonuses add to the overall expense.

    • Training programs to keep engineers updated with the latest technologies can be costly.

    • Equipment and tools needed for engineering work can be a sign...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - really i knw dilip buildcon is also high peofile of comny nd its lots of monthly turnover so im also want completing this task and joine to your company for better future with the honestfully as a good engineer

Electrical Engineer Interview Questions Asked at Other Companies

Q1. What is the difference between Switch gear & Circuit Breakers ... read more
Q2. What is ATS, transformer maintenance procedure, protection of tra ... read more
asked in Tata Steel
Q3. 1.what is composite error and ratio error in current transformer?
Q4. 1. Power factor of transformer 2. types of DC machine 3. Working ... read more
Q5. How many types of transformer according to voltage transfer

Interview questions from similar companies

I applied via Recruitment Consultant and was interviewed before Aug 2020. There were 5 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. Machinery maintenance Dpr maintenance,local purchasing,

Interview Preparation Tips

Interview preparation tips for other job seekers - Nice,good and teritical intrew done and completed

Interview Questionnaire 

3 Questions

  • Q1. What is android architecture stack?
  • Q2. What is AIDL?
  • Ans. 

    AIDL stands for Android Interface Definition Language, used for inter-process communication in Android.

    • AIDL is used to define the interface between client and service in Android.

    • It allows communication between different processes in Android.

    • AIDL is used to pass complex data types between processes.

    • AIDL is similar to Remote Procedure Call (RPC) in other programming languages.

    • Example: AIDL is used in Android to implement...

  • Answered by AI
  • Q3. What is hash set and hash map
  • Ans. 

    Hash set and hash map are data structures used to store key-value pairs for efficient retrieval.

    • Hash set stores unique values without any specific order.

    • Hash map stores key-value pairs and allows fast retrieval of values based on keys.

    • Both use hashing to map keys to their corresponding values.

    • In Java, HashSet and HashMap are implementations of these data structures.

  • Answered by AI

Skills evaluated in this interview

I applied via Company Website and was interviewed before Apr 2020. There were 4 interview rounds.

Interview Questionnaire 

2 Questions

  • Q1. Load distribution under rigid and flexible footings,water tank design, steel foundation design
  • Q2. Mix design of concrete, btech project
  • Ans. 

    Mix design of concrete and BTech project

    • Mix design involves determining the proportions of cement, water, aggregates, and admixtures to achieve desired properties of concrete

    • Factors like strength, workability, durability, and cost are considered while designing the mix

    • BTech project can involve studying the effect of different mix designs on properties of concrete or developing a new mix design

    • Examples of BTech projects...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - be well prepared with basics and if you are already experienced, be prepared with site knowledge

Interview Questionnaire 

3 Questions

  • Q1. How many time u take any update shuttering system?
  • Ans. 

    The question is unclear and lacks context.

    • Please provide more information about the 'update shuttering system'.

    • Specify the time frame for the updates.

    • Clarify the purpose or objective of the updates.

    • Provide any relevant examples or scenarios.

  • Answered by AI
  • Q2. Why u want to work as a execution engineer? Why not any special team such as formwork team,or quality team?
  • Ans. 

    I want to work as an execution engineer because I enjoy the challenge of overseeing and coordinating all aspects of a project.

    • As an execution engineer, I would have the opportunity to work on a variety of projects and oversee all aspects of their execution.

    • I enjoy the challenge of coordinating different teams and ensuring that everything runs smoothly.

    • While working on a formwork or quality team would be valuable experi...

  • Answered by AI
  • Q3. As contractor farm Engineer in RCC which is most important? 1) Reinforcements 2)Formwork 3)Concrete And why?
  • Ans. 

    Concrete is the most important as it provides the strength and durability to the structure.

    • Concrete is the backbone of any RCC structure.

    • It provides the strength and durability to the structure.

    • Reinforcements and formwork are important too, but without concrete, they are useless.

    • Proper mix design and curing of concrete are crucial for the longevity of the structure.

  • Answered by AI

I appeared for an interview before Jul 2016.

Interview Preparation Tips

Round: Group Discussion
Duration: 4 hours 5 minutes

Round: Test
Duration: 2 hours 5 minutes

I applied via Recruitment Consultant and was interviewed in Nov 2019. There were 3 interview rounds.

Interview Questionnaire 

3 Questions

  • Q1. My past work related questions
  • Q2. Bbs, reinforcement formula
  • Q3. Concrete realated

Interview Preparation Tips

Interview preparation tips for other job seekers - Your experience is the best teacher

I applied via Company Website and was interviewed before Oct 2020. There were 3 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. About site handling

Interview Preparation Tips

Interview preparation tips for other job seekers - Should be good technical knowledge

I applied via Recruitment Consultant and was interviewed in Apr 2020. There were 3 interview rounds.

Interview Questionnaire 

1 Question

  • Q1. About HT/LT,Motor/Feeder & Substation Errection & Commission.

Interview Preparation Tips

Interview preparation tips for other job seekers - Good Questions Are Asked.

Dilip Buildcon Interview FAQs

How many rounds are there in Dilip Buildcon Electrical Engineer interview?
Dilip Buildcon interview process usually has 2 rounds. The most common rounds in the Dilip Buildcon interview process are Resume Shortlist and Technical.
How to prepare for Dilip Buildcon Electrical Engineer interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Dilip Buildcon. The most common topics and skills that interviewers at Dilip Buildcon expect are Electrical Engineering and Electricals.
What are the top questions asked in Dilip Buildcon Electrical Engineer interview?

Some of the top questions asked at the Dilip Buildcon Electrical Engineer interview -

  1. What is Full form DOL star...read more
  2. What is APFC PA...read more
  3. if i "m qualifing this task in your comny so how many days in u r providing me ...read more

Tell us how to improve this page.

Dilip Buildcon Electrical Engineer Interview Process

based on 2 interviews

Interview experience

3.5
  
Good
View more

Fast track your campus placements

View all
Dilip Buildcon Electrical Engineer Salary
based on 71 salaries
₹2.4 L/yr - ₹6.2 L/yr
6% less than the average Electrical Engineer Salary in India
View more details

Dilip Buildcon Electrical Engineer Reviews and Ratings

based on 17 reviews

3.5/5

Rating in categories

3.4

Skill development

3.3

Work-life balance

2.9

Salary

3.3

Job security

3.1

Company culture

2.8

Promotions

3.5

Work satisfaction

Explore 17 Reviews and Ratings
Assistant Manager
210 salaries
unlock blur

₹4 L/yr - ₹12.1 L/yr

Senior Engineer
210 salaries
unlock blur

₹4 L/yr - ₹10.9 L/yr

Asst Store
202 salaries
unlock blur

₹1.6 L/yr - ₹4 L/yr

Store Executive
190 salaries
unlock blur

₹1.5 L/yr - ₹5 L/yr

Structural Engineer
179 salaries
unlock blur

₹2 L/yr - ₹6.7 L/yr

Explore more salaries
Compare Dilip Buildcon with

Larsen & Toubro Limited

3.9
Compare

L&T Construction

4.0
Compare

Tata Projects

4.2
Compare

Megha Engineering & Infrastructures

3.9
Compare
Did you find this page helpful?
Yes No
write
Share an Interview