I applied via Walk-in and was interviewed in Jun 2022. There were 3 interview rounds.
Top trending discussions
posted on 14 Oct 2023
I applied via Naukri.com and was interviewed in Apr 2023. There were 3 interview rounds.
Process of variation involves documenting and analyzing changes in project scope, cost, or schedule.
Variations are changes to the original scope, cost, or schedule of a project
Variations must be documented and approved by the relevant parties
The impact of variations on project budget and timeline must be analyzed
Examples of variations include design changes, unforeseen site conditions, and client requests
I applied via Recruitment Consulltant and was interviewed before Apr 2021. There was 1 interview round.
Rate analysis for plaster involves calculating the cost of materials, labor, and equipment required for plastering a specific area.
Determine the area to be plastered
Calculate the quantity of materials required (cement, sand, water)
Determine the cost of materials per unit
Calculate the cost of labor per unit area
Include the cost of equipment and tools used
Add all costs to get the total cost of plastering
Example: For plas...
BBS is Bar Bending Schedule used for steel reinforcement and BOQ is Bill of Quantities used for building items.
BBS provides details of reinforcement steel required for construction.
BOQ lists all the materials and quantities required for construction.
BBS is used for steel reinforcement in structures like columns, beams, slabs, etc.
BOQ is used for building items like bricks, cement, sand, etc.
Both BBS and BOQ are importa...
posted on 14 Oct 2023
I applied via Naukri.com and was interviewed in Apr 2023. There were 3 interview rounds.
Process of variation involves documenting and analyzing changes in project scope, cost, or schedule.
Variations are changes to the original scope, cost, or schedule of a project
Variations must be documented and approved by the relevant parties
The impact of variations on project budget and timeline must be analyzed
Examples of variations include design changes, unforeseen site conditions, and client requests
I applied via Recruitment Consulltant and was interviewed before Apr 2021. There was 1 interview round.
Rate analysis for plaster involves calculating the cost of materials, labor, and equipment required for plastering a specific area.
Determine the area to be plastered
Calculate the quantity of materials required (cement, sand, water)
Determine the cost of materials per unit
Calculate the cost of labor per unit area
Include the cost of equipment and tools used
Add all costs to get the total cost of plastering
Example: For plas...
BBS is Bar Bending Schedule used for steel reinforcement and BOQ is Bill of Quantities used for building items.
BBS provides details of reinforcement steel required for construction.
BOQ lists all the materials and quantities required for construction.
BBS is used for steel reinforcement in structures like columns, beams, slabs, etc.
BOQ is used for building items like bricks, cement, sand, etc.
Both BBS and BOQ are importa...
Interview experience
based on 10 reviews
Rating in categories
Civil Site Engineer
47
salaries
| ₹2 L/yr - ₹5.3 L/yr |
Senior Engineer
23
salaries
| ₹4.2 L/yr - ₹8.5 L/yr |
Safety Officer
17
salaries
| ₹3 L/yr - ₹5.5 L/yr |
Billing Engineer
16
salaries
| ₹3 L/yr - ₹7.2 L/yr |
Accountant
13
salaries
| ₹2.5 L/yr - ₹3.6 L/yr |
Larsen & Toubro Limited
TCS
Reliance Industries
Hindustan Unilever