I applied via Approached by Company and was interviewed in Aug 2022. There were 2 interview rounds.
The compressive strength of M30 grade concrete in day 7 is 22.5 N/mm².
The compressive strength of concrete is measured in N/mm².
M30 grade concrete has a compressive strength of 30 N/mm² at 28 days.
The compressive strength of M30 grade concrete at day 7 is approximately 60% of its 28-day strength.
The compressive strength of M30 grade concrete at day 7 is 22.5 N/mm².
Mix designs are the process of determining the proportions of various ingredients to create a concrete mix with desired properties.
Mix designs involve selecting the appropriate materials for the concrete mix
The proportions of each material are determined based on the desired strength, workability, and durability of the concrete
Factors such as water-cement ratio, aggregate size and type, and admixtures are considered in...
Before starting a new site, certain basic things need to be considered.
Site location and accessibility
Availability of resources like water, electricity, and raw materials
Environmental impact assessment
Legal permits and approvals
Safety measures and emergency plans
Budget and timeline
Project management and team coordination
The size of bricks and blocks varies, and their compressive strength depends on the materials used.
Bricks can range in size from 2.25 x 3.75 x 7.5 inches to 3.5 x 4.5 x 9 inches
Blocks can range in size from 4 x 8 x 16 inches to 8 x 8 x 16 inches
Compressive strength can range from 1,000 psi to over 10,000 psi depending on materials and manufacturing process
Things to consider while flooring
Type of flooring material
Durability and maintenance
Moisture resistance
Slip resistance
Aesthetics and design
Cost and budget
Installation process
I have previous experience working as an assistant engineer in the field of [field].
Worked as an assistant engineer at [Company A] for [duration].
Assisted in designing and implementing [specific projects or tasks].
Collaborated with a team of engineers to troubleshoot and resolve technical issues.
Utilized [specific software or tools] to analyze data and generate reports.
Participated in regular meetings and provided upda...
posted on 10 Sep 2017
I was interviewed before Sep 2016.
posted on 10 Sep 2015
I applied via PLACEMENT
posted on 11 May 2018
posted on 12 May 2018
I was interviewed before Mar 2020.
posted on 18 Jan 2020
I applied via Naukri.com and was interviewed in Jul 2019. There were 3 interview rounds.
Maintain elevation of underground piping by using level instruments and proper installation techniques.
Use a level instrument to check the elevation of the piping during installation.
Ensure that the piping is installed with a consistent slope to prevent low spots where water can accumulate.
Regularly inspect the piping to ensure that it has not shifted or settled, which can affect the elevation.
Consider using supports o...
In my previous role as Assistant Manager, I was responsible for overseeing daily operations, managing staff, and ensuring customer satisfaction.
Managed a team of employees and delegated tasks effectively
Handled customer complaints and resolved issues in a timely manner
Created and implemented strategies to improve efficiency and productivity
Collaborated with other departments to achieve company goals
Conducted performanc
Welding electrodes are chosen based on the material being welded. Different materials require different types of electrodes.
Electrodes for mild steel have a coating that produces a stable arc and minimal spatter.
Stainless steel electrodes have a coating that resists corrosion and produces a smooth, clean weld.
Cast iron electrodes have a high nickel content to prevent cracking.
Aluminum electrodes have a special coating ...
posted on 12 Oct 2020
I applied via Naukri.com and was interviewed before Oct 2019. There were 3 interview rounds.
posted on 14 Jul 2021
posted on 4 Mar 2022
I applied via Approached by Company and was interviewed before Mar 2021. There was 1 interview round.
based on 8 reviews
Rating in categories
Civil Site Engineer
48
salaries
| ₹0 L/yr - ₹0 L/yr |
Assistant Engineer
46
salaries
| ₹0 L/yr - ₹0 L/yr |
Assistant Engineer - Civil
29
salaries
| ₹0 L/yr - ₹0 L/yr |
Site Engineer
25
salaries
| ₹0 L/yr - ₹0 L/yr |
Safety Engineer
19
salaries
| ₹0 L/yr - ₹0 L/yr |
Larsen & Toubro Limited
Shapoorji Pallonji Group
Tata Projects
Hindustan Construction Company