I applied via Naukri.com and was interviewed in Aug 2021. There was 1 interview round.
SPI and CPI are performance indicators used in project management to measure project progress and efficiency.
SPI (Schedule Performance Index) measures the project's progress against the planned schedule.
CPI (Cost Performance Index) measures the project's efficiency in terms of cost.
SPI and CPI values of 1 indicate that the project is on schedule and within budget.
Values greater than 1 indicate that the project is ahead...