Subject expert question
posted on 23 Nov 2019
The process for erection in complete pyro section involves assembling and installing all components for the pyro processing unit.
Prepare the site for erection by clearing the area and ensuring proper foundation
Assemble the various components of the pyro section such as kiln, preheater, cooler, and other equipment
Install the components according to the manufacturer's specifications and engineering drawings
Connect all ne...
I appeared for an interview before Feb 2024.
I applied via Campus Placement and was interviewed before May 2023. There was 1 interview round.
LT stands for Leadership Team.
LT refers to the group of leaders within an organization who make important decisions and set strategic direction.
Members of the LT typically include top executives such as the CEO, CFO, and other key department heads.
The LT is responsible for guiding the overall direction of the company and ensuring that goals are met.
They often meet regularly to discuss performance, challenges, and oppor
based on 1 review
Rating in categories
Assistant Manager
377
salaries
| ₹5 L/yr - ₹19 L/yr |
Manager
256
salaries
| ₹9 L/yr - ₹35 L/yr |
Senior Manager
168
salaries
| ₹10 L/yr - ₹41.5 L/yr |
Deputy Manager
139
salaries
| ₹6.1 L/yr - ₹23 L/yr |
Sales Manager
118
salaries
| ₹2 L/yr - ₹9 L/yr |
UltraTech Cement
JK Cement
Grasim Industries
ACC