Q1. What are earned value metrics? Draw S curve and cashflows.
Earned value metrics are project management tools used to measure project performance and progress.
Earned Value (EV): The budgeted cost of work performed.
Planned Value (PV): The budgeted cost of work scheduled.
Actual Cost (AC): The actual cost incurred for the work performed.
Cost Variance (CV): The difference between EV and AC.
Schedule Variance (SV): The difference between EV and PV.
S-Curve: Graphical representation of planned value, earned value, and actual cost over time.
Ca...read more
Q2. What are different activity types in P6?
Different activity types in P6 include Task, Milestone, Hammock, Level of Effort, and WBS Summary.
Task - Represents a specific work item with a duration and resources assigned
Milestone - Represents a significant event or achievement with zero duration
Hammock - Represents a summary task that spans multiple activities
Level of Effort - Represents work that is not tied to a specific duration or quantity
WBS Summary - Represents a summary of activities within a specific Work Breakd...read more
Q3. How bigger capacity pumping station have you worked in
I have worked in a pumping station with a capacity of 10,000 cubic meters per hour.
Worked in a pumping station with a capacity of 10,000 cubic meters per hour
Managed operations and maintenance of pumps, valves, and pipelines
Implemented efficiency improvements to optimize pumping station performance
Q4. What is depreciation?
Depreciation is the gradual decrease in the value of an asset over time due to wear and tear, obsolescence, or other factors.
Depreciation is an accounting method used to allocate the cost of an asset over its useful life.
It represents the reduction in value of tangible assets like buildings, vehicles, or equipment.
Depreciation expense is recorded on the income statement and accumulated depreciation is shown on the balance sheet.
Different methods of depreciation include straig...read more
Q5. What is bank reconciliation?
Bank reconciliation is the process of comparing and matching the balances in a company's accounting records with the bank statement.
Bank reconciliation ensures that the company's records accurately reflect the transactions and balances in its bank accounts.
It involves comparing the company's cash account balance with the bank statement balance and identifying any discrepancies.
Common reasons for discrepancies include outstanding checks, deposits in transit, bank fees, and err...read more
Q6. What is no cash expenses?
No cash expenses are expenses that do not involve the use of physical cash.
No cash expenses are transactions that are not paid for with cash.
These expenses are typically paid for using other forms of payment such as credit cards, checks, or electronic transfers.
Examples of no cash expenses include utility bills paid by direct debit, online purchases made with a credit card, or vendor payments made by electronic funds transfer.
Q7. What is peak factor
Peak factor is the ratio of the peak value of a signal to its RMS value.
Peak factor is used to measure the peak-to-average ratio of a signal.
It is calculated by dividing the peak value of a signal by its RMS value.
A higher peak factor indicates a signal with larger peaks and greater dynamic range.
For example, a sine wave with no distortion has a peak factor of √2 or approximately 1.414.
Q8. What are the maximum Tags for the SCADA system you have handled? IEC 104 protocol why is it used?
Handled over 10,000 tags in a SCADA system. IEC 104 protocol is used for real-time data communication in power systems.
Handled over 10,000 tags in a SCADA system
IEC 104 protocol is used for real-time data communication in power systems
Q9. All aspects of Planning
Planning in project control involves creating schedules, setting milestones, allocating resources, and monitoring progress.
Developing detailed project schedules
Setting milestones and deadlines
Allocating resources effectively
Monitoring progress and adjusting plans as needed
Q10. Tools about sewer gems
Sewer gems are tools used in network engineering for monitoring and troubleshooting network performance in complex systems.
Sewer gems are specialized software or hardware tools used by network engineers.
They help in monitoring and analyzing network traffic, identifying bottlenecks, and troubleshooting issues.
Examples of sewer gems include Wireshark, SolarWinds Network Performance Monitor, and Cisco Network Assistant.
Q11. What was the velocity of last month?
The velocity of last month was 35 story points.
Velocity is a measure of the amount of work a team can complete in a sprint.
It is usually measured in story points.
Velocity helps the team to plan future sprints based on past performance.
More about working at Stantec
Top HR Questions asked in CoreFlex Solutions
Interview Process at CoreFlex Solutions
Top Interview Questions from Similar Companies
Reviews
Interviews
Salaries
Users/Month