Filter interviews by
I applied via Walk-in
To check IR of XLPE cable, use a megger to measure insulation resistance.
Use a megger to measure insulation resistance of XLPE cable
Ensure the cable is de-energized before testing
Compare the measured IR value with the manufacturer's specifications
Repeat the test at different points along the cable for accuracy
Tests for transformers include turns ratio test, insulation resistance test, power factor test, and winding resistance test.
Turns ratio test measures the turns ratio between primary and secondary windings.
Insulation resistance test checks the insulation resistance of the transformer windings.
Power factor test evaluates the power factor of the transformer.
Winding resistance test measures the resistance of the transforme
Types of excavations include trench excavation, basement excavation, road excavation, and pit excavation.
Trench excavation involves digging a narrow channel in the ground for laying pipes or cables.
Basement excavation is the process of digging out the foundation of a building to create a below-ground level.
Road excavation is the removal of soil and rocks to construct or repair roads.
Pit excavation involves digging a la...
posted on 8 Jun 2024
I applied via Recruitment Consulltant and was interviewed before Jun 2023. There were 3 interview rounds.
Preventive and corrective maintenance of various electrical equipment including breakers, motors, transformers, and relays.
Perform regular maintenance on high and low voltage breakers, motors, and transformers.
Test and calibrate various protection relays for motors, transformers, and generators.
Conduct transformer oil BDV test, thermal scanning, and earth fault and prediction tests.
Terminate high voltage motors, instal...
Preventive and corrective maintenance of various electrical equipment including breakers, motors, transformers, and relays.
Perform regular maintenance tasks on high and low voltage breakers, motors, and transformers.
Test and calibrate protection relays for motors, transformers, and generators.
Conduct transformer oil BDV tests, thermal scanning, and earth fault and prediction tests.
Terminate high voltage motors, install...
Preventive and corrective maintenance of various electrical equipment including breakers, motors, transformers, switches, relays, and testing/calibration of protections.
Preventive maintenance of H.V & LV breakers, motors, transformers, switches, etc.
Corrective maintenance of HV/MV/LV switchgears, breakers, cubicles, etc.
Testing and calibration of various protection relays for motors, transformers, generators.
Transforme...
posted on 8 Jun 2024
I applied via Recruitment Consulltant and was interviewed before Jun 2023. There were 3 interview rounds.
I applied via Recruitment Consultant and was interviewed in May 2021. There were 3 interview rounds.
Stall in a motor refers to a condition where the motor stops rotating despite the presence of power supply.
Stall occurs when the motor is overloaded or when there is a mechanical obstruction preventing the motor from rotating.
It can also occur when the motor is underpowered or when there is a fault in the electrical system.
Stall can cause damage to the motor and other components if not addressed promptly.
Examples of mo...
UPS stands for Uninterruptible Power Supply. It is an electrical device that provides emergency power to a load when the input power source fails.
UPS has three main components: battery, inverter, and rectifier.
The battery provides backup power during a power outage.
The rectifier converts AC power to DC power to charge the battery.
The inverter converts DC power from the battery to AC power to supply the load.
UPS also ha...
based on 2 reviews
Rating in categories
Safety Officer
12
salaries
| ₹5 L/yr - ₹12 L/yr |
Senior Planning Engineer
11
salaries
| ₹10 L/yr - ₹30 L/yr |
Planning Engineer
11
salaries
| ₹7.9 L/yr - ₹29.2 L/yr |
HSE Advisor
10
salaries
| ₹12 L/yr - ₹24 L/yr |
HSE Officer
9
salaries
| ₹6 L/yr - ₹14 L/yr |
Larsen & Toubro Limited
TCS
Tech Mahindra
Wipro