I applied via Referral and was interviewed in Apr 2024. There was 1 interview round.
Slab shuttering is checked by ensuring proper alignment, levelness, and stability of formwork before concrete pouring.
Check alignment of formwork with respect to the structural drawings
Ensure formwork is level using a spirit level
Inspect the stability of formwork to prevent any collapse during concrete pouring
Check for any gaps or misalignments in the formwork that may affect the quality of the slab
Verify that all nece...
Concrete quantity can be calculated by multiplying the volume of the area to be filled by the density of the concrete.
Calculate the volume of the area to be filled (length x width x height)
Determine the density of the concrete (usually around 2400 kg/m^3)
Multiply the volume by the density to get the total concrete quantity needed
Consider adding a percentage for wastage or spillage
Lapping is provided in columns to ensure proper bonding between the column reinforcement and the beam reinforcement.
Lapping is typically provided at the junction of vertical and horizontal reinforcement bars in columns.
It helps in transferring the load from the column to the beam effectively.
The length of lapping required is specified in the structural drawings or as per design requirements.
Proper lapping ensures struc...
Civil Site Engineer
8
salaries
| ₹3.5 L/yr - ₹5.3 L/yr |
Manager
7
salaries
| ₹11.9 L/yr - ₹19 L/yr |
Assistant Manager
7
salaries
| ₹7.5 L/yr - ₹11.6 L/yr |
Deputy Manager MEP
5
salaries
| ₹12.3 L/yr - ₹20 L/yr |
Operations Executive
5
salaries
| ₹4.5 L/yr - ₹7 L/yr |
DLF
Godrej Properties
Prestige Group
Sobha