I applied via LinkedIn

Round 1 - One-on-one 

(5 Questions)

  • Q1. Piling work,MMS work, related questions
  • Q2. MCR building and switch yard questions
  • Q3. Reainforment releted questions
  • Q4. Land survey related questions
  • Q5. Pile casting related questions

Interview Preparation Tips

Topics to prepare for Oman Shapoorji Llc Diploma Civil Engineer interview:
  • Civil Construction
Interview preparation tips for other job seekers - Civil engineer

Interview questions from similar companies

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Recruitment Consulltant and was interviewed before Jan 2024. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. Regarding Underground Metro Station
  • Q2. Construction process of Underground Metro Station
  • Ans. 

    Construction process of Underground Metro Station involves excavation, tunneling, structural work, and finishing.

    • Excavation of the site to create space for the station and tunnels

    • Tunneling to create passages for trains and passengers

    • Structural work including building the station walls, platforms, and support structures

    • Installation of electrical, mechanical, and safety systems

    • Finishing touches such as flooring, lighting

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - If getting a chance to join Nesma, don't miss

I applied via Approached by Company and was interviewed in Mar 2022. There were 2 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Don’t add your photo or details such as gender, age, and address in your resume. These details do not add any value.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. Related to department

Interview Preparation Tips

Topics to prepare for Hyundai Engineering Civil Engineer interview:
  • Related to experience
Interview preparation tips for other job seekers - Please prepare professional cv related to work
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed in Jul 2024. There was 1 interview round.

Round 1 - Technical 

(5 Questions)

  • Q1. What is bar bending schedule
  • Ans. 

    Bar bending schedule is a document that provides details of reinforcement steel bars used in construction projects.

    • It includes details such as bar mark, bar size, quantity, shape, and bending dimensions.

    • Helps in estimating the quantity of steel required for construction.

    • Ensures proper placement and bending of reinforcement bars as per design specifications.

    • Used by contractors, engineers, and construction workers for re...

  • Answered by AI
  • Q2. 28 days concrete strength
  • Ans. 

    28 days concrete strength is the standard measure of concrete's compressive strength after 28 days of curing.

    • 28 days concrete strength is the standard measure of concrete's compressive strength after 28 days of curing

    • It is important for assessing the quality of concrete and its ability to support structural loads

    • The strength of concrete typically continues to increase beyond 28 days, but 28 days is the standard testing

  • Answered by AI
  • Q3. Difference between mivan and conventional
  • Ans. 

    Mivan is a modern construction technique using aluminum formwork, while conventional construction involves traditional methods like brick and mortar.

    • Mivan is faster and more efficient than conventional construction methods.

    • Mivan requires skilled labor for installation of aluminum formwork.

    • Conventional construction is more labor-intensive and time-consuming.

    • Mivan provides better quality finishes compared to conventional...

  • Answered by AI
  • Q4. What is self leveling concrete
  • Ans. 

    Self leveling concrete is a type of concrete that has a high flow consistency and is used to create smooth and level surfaces.

    • Self leveling concrete is designed to flow easily and settle into place without the need for troweling or leveling.

    • It is commonly used to level uneven floors before installing flooring materials such as tile or carpet.

    • Self leveling concrete can be applied in thicknesses ranging from a featheredg...

  • Answered by AI
  • Q5. How many days will take 1st Aluform mockup Concreting
  • Ans. 

    The 1st Aluform mockup concreting typically takes 1-2 days to complete.

    • 1-2 days is the usual timeframe for 1st Aluform mockup concreting

    • Factors such as weather conditions, size of the mockup, and availability of resources can affect the duration

    • Proper planning and coordination can help expedite the process

  • Answered by AI

Interview Preparation Tips

Topics to prepare for Shimizu Senior Site Engineer interview:
  • Construction
  • Structural
  • Quality Control
  • Quality Assurance
  • Bar Bending Schedule
  • Project Execution
Interview preparation tips for other job seekers - Be active and action to learn every step and work hard and smart . Please ensure technical criticis and how it resolve it
Interview experience
5
Excellent
Difficulty level
Easy
Process Duration
2-4 weeks
Result
Not Selected

I applied via Newspaper Ad and was interviewed in Feb 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - Technical 

(1 Question)

  • Q1. About Carriageways, Service Roads and patchwork i.e pot Holes, slippage cracks i.e alligator crack, horizontal or vertical crack, Undulating surface,rain cut, Metals beam crash barrier,Gaurd Rail or Mild s...
Round 3 - Technical 

(3 Questions)

  • Q1. Checking level of the layer
  • Q2. Testing the field dry density of the bed like Sub Grade ,GSB,WMM, DBM or BC
  • Q3. Checking the road width

Interview Preparation Tips

Interview preparation tips for other job seekers - Sir I m very hardworker employee .
I m very panchtual for my job duty and going to site daily and prepare daily progress report and also prepare monthly progress report.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Naukri.com and was interviewed in Apr 2023. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Double-check your resume for any spelling mistakes. The recruiter may consider spelling mistakes as careless behavior or poor communication skills.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. About salary and benefits
Round 3 - One-on-one 

(4 Questions)

  • Q1. About my key activity and responsibility
  • Q2. Process of variation
  • Ans. 

    Process of variation involves documenting and analyzing changes in project scope, cost, or schedule.

    • Variations are changes to the original scope, cost, or schedule of a project

    • Variations must be documented and approved by the relevant parties

    • The impact of variations on project budget and timeline must be analyzed

    • Examples of variations include design changes, unforeseen site conditions, and client requests

  • Answered by AI
  • Q3. Details about TDS
  • Q4. Details about NS items

Interview Preparation Tips

Topics to prepare for The Louis Berger Group Billing Engineer interview:
  • Contact
  • Running bill
  • Escalations
  • Variation
  • Ns items

I applied via Recruitment Consulltant and was interviewed in Mar 2022. There was 1 interview round.

Round 1 - Technical 

(2 Questions)

  • Q1. Explain compressor troubleshooting
  • Ans. 

    Compressor troubleshooting involves identifying and resolving issues with the compressor in a system.

    • Check for leaks in the system

    • Inspect the compressor for damage or wear

    • Check the electrical connections and wiring

    • Monitor the pressure and temperature readings

    • Clean or replace air filters

    • Check the oil level and quality

    • Inspect the belts and pulleys for wear or damage

  • Answered by AI
  • Q2. Prespare well and before interview make sure

Interview Preparation Tips

Interview preparation tips for other job seekers - Prepare well and all types mechanical equipment
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed in Jun 2024. There was 1 interview round.

Round 1 - One-on-one 

(2 Questions)

  • Q1. Tell me about yourself
  • Q2. What do you know about our company

Interview Preparation Tips

Interview preparation tips for other job seekers - they will ask about some finance knowledge and the rest is just a normal interview question
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Campus Placement and was interviewed in Apr 2024. There was 1 interview round.

Round 1 - One-on-one 

(2 Questions)

  • Q1. Where are you from Tell me something about yourself.
  • Ans. 

    I am from a small town in the Midwest and I am passionate about environmental conservation.

    • I grew up in a close-knit community in the Midwest

    • I have always been interested in protecting the environment

    • I enjoy outdoor activities like hiking and gardening

  • Answered by AI
  • Q2. Tell me about education background
  • Ans. 

    I have a Bachelor's degree in Computer Science from XYZ University.

    • Bachelor's degree in Computer Science

    • Graduated from XYZ University

    • Specialized in software development

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - It was an excellent experience for me.

Interview Questions & Answers

Hyundai Engineering user image

posted on 3 Jun 2022

I applied via Walk-in and was interviewed before Jun 2021. There were 3 interview rounds.

Round 1 - Resume Shortlist 
Pro Tip by AmbitionBox:
Keep your resume crisp and to the point. A recruiter looks at your resume for an average of 6 seconds, make sure to leave the best impression.
View all tips
Round 2 - HR 

(1 Question)

  • Q1. Hr department getting test
Round 3 - Technical 

(1 Question)

  • Q1. Technical tèst about our working experience.

Interview Preparation Tips

Interview preparation tips for other job seekers - I am Instrument engineer construction side. I have good knowledge in oil and gas

Oman Shapoorji Llc Interview FAQs

How many rounds are there in Oman Shapoorji Llc Diploma Civil Engineer interview?
Oman Shapoorji Llc interview process usually has 1 rounds. The most common rounds in the Oman Shapoorji Llc interview process are One-on-one Round.
What are the top questions asked in Oman Shapoorji Llc Diploma Civil Engineer interview?

Some of the top questions asked at the Oman Shapoorji Llc Diploma Civil Engineer interview -

  1. MCR building and switch yard questi...read more
  2. Piling work,MMS work, related questi...read more
  3. Reainforment releted questi...read more

Tell us how to improve this page.

Oman Shapoorji Llc Diploma Civil Engineer Interview Process

based on 1 interview

Interview experience

5
  
Excellent
View more
Project Engineer
7 salaries
unlock blur

₹13 L/yr - ₹20 L/yr

Electrical Engineer
7 salaries
unlock blur

₹10 L/yr - ₹12 L/yr

Project Engineer - Civil
7 salaries
unlock blur

₹9.8 L/yr - ₹26 L/yr

Electrical Supervisor
7 salaries
unlock blur

₹4.8 L/yr - ₹12.4 L/yr

Housekeeping Supervisor
6 salaries
unlock blur

₹4 L/yr - ₹8.3 L/yr

Explore more salaries
Compare Oman Shapoorji Llc with

Military Engineer Services

4.4
Compare

The Louis Berger Group

4.3
Compare

Nesma & Partners

4.3
Compare

El Seif Engineering Contracting

4.3
Compare
Did you find this page helpful?
Yes No
write
Share an Interview