Filter interviews by
I applied via Walk-in and was interviewed in Jun 2024. There were 2 interview rounds.
All over about Wind turbine
Top trending discussions
posted on 9 Apr 2024
I applied via Walk-in and was interviewed before Apr 2023. There was 1 interview round.
Gravels are used in switch yards to provide a stable surface for equipment and to improve drainage.
Gravels help in reducing the risk of equipment damage due to flooding or standing water.
They also help in preventing erosion and maintaining the stability of the ground.
Gravels are easy to install and maintain, making them a cost-effective option for switch yards.
They allow for better heat dissipation, which is important ...
A Single Line Diagram (SLD) of a 33/11 kV switchyard shows the layout and connections of electrical equipment.
Key equipments include transformers, circuit breakers, isolators, busbars, surge arresters, and control panels.
Transformers step down voltage from 33 kV to 11 kV for distribution.
Circuit breakers protect the system from overloads and short circuits.
Isolators are used for isolating equipment for maintenance.
Busb...
OC and SC tests are conducted on transformers to determine their efficiency and performance under different load conditions.
OC test (Open Circuit test) is conducted to determine the no-load loss and magnetizing impedance of the transformer.
SC test (Short Circuit test) is conducted to determine the full-load copper loss and equivalent resistance of the transformer.
Both tests help in evaluating the efficiency and voltage...
posted on 5 Aug 2024
I applied via Company Website and was interviewed in Jul 2024. There was 1 interview round.
I chose Electrical Engineering because of my passion for understanding and working with technology.
Fascination with technology and how things work
Interest in problem-solving and innovation
Desire to contribute to advancements in the field
Enjoyment of hands-on projects and experimentation
posted on 2 May 2024
I applied via Walk-in and was interviewed in Jun 2021. There were 7 interview rounds.
JMS stands for Java Message Service, a messaging standard that allows applications to communicate asynchronously.
JMS is a Java-based messaging system used for exchanging messages between two or more clients.
It provides a reliable and flexible way to send messages between distributed systems.
JMS supports both point-to-point and publish-subscribe messaging models.
It uses a message-oriented middleware to handle the commun...
posted on 28 Sep 2021
I applied via Referral and was interviewed before Sep 2020. There was 1 interview round.
posted on 9 Apr 2024
I applied via Walk-in and was interviewed before Apr 2023. There was 1 interview round.
Gravels are used in switch yards to provide a stable surface for equipment and to improve drainage.
Gravels help in reducing the risk of equipment damage due to flooding or standing water.
They also help in preventing erosion and maintaining the stability of the ground.
Gravels are easy to install and maintain, making them a cost-effective option for switch yards.
They allow for better heat dissipation, which is important ...
A Single Line Diagram (SLD) of a 33/11 kV switchyard shows the layout and connections of electrical equipment.
Key equipments include transformers, circuit breakers, isolators, busbars, surge arresters, and control panels.
Transformers step down voltage from 33 kV to 11 kV for distribution.
Circuit breakers protect the system from overloads and short circuits.
Isolators are used for isolating equipment for maintenance.
Busb...
OC and SC tests are conducted on transformers to determine their efficiency and performance under different load conditions.
OC test (Open Circuit test) is conducted to determine the no-load loss and magnetizing impedance of the transformer.
SC test (Short Circuit test) is conducted to determine the full-load copper loss and equivalent resistance of the transformer.
Both tests help in evaluating the efficiency and voltage...
posted on 20 Feb 2024
I applied via Company Website and was interviewed in Jan 2024. There was 1 interview round.
posted on 26 Sep 2019
I applied via Walk-in and was interviewed in Aug 2019. There was 1 interview round.
Power transmission lines carry high voltage power from power plants to substations while distribution lines carry lower voltage power from substations to homes and businesses.
Power transmission lines carry high voltage power over long distances
Distribution lines carry lower voltage power over shorter distances
Transmission lines use high voltage to reduce energy loss during long distance transmission
Distribution lines u...
posted on 31 Oct 2022
based on 3 reviews
Rating in categories
Electrical Engineer
64
salaries
| ₹2.4 L/yr - ₹5.8 L/yr |
Engineer
43
salaries
| ₹3.2 L/yr - ₹5 L/yr |
Senior Engineer
28
salaries
| ₹3.5 L/yr - ₹7.3 L/yr |
Junior Engineer
13
salaries
| ₹2.7 L/yr - ₹4.2 L/yr |
Assistant Manager
7
salaries
| ₹6.6 L/yr - ₹7.8 L/yr |
Suzlon Group
Adani Green Energy
Azure Power
ReNew