I applied via Walk-in and was interviewed in Feb 2023. There were 2 interview rounds.
The Grade of GSB at my previous site was 40 mm.
The Grade of GSB at my previous site was 40 mm.
GSB stands for Granular Sub Base.
The thickness of GSB is usually specified in millimeters.
GSB is a layer of compacted granular material used as a base for asphalt, concrete, or other paving materials.
Tolerances in base and sub-base coarse materials are critical for ensuring proper compaction and stability of the highway.
Tolerances for base coarse typically range from +/- 20mm to +/- 40mm depending on the specified thickness.
Tolerances for sub-base coarse are usually wider, ranging from +/- 50mm to +/- 100mm.
Proper compaction is essential to meet these tolerances and ensure the structural integrity of the highway.
To...
MDD is Maximum Dry Density, FDD is Field Dry Density. MDD is the maximum density achieved by compacting soil in the lab, FDD is the density achieved in the field after compaction.
MDD is determined through laboratory tests using standard compaction methods.
FDD is measured in the field using a nuclear density gauge or sand cone method.
MDD is used to determine the optimum moisture content for compaction.
FDD helps in asses...
Top trending discussions
I applied via Company Website and was interviewed in Oct 2023. There were 5 interview rounds.
Yes, I have 3 years of experience working with G.s.b in highway 3D system (Trimble) as an assistant surveyor on a railway project in Chasma, Gujarat.
Experience working with G.s.b in highway 3D system (Trimble) for 3 years
Currently working as an assistant surveyor at Ashoka Buildcon on a railway project in Chasma, Gujarat
I applied via LinkedIn and was interviewed before Oct 2022. There were 2 interview rounds.
I applied via Naukri.com
According to the topic
Some projects needful for you
Presence of mind
Knowledge of me in this field
posted on 1 Jun 2022
I was interviewed in May 2022.
Crossfall, height of embankment, and type of stability are important factors in highway engineering.
Crossfall refers to the slope of the road surface from the centerline to the edge of the road.
The height of the embankment is the vertical distance between the road surface and the natural ground level.
Stability can refer to the stability of the embankment itself, as well as the stability of the road surface on top of th...
No GD
I was interviewed in Oct 2023.
Yes, I have 3 years of experience working with G.s.b in highway 3D system (Trimble) as an assistant surveyor at Ashoka Buildcon on a railway project in Chasma, Gujarat.
3 years of experience working with G.s.b in highway 3D system (Trimble)
Current job as an assistant surveyor at Ashoka Buildcon
Working on a railway project in Chasma, Gujarat
I applied via Walk-in and was interviewed in Mar 2022. There was 1 interview round.
I applied via Recruitment Consultant and was interviewed in Jan 2021. There was 1 interview round.
Highway Engineer side incharge
Assistant Manager
116
salaries
| ₹4.2 L/yr - ₹12.2 L/yr |
Senior Engineer
85
salaries
| ₹4.1 L/yr - ₹8.5 L/yr |
Assistant Engineer
80
salaries
| ₹2.4 L/yr - ₹4.5 L/yr |
Engineer
64
salaries
| ₹2.5 L/yr - ₹7.5 L/yr |
Structural Engineer
64
salaries
| ₹2.6 L/yr - ₹5.4 L/yr |
Ashoka Buildcon
IRB Infrastructure
Nagarjuna Construction Company
PNC Infratech