I applied via Company Website and was interviewed in Feb 2022. There were 2 interview rounds.
Top trending discussions
posted on 8 Feb 2023
I was interviewed before Feb 2022.
Managing project scope changes and ensuring timely delivery are my biggest challenges.
Managing scope changes and ensuring timely delivery
Balancing competing priorities
Dealing with unexpected issues and risks
Communicating effectively with stakeholders
Ensuring project team is aligned and motivated
posted on 18 Jul 2024
posted on 12 Jul 2024
I applied via Company Website and was interviewed in Nov 2023. There were 2 interview rounds.
I applied via Approached by Company and was interviewed in Dec 2023. There was 1 interview round.
EVM stands for Earned Value Management, a project management technique to measure project performance and progress.
EVM compares the planned work with the actual work completed to determine if a project is on track.
Key EVM metrics include Planned Value (PV), Earned Value (EV), and Actual Cost (AC).
EVM helps in forecasting project outcomes and identifying potential risks.
Formula: EV = % of work completed * BAC (Budget at...
TCPI stands for To Complete Performance Index, a measure of the cost performance required to achieve a specific management goal.
TCPI is calculated as the ratio of the remaining work to be done to the remaining budget available.
It helps project managers assess the efficiency needed to complete a project within budget.
TCPI values greater than 1 indicate that more efficiency is needed to stay within budget, while values l...
I applied via Approached by Company and was interviewed in Mar 2023. There were 2 interview rounds.
The document controller is responsible for managing and organizing documents throughout their lifecycle.
Introduction: Provide a brief overview of your background, experience, and skills relevant to the document controller role.
Pre PO & Post PO: Explain the processes and procedures involved in managing documents before and after purchase orders are issued.
IDC: Describe the importance of an Information and Document Contr...
Engineering documents are created by the engineering team while vendor documents are created by the vendor.
Engineering documents are created by the in-house engineering team while vendor documents are created by the vendor supplying the equipment or materials.
Engineering documents are used for design, construction, and operation of a project while vendor documents are used for procurement and quality control purposes.
E...
I applied via LinkedIn and was interviewed in Aug 2022. There were 2 interview rounds.
I applied via Naukri.com and was interviewed in Jun 2020. There were 4 interview rounds.
posted on 4 May 2019
I applied via Naukri.com and was interviewed in Dec 2018. There were 6 interview rounds.
Senior Engineer
119
salaries
| ₹14 L/yr - ₹49 L/yr |
Process Engineer
95
salaries
| ₹6 L/yr - ₹19.1 L/yr |
Engineer
64
salaries
| ₹6 L/yr - ₹24 L/yr |
Purchasing Specialist
63
salaries
| ₹6.5 L/yr - ₹24 L/yr |
Piping Engineer
50
salaries
| ₹8.9 L/yr - ₹23 L/yr |
Larsen & Toubro Limited
Tata Group
Hindustan Construction Company
Shapoorji Pallonji Group