The critical path is the longest sequence of tasks in a project that must be completed on time in order for the project to finish on schedule.
Identifying the critical path helps in determining the minimum time needed to complete a project.
It consists of tasks that have zero slack or float, meaning any delay in these tasks will delay the entire project.
Activities on the critical path are often marked with a double line ...
I will plan a 50 Mwp project by conducting feasibility studies, creating a detailed project timeline, securing necessary permits, sourcing materials and contractors, and implementing a quality control plan.
Conduct feasibility studies to assess site suitability and potential challenges
Create a detailed project timeline outlining key milestones and deadlines
Secure necessary permits and approvals from local authorities
Sou...
MSP (Microsoft Project) is a project management software developed by Microsoft, while Primavera is a project management software developed by Oracle.
MSP is developed by Microsoft, while Primavera is developed by Oracle.
MSP is more commonly used for smaller projects, while Primavera is preferred for larger and more complex projects.
MSP is known for its user-friendly interface and ease of use, while Primavera is known f...
posted on 28 Feb 2024
I applied via Naukri.com and was interviewed before Feb 2023. There were 4 interview rounds.
Past case study and how you slove it
posted on 2 Feb 2024
I applied via Approached by Company and was interviewed in Aug 2023. There were 3 interview rounds.
posted on 6 Sep 2023
posted on 10 Nov 2023
I applied via Approached by Company and was interviewed in Oct 2023. There were 3 interview rounds.
posted on 6 Aug 2021
I applied via Naukri.com and was interviewed in Jul 2021. There were 4 interview rounds.
The future of electric vehicles in India is promising with government initiatives and increasing demand.
Government incentives and subsidies for electric vehicles
Growing awareness and concern for the environment
Improving infrastructure for charging stations
Introduction of new and affordable electric vehicle models
Shift towards renewable energy sources
Potential for electric vehicles in public transportation
Challenges inc...
I applied via Company Website and was interviewed in Feb 2022. There were 4 interview rounds.
posted on 5 Dec 2024
What is more important product quality and marketing
based on 1 review
Rating in categories
Dhoot Transmission
R.K.M Powergen
SHV Energy
New Allenberry Works