Upload Button Icon Add office photos

Filter interviews by

Protecon BTG Interview Questions, Process, and Tips

Updated 21 Feb 2024

Top Protecon BTG Interview Questions and Answers

View all 7 questions

Protecon BTG Interview Experiences

Popular Designations

5 interviews found

Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Company Website and was interviewed before Feb 2023. There was 1 interview round.

Round 1 - Technical 

(5 Questions)

  • Q1. How to prepare a schedule in P6
  • Ans. 

    To prepare a schedule in P6, start by defining project activities, assigning resources, setting durations, and establishing dependencies.

    • Define project activities with start and finish dates

    • Assign resources to each activity

    • Set durations for each activity

    • Establish dependencies between activities

    • Review and adjust the schedule as needed

  • Answered by AI
  • Q2. What is Progress Measurement System
  • Ans. 

    Progress Measurement System is a method used to track and monitor the progress of a project by measuring completed work against planned work.

    • It involves setting up a baseline schedule to compare actual progress against

    • Progress is measured using various methods such as Earned Value Management (EVM) or milestone tracking

    • It helps in identifying delays, deviations, and areas of improvement in the project

    • Regular progress re...

  • Answered by AI
  • Q3. What is baseline schedule
  • Ans. 

    Baseline schedule is the original project schedule against which actual progress is measured.

    • Baseline schedule is the initial approved project schedule.

    • It serves as a reference point for comparing actual progress and performance.

    • Any changes to the baseline schedule require formal approval and documentation.

    • It includes key milestones, deliverables, and timelines.

    • Example: If a project is scheduled to be completed in 6 mo...

  • Answered by AI
  • Q4. How to prepare MPR
  • Ans. 

    MPR stands for Monthly Progress Report. It is a document prepared by the Planning Engineer to track and report the progress of a project on a monthly basis.

    • Gather data on project progress, including completed activities, milestones achieved, and any delays or issues encountered.

    • Update the project schedule with actual progress and analyze any deviations from the baseline schedule.

    • Include a summary of key performance ind...

  • Answered by AI
  • Q5. How to repare DPR
  • Ans. 

    DPR (Daily Progress Report) can be prepared by collecting daily updates, analyzing progress against plan, and documenting any issues or delays.

    • Collect daily updates from site engineers and subcontractors

    • Analyze progress against the planned schedule to identify any deviations

    • Document any issues or delays encountered during the day

    • Include details of work completed, work planned for the next day, and any resources/materia...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Have good understanding of p6

Top Protecon BTG Planning Engineer Interview Questions and Answers

Q1. How to do planning in primavera
View answer (1)

Planning Engineer Interview Questions asked at other Companies

Q1. Prepare a small given example site schedule with sequencing and duration determine project duration in MSP/on Paper What is critical path method? How will you identify while making on paper rather than MSP? How would you track schedule-Proc... read more
View answer (1)
Interview experience
4
Good
Difficulty level
Moderate
Process Duration
2-4 weeks
Result
Selected Selected

I applied via Walk-in and was interviewed before Feb 2023. There was 1 interview round.

Round 1 - One-on-one 

(1 Question)

  • Q1. 1.Tell me about yourself 2.what is critical path 3.how will you develop Progress measurement sheet 4.What is total float 5.

Interview Preparation Tips

Interview preparation tips for other job seekers - Be Confident
speak clearly

Lead Planning Engineer Interview Questions asked at other Companies

Q1. What is the planning for maintenance, how it is proceed and how to help planning for equipment reliability, availability and plan adherence?
View answer (2)

I applied via Approached by Company and was interviewed in Feb 2022. There was 1 interview round.

Round 1 - Technical 

Interview Preparation Tips

Interview preparation tips for other job seekers - How you can identify EOT and how to convince the message to client

Project Control Manager Interview Questions asked at other Companies

Q1. which Activity having long duration in a network schedule/ project engineering duration
View answer (1)

I applied via Walk-in and was interviewed before Jan 2020. There were 3 interview rounds.

Interview Questionnaire 

9 Questions

  • Q1. Tell me about yourself.
  • Q2. About project management
  • Q3. Total float
  • Q4. Earn value management
  • Q5. CPM & PERT
  • Q6. About previous experience
  • Q7. S- Curve
  • Q8. What is baseline schedule
  • Ans. 

    A baseline schedule is the original project schedule that is used as a reference point for measuring progress and performance.

    • It is the approved version of the project schedule

    • It includes the planned start and end dates for each activity

    • It serves as a benchmark for measuring project performance

    • Changes to the baseline schedule must be approved through a formal change control process

    • It is used to compare actual progress

  • Answered by AI
  • Q9. How to do planning in primavera
  • Ans. 

    Planning in Primavera involves creating a project schedule, assigning resources, and tracking progress.

    • Create a Work Breakdown Structure (WBS)

    • Define activities and their dependencies

    • Assign resources and durations

    • Set baselines and track progress

    • Use filters and reports to analyze data

    • Update the schedule regularly

    • Use risk management techniques

    • Integrate with other software tools

    • Train team members on Primavera

    • Follow industr

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Be confident
Dont Hesitate
Be precise
Remove fear as much you can

Top Protecon BTG Planning Engineer Interview Questions and Answers

Q1. How to do planning in primavera
View answer (1)

Planning Engineer Interview Questions asked at other Companies

Q1. Prepare a small given example site schedule with sequencing and duration determine project duration in MSP/on Paper What is critical path method? How will you identify while making on paper rather than MSP? How would you track schedule-Proc... read more
View answer (1)

Protecon BTG interview questions for popular designations

 Planning Engineer

 (2)

 Management Trainee

 (1)

 Lead Planning Engineer

 (1)

 Project Control Manager

 (1)

I applied via Naukri.com and was interviewed in Jun 2019. There was 1 interview round.

Interview Questionnaire 

2 Questions

  • Q1. What is carpet area, super built up area and built up area?
  • Ans. 

    Carpet area is the actual usable area of a flat, built-up area includes carpet area plus thickness of walls, super built-up area includes built-up area plus common areas.

    • Carpet area is the area within the walls of a flat that can be used for living purposes.

    • Built-up area includes carpet area plus the thickness of walls.

    • Super built-up area includes built-up area plus common areas like lobby, staircase, etc.

    • Carpet area i...

  • Answered by AI
  • Q2. What are your strengths and weaknesses

Interview Preparation Tips

Interview preparation tips for other job seekers - Just be calm, humble and confident while giving your interview.

Management Trainee Interview Questions asked at other Companies

Q1. What do you mean by balance sheet reconciliation could you explain briefly?
View answer (45)

Interview questions from similar companies

I applied via Campus Placement and was interviewed before Jun 2021. There were 2 interview rounds.

Round 1 - Aptitude Test 

Aptitude question and reasoning.

Round 2 - interview 

(1 Question)

  • Q1. Design of a building
  • Ans. 

    Design of a building

    • Determine the purpose and function of the building

    • Consider the site and location

    • Create a preliminary design and get feedback

    • Finalize the design and create detailed plans

    • Ensure compliance with building codes and regulations

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - It is good for all freshers. all the facilities and pay scale are quite good.
Interview experience
5
Excellent
Difficulty level
Moderate
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Company Website and was interviewed before Jan 2023. There were 2 interview rounds.

Round 1 - Technical 

(5 Questions)

  • Q1. What is free float & total float?
  • Ans. 

    Free float is the amount of time a task can be delayed without affecting the project's critical path. Total float is the total amount of time a task can be delayed without delaying the project's completion.

    • Free float is specific to an individual task, while total float is applicable to the entire project.

    • Free float is calculated by subtracting the early start date of a task from the early finish date of its successor t...

  • Answered by AI
  • Q2. What is critival path?
  • Ans. 

    Critical path is the longest sequence of activities in a project that determines the project's overall duration.

    • Critical path consists of activities that have zero slack or float time.

    • Any delay in activities on the critical path will directly impact the project's completion time.

    • Activities on the critical path must be closely monitored and managed to ensure timely project completion.

    • Critical path analysis helps in iden...

  • Answered by AI
  • Q3. What is look ahead and how find 1month look ahead in P6?
  • Ans. 

    Look ahead is a planning technique to anticipate future activities. In P6, the 1-month look ahead can be found using filters and layouts.

    • Look ahead is a proactive planning approach to identify and prepare for upcoming activities.

    • In P6, the 1-month look ahead can be created by applying filters and layouts to the project schedule.

    • Filters can be set to display activities that are scheduled within the next month.

    • Layouts ca...

  • Answered by AI
  • Q4. What is global change?
  • Ans. 

    Global change refers to the long-term alterations in the Earth's systems and processes due to human activities and natural factors.

    • Global change encompasses various interconnected phenomena such as climate change, biodiversity loss, deforestation, and pollution.

    • It involves both anthropogenic (human-induced) factors like greenhouse gas emissions and natural factors like volcanic eruptions.

    • Global change has wide-ranging ...

  • Answered by AI
  • Q5. Productivity rate of a welder ?
  • Ans. 

    The productivity rate of a welder refers to the amount of work they can complete in a given time period.

    • Productivity rate is measured in units of work per hour or per day.

    • Factors that can affect a welder's productivity rate include their skill level, the complexity of the welding task, and the availability of necessary equipment.

    • For example, an experienced welder may have a higher productivity rate than a novice welder...

  • Answered by AI
Round 2 - Assignment 

Asked to prepare a schedule of a building

Interview Questionnaire 

1 Question

  • Q1. Engineering related questions like how to define material volume and weight and density etc..

Interview Preparation Tips

Interview preparation tips for other job seekers - I am in contract base joining job.
Interview experience
4
Good
Difficulty level
Easy
Process Duration
Less than 2 weeks
Result
Selected Selected

I applied via Approached by Company and was interviewed before Mar 2023. There was 1 interview round.

Round 1 - Technical 

(1 Question)

  • Q1. Difference between EPC and Item rate contract.
  • Ans. 

    EPC contract involves Engineering, Procurement, and Construction services provided by a single contractor, while item rate contract involves pricing based on individual items of work.

    • EPC contract is a turnkey solution where the contractor is responsible for the design, procurement, and construction of the project.

    • Item rate contract involves pricing based on specific items of work, with rates predetermined for each item...

  • Answered by AI

Interview Preparation Tips

Interview preparation tips for other job seekers - Prepare ur self before attending

I applied via Referral and was interviewed before Nov 2020. There was 1 interview round.

Interview Questionnaire 

1 Question

  • Q1. Completly about previous experience

Interview Preparation Tips

Interview preparation tips for other job seekers - Just be honest and give your best

Protecon BTG Interview FAQs

How many rounds are there in Protecon BTG interview?
Protecon BTG interview process usually has 1 rounds. The most common rounds in the Protecon BTG interview process are Technical and One-on-one Round.
How to prepare for Protecon BTG interview?
Go through your CV in detail and study all the technologies mentioned in your CV. Prepare at least two technologies or languages in depth if you are appearing for a technical interview at Protecon BTG. The most common topics and skills that interviewers at Protecon BTG expect are Construction, Electronics and Communication, Instrumentation Engineering, Transmission Line and Contract Administration.
What are the top questions asked in Protecon BTG interview?

Some of the top questions asked at the Protecon BTG interview -

  1. What is carpet area, super built up area and built up ar...read more
  2. How to do planning in primav...read more
  3. How to prepare a schedule in...read more

Tell us how to improve this page.

Protecon BTG Interview Process

based on 3 interviews

Interview experience

4.7
  
Excellent
View more

Interview Questions from Similar Companies

Siemens Interview Questions
4.1
 • 416 Interviews
Thermax Limited Interview Questions
4.1
 • 250 Interviews
ABB Interview Questions
4.1
 • 232 Interviews
Havells Interview Questions
4.0
 • 209 Interviews
Tata Power Interview Questions
3.9
 • 161 Interviews
BHEL Interview Questions
4.1
 • 113 Interviews
View all

Protecon BTG Reviews and Ratings

based on 52 reviews

4.4/5

Rating in categories

4.1

Skill development

4.2

Work-life balance

4.1

Salary

4.1

Job security

4.1

Company culture

4.2

Promotions

4.0

Work satisfaction

Explore 52 Reviews and Ratings
Contract Managers ( CTM )

New Delhi

10-15 Yrs

Not Disclosed

Director - Business Development

New Delhi

15-20 Yrs

Not Disclosed

Deputy General Manager (DGM)-Contract Management

New Delhi

15-20 Yrs

Not Disclosed

Explore more jobs
Planning Engineer
28 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Management Trainee
16 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Cost and Planning Engineer
14 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Senior Planning Engineer
13 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Senior Cost and Planning Engineer
6 salaries
unlock blur

₹0 L/yr - ₹0 L/yr

Explore more salaries
Compare Protecon BTG with

Thermax Limited

4.1
Compare

BGR Energy Systems

3.8
Compare

Larsen & Toubro Limited

4.0
Compare

Siemens

4.1
Compare
Did you find this page helpful?
Yes No
write
Share an Interview