Schedule crashing is a technique used in project management to shorten the project duration without changing the scope of work.
Schedule crashing involves adding more resources to critical path activities to reduce their duration.
It may involve working overtime, hiring additional staff, or using more efficient equipment.
The goal of schedule crashing is to meet project deadlines or finish the project earlier than planned...
Top trending discussions
posted on 5 Jun 2024
Optimistic costing involves estimating project costs on the lower end of the spectrum.
Identify all potential cost-saving measures and efficiencies in the project plan.
Use historical data and benchmarks to estimate costs on the lower side.
Consider best-case scenarios and optimistic assumptions when estimating costs.
Collaborate with stakeholders to gather insights and input on cost-saving opportunities.
Regularly review a...
Interview experience
Safety Officer
11
salaries
| ₹3 L/yr - ₹5 L/yr |
Civil Site Engineer
6
salaries
| ₹2.5 L/yr - ₹4.2 L/yr |
Project Engineer
5
salaries
| ₹4 L/yr - ₹6.6 L/yr |
Civil Engineer
5
salaries
| ₹3.2 L/yr - ₹6 L/yr |
Site Engineer
5
salaries
| ₹2.9 L/yr - ₹3.7 L/yr |
Larsen & Toubro Limited
Tata Projects
GMR Group
Hindustan Construction Company