Filter interviews by
I applied via Recruitment Consultant and was interviewed before Oct 2020. There was 1 interview round.
Top trending discussions
posted on 31 Oct 2024
I applied via Naukri.com and was interviewed in Oct 2024. There were 2 interview rounds.
I applied via Recruitment Consulltant and was interviewed in Sep 2024. There was 1 interview round.
The repeated burning of a 22 kW AOP motor CT cable may be due to overloading, short circuits, poor insulation, or incorrect cable sizing.
Check for overloading of the motor causing excessive heat in the cable
Inspect for short circuits in the motor or the wiring
Ensure proper insulation of the cable to prevent overheating
Verify if the cable size is appropriate for the motor's power requirements
Bypassing the CT of an AOP motor can lead to overcurrent and damage to the motor.
Bypassing the CT can result in the motor drawing excessive current.
This can lead to overheating of the motor windings.
Overcurrent can cause damage to the motor components.
It can also pose a safety risk due to potential electrical faults.
posted on 6 May 2024
VFD stands for Variable Frequency Drive, which is a type of motor controller that drives an electric motor by varying the frequency and voltage supplied to the motor.
VFDs are used to control the speed and torque of AC motors in various applications.
They are commonly used in HVAC systems, industrial pumps, conveyor systems, and machine tools.
VFDs can help save energy by adjusting motor speed to match the actual load req...
posted on 19 Apr 2023
I applied via Referral and was interviewed before Apr 2022. There were 2 interview rounds.
I applied via Company Website and was interviewed in Sep 2021. There were 2 interview rounds.
posted on 30 Nov 2019
I applied via Naukri.com and was interviewed in Mar 2020. There were 5 interview rounds.
posted on 11 Apr 2022
I applied via Approached by Company and was interviewed before Apr 2021. There were 2 interview rounds.
posted on 7 Oct 2024
I applied via LinkedIn and was interviewed in Sep 2024. There was 1 interview round.
Synchronisation process of a plant involves matching the frequency, voltage, and phase angle of the incoming generator with the grid.
Ensure the generator frequency matches the grid frequency (50Hz or 60Hz).
Match the voltage levels of the generator with the grid.
Adjust the phase angle of the generator to synchronize with the grid.
Use synchronizing equipment like synchroscope or synchronizing lamps to ensure proper synch...
Alternator and transformer protection systems are essential for preventing damage and ensuring safe operation.
Alternator protection systems typically include overcurrent, overvoltage, and reverse power protection to safeguard the alternator from damage.
Transformer protection systems often involve differential protection, overcurrent protection, and temperature monitoring to prevent overheating and insulation breakdown.
...
posted on 9 Dec 2024
I applied via Naukri.com and was interviewed before Dec 2023. There were 2 interview rounds.
Logical Reasoning, English Quant, Aptitude
Production Engineer
48
salaries
| ₹1.8 L/yr - ₹5 L/yr |
Design Engineer
39
salaries
| ₹1.8 L/yr - ₹6 L/yr |
Assistant Engineer
23
salaries
| ₹2.2 L/yr - ₹3.6 L/yr |
Graduate Engineer Trainee (Get)
18
salaries
| ₹1.4 L/yr - ₹3.2 L/yr |
Engineer
14
salaries
| ₹2.6 L/yr - ₹5.2 L/yr |
Thermax Limited
Tractors and Farm Equipment
Isgec Heavy Engineering
Kirloskar Oil Engines